Budget and Policy Framework 2010/11 - Corporate Plan

Agreed Executive 2 papers

Cabinet agreed this item on Tuesday 16 March 2010. Below is the council's own wording, with the papers it was decided on.

Item144

Resolved

Resolved unanimously: (1) That provision be made within the new Community Engagement Service to progress the Council’s work on the Equalities Framework for Local Government. (2) That ideas for key targets and key actions be fed to the Leader and the Corporate Director (Finance and Performance), to be drafted into the Corporate Plan. (3) That an informal meeting of Cabinet Members be arranged to agree the revised draft. Officers responsible for effecting the decision: Corporate Director (Finance and Performance) Head of Corporate Strategy Reasons for making the decision: The Corporate Plan is the cornerstone of the Council’s Policy Framework and effectively links the council’s service delivery aspirations to its spending plans included in the budget and capital programme. It is essential that the Council agrees its Corporate Plan in good time to provide a clear framework for officers to work within.
Word for word from the decision Lancaster published for this meeting. Source: committeeadmin.lancaster.gov.uk

Follow this further

Built from Lancaster's papers

What the report saysPro

Report to Cabinet

Purpose of report

To present to Cabinet a first draft of the Corporate Plan for the 3 year period commencing 2010/11 and seek any amendments

Key Non-Key Decision Referral from Officers Decision X Date Included in Forward Plan N/A This report is public.

OFFICER RECOMMENDATIONS

(1) That Cabinet considers the draft Corporate Plan for 2010/11 onwards and makes amendments as appropriate.

(2) That Cabinet agrees a process for making further changes to the draft Plan with a view to making recommendations to Council in April 2010 for approving the Plan.

1 Introduction

1.1The Corporate Plan brings together the Council’s strategic priorities and objectives that it wishes to deliver in the medium term. It is not just an annual plan - its content drives the allocation of resources that are included in the Council’s medium term budgets and capital programme, and related service business plans.

1.2At the last Cabinet meeting, minute 134 refers, it was agreed that Cabinet’s revised 4 draft corporate priorities for the 3 year period beginning 2010/11 should be used as the basis for developing a refreshed Corporate Plan. These priorities had been included in the recent public consultation exercise and had been developed and informed from a variety of sources that included the recent Comprehensive Area Assessment, Place Survey data, performance management information for the current year, and other feedback from service users and partners. Minute 134 is set out below.

(1) That Cabinet notes the information and feedback from consultees and other sources regarding its draft corporate priorities and approves the 4 priorities included in Appendix A of the report, as the basis for drafting the 2010/11 Corporate Plan. (2) That the 2010/11 draft Corporate Plan be considered further at Cabinet’s March meeting prior to referral on to Council in April.”

1.3The 4 draft corporate priorities are set out below and these have been included in a first draft of the Corporate Plan which is currently being prepared and which will be circulated as Appendix A prior to the meeting.

• Economic Regeneration –Supporting out local economy

• Tackling Climate Change

• Meeting Our Statutory Responsibilities

• Working In Partnership

2 Proposal Details

2.1At this stage the Plan only provides a framework of what will be included and much work still has to be undertaken before a finished version can be agreed and formally signed off by Council.

However, the results of the public consultation did encourage Cabinet to ensure that the priorities were clear and focused so that people could understand what each priority meant. Consequently, Cabinet needs to consider the current wording included for each priority and determine if and where changes need to be made. This is essential before the next stages of developing key targets, actions, and projects can be completed.

2.2Cabinet is therefore asked to consider the draft Corporate Plan at Appendix A ( to be sent out under separate cover) and agree any changes to enable the next stages to be completed.

2.3Cabinet will also be mindful of the need to complete the Plan in good time and are therefore also asked to consider how further changes will be made to the document following Cabinet if a version is to be presented to Council on 14th April 2010.

3 Options and Options Analysis (including risk assessment)

Option 1

That the Cabinet considers the Corporate Plan as set out in Appendix A, makes any changes as appropriate, and determines a process for agreeing any further changes prior to presenting to Council in April.

Option 2

That Cabinet determines an alternative course of action to prepare the Corporate Plan than that recommended in Option 1 above.

The preferred option is option 1 as it would provide a process for ensuring that Cabinet could agree a version of the Corporate Plan to refer to full Council in April. 4 Consultation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget and Policy Framework 2010/11: Corporate PlanReport 19 KB DownloadRead as text
PDF
Draft Corporate Plan 10-13 V2Report 45 KB Download

At this meeting

Whole meeting

On this subject at Lancaster

Search all
  1. Budget and Policy Framework 2010/11 - Corporate PlanThis decision
  2. Budget and Policy Framework 2026/27 - 2030/31Approved
  3. Budget and Policy Framework General Fund Revenue Budget 2026/27 - 2030/31Approved
  4. Budget and Policy Framework Update 2026/27 to 2030/31Approved
  5. Budget and Policy Framework Update 2026/27 to 2030/31Noted
  6. Budget and Policy Framework Update 2026/27 to 2030/31Decided

More from Lancaster Cabinet

All decisions
MeetingDecisionOutcome
28 Jul 2026 Provisional Revenue, Capital and Treasury Management Outturn 2025/26Resolved unanimously: (1) That the provisional outturn for 2025/26 be endorsed, including the transfers to and from R... Approved Open
28 Jul 2026 Exclusion of the Press and PublicResolved unanimously: That in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and publi... Decided Open
7 Jul 2026 Exclusion of press and publicResolved unanimously: (1) That, in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and ... Decided Open
9 Jun 2026 Reports from Overview and Scrutiny(8 Members (Councillors Bannon, Bottoms, Hart, Caroline Jackson, Peter Jackson, Riches, Stubbins & Tyldesley) voted i... Approved Open
9 Jun 2026 Appointments ReportResolved unanimously: That the