AI summaryLancashire Combined County Authority approves Skills Hub and UK Shared Prosperity Fund budget amendments, noting a £0.002m forecast overspend at Quarter 1 that increases the planned reserves drawdown to £0.147m.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSkills Hub transfer 1 April 2027, UKSPF grant balance, overspend noted
Money£0.002m forecast overspendIncreases reserves drawdown from £0.145m to £0.147m
What happens nextSkills Hub transfers 1 April 2027Subject to necessary consultations
Who it affectsLCCA services, staff, reservesSkills Hub staff, contractors, Connect to Work, Skills Bootcamps
What was decided
The authority approved two budget amendments: the Skills and Employment Hub transferring in its entirety from Lancashire County Council to the LCCA on 1 April 2027, and adjustments to the UK Shared Prosperity Fund to reflect the remaining grant balance for 2026/27 in both the revenue budget and capital programme. Report P3, P4, P13
The Q1 budget monitoring report was noted, including a forecast revenue overspend of £0.002m that increases the required contribution from reserves for 2026/27 to £0.147m. Report P5, P51
Why
The Adults Skills Fund became a devolved LCCA responsibility on 1 August 2026, but to safeguard delivery and the full transfer of staff, contracts and programmes such as Connect to Work, the wider Skills and Employment Hub will now transfer on 1 April 2027 rather than in-year. Report P13, P23
The LCCA has a legal duty under the Local Government Finance Act 1992 to set a balanced budget, and regular monitoring ensures compliance; members must also have regard to the Chief Finance Officer's advice on the robustness of estimates and adequacy of reserves under section 25 of the Local Government Act 2003. Report P55, P56
The original revenue budget of £53.003m was set in February 2026 on assumptions about transferring services and inflationary pressures, and is expected to fluctuate as the LCCA grows and new government announcements are made. Report P6, P7, P8
What happens next
The Skills and Employment Hub, including Connect to Work and Skills Bootcamps Grants, will transfer to the LCCA on 1 April 2027, subject to the necessary consultations. Report P4, P13, P25
Capital programme values are expected to fluctuate, particularly in relation to transport funding, and any variations will be reported in future budget monitoring reports. Report P30
Future budget monitoring will track pressures on the Central Resourcing staffing and running costs budget as the LCCA expands. Report P27, P28, P59
The money
£53.003m Original approved revenue budget for 2026/27 Report P6, P10
£0.145m Original planned contribution from reserves in 2026/27 Report P6, P10
£0.002m Forecast overspend at Quarter 1, increasing the reserves drawdown Report P5, P19, P51
£0.147m Revised 2026/27 forecast contribution from reserves Report P5, P51
£2.435m Opening balance on the general reserve at 1 April 2026 Report P45, P48
£2.288m Forecast closing balance on the general reserve at 31 March 2027 Report P46, P49
£121.560m Original approved capital programme for 2026/27 Report P30
£123.441m Revised 2026/27 capital programme Report P30, P33
£0.750m Forecast interest income from the Lancashire Investment Fund in 2026/27 Report P10, P42
£25.352m Forecast Adult Skills Fund spend in 2026/27 to March 2027 Report P24
Options considered
Chosen: Transfer the Skills and Employment Hub in its entirety on 1 April 2027 instead of in-year. To avoid jeopardising delivery and ensure full and safe transfer of staff, contracts and programmes such as Connect to Work Report P13
Chosen: Adjust the UK Shared Prosperity Fund budget to reflect the remaining grant balance for 2026/27 Report P4, P30
Implications
Legal: The LCCA has a legal duty under the Local Government Finance Act 1992 to set a balanced budget; section 25 of the Local Government Act 2003 requires members to have regard to the Chief Finance Officer's advice on estimates and reserves. Report P55, P56
Financial: The forecast overspend of £0.002m is covered by an increased drawdown from reserves, leaving a forecast closing general reserve of £2.288m at 31 March 2027. Report P46, P49
Staffing: Staff in the Skills and Employment Hub, including those working on Adult Skills Fund, Connect to Work and Skills Bootcamps, will transfer from Lancashire County Council to the LCCA on 1 April 2027 subject to consultation. Report P13, P25
Other: Officers note a need to consider the capacity of current support service arrangements as the LCCA expands and external governance reviews report. Report P59
Who and where
Lancashire Combined County Authority members and officers Report P2, P55
Staff of the Lancashire Skills and Employment Hub transferring from Lancashire County Council Report P13
Recipients of Connect to Work and Skills Bootcamps programmes Report P13, P25
Constituent councils receiving passported transport grants as accountable body arrangements continue Report P21
More than 180 projects across Lancashire's Unitary and District Councils funded through the UK Shared Prosperity Fund Report P38
Timeline
1 April 2026: LCCA became the Local Transport Authority Report P20
30 June 2026: End of Quarter 1; budget monitoring data as at this date Report P17, P19
1 August 2026: Adults Skills Fund became a devolved LCCA responsibility Report P13, P23
1 September 2026: Start of the 2026/27 Academic Year when ASF transfers into LCCA Report P23
30 September 2026: End of the UK Shared Prosperity Fund Report P38
31 March 2027: Forecast end of 2026/27 financial year; forecast closing reserve balance £2.288m Report P46, P49
1 April 2027: Skills and Employment Hub transfers in its entirety from Lancashire County Council to the LCCA, subject to consultation Report P4, P13
Plain English for the jargon
LCCA: Lancashire Combined County Authority, the devolved authority covering Lancashire
UKSPF: UK Shared Prosperity Fund, a government grant programme supporting local projects
REPF: Rural England Prosperity Fund, capital funding ringfenced for rural projects under UKSPF
ASF: Adult Skills Fund, devolved to the LCCA from 1 August 2026
LEVI: Local Electric Vehicle Infrastructure grant
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12
Resolved
That i. The following budget amendments as listed below and detailed in the report, be approved: a. Skills Hub transfer to the LCCA 1 April 2027; and b. UK Shared Prosperity Fund (UKSPF) to reflect remaining grant balance for 2026/27 (revenue budget and capital programme). ii. The LCCA 2026/27 Budget Monitoring Report as at Quarter 1 be noted, including the forecast overspend of £0.002m, which resulted in an increase to the required contribution from reserves, making the 2026/27 forecast contribution £0.147m.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
This report presents a summary of 2026/27 budget performance as at the end of Quarter 1 and includes proposed budget amendments that have arisen to date.
Recommendations
The Lancashire Combined County Authority is asked to:
(i) Approve the budget amendments as listed below and detailed in the report:
• Skills Hub transfer to the LCCA 1 April 2027 • UK Shared Prosperity Fund (UKSPF) to reflect remaining grant balance for 2026/27 (revenue budget and capital programme), and
(ii) Receive the LCCA 2026/27 Budget Monitoring Report as at Quarter 1, noting a forecast overspend of £0.002m, resulting in an increase to the required contribution from reserves, making the 2026/27 forecast contribution £0.147m. 2026/27 REVENUE BUDGET
1. The original revenue budget of £53.003m with a planned contribution from the reserve of £0.145m was approved by the LCCA on 17 February 2026 as set out in Table 1.
2. The 2026/27 financial year represents the second year of the LCCA's operation and, as such, is a period of significant budget growth as additional functions transfer to the Authority's responsibility. Consequently, the original Revenue Budget proposed and approved was based on a number of key assumptions relating to these transferring services, together with future pressures and commitments, including inflationary uplifts.
3. It is expected that the budget position will fluctuate during 2026/27, as the LCCA continues to develop and grow, and as any new Government announcements are made.
Table 1: Original Approved Revenue Budget 2026/27
Budgeted Budgeted Net Revenue Income Budget Revenue Service Expenditure Expenditure £m £m £m Transport 22.807 (22.708) 0.099 Skills Hub 28.681 (28.576) 0.105 Economic Growth 0.639 (0.435) 0.204 Central Resourcing 0.877 (0.390) 0.487 Sub -Total 53.003 (52.109) 0.895 Financing (0.750) (0.750) Contribution from Reserves (0.145) (0.145) Revenue Budget 2026/27 53.003 (53.003) 0
Budget Adjustments
4. The budget is continually being reviewed and updated so that it remains relevant and accurately reflects the range and timing of existing or future functions of the LCCA.
5. The Adults Skills Fund became a devolved responsibility of the LCCA with effect from 1 August 2026 as originally planned and is being managed by the existing Lancashire Skills and Employment Hub as covered under a separate item on the agenda. However, as not to jeopardise delivery and to ensure the full and safe transfer of all staff and all other contracts and programmes, such as Connect to Work, it is proposed that the Skills and Employment Hub will transfer in its entirety from Lancashire County Council to the LCCA on 1 April 2027, subject to the necessary consultations, as opposed to an in-year transfer as originally budgeted. Table 2 shows the required budget amendments. Table 2: Skills Hub Budget Amendments in 2026/27
Original Revised Reason for Budget Movement Budget Budget Budget Adjustment £m £m £m Skills Employees and ASF grant funded roles and 1.056 0.620 (0.436) Expenses administrative costs Grants 27.625 24.837 (2.788) Reprofiled transfer of grants Sub -Total 28.681 25.457 (3.223) Grant Income (28.576) (25.352) 3.223 Net Expenditure 0.105 0.105 0.000
Forecast Outturn at Quarter 1
6. Expenditure has been made against various budget headings both through the LCCA finance ledger and through constituent council financial systems reflecting the corporate services being provided to the LCCA, such as payroll services.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Lancashire Combined County Authority at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.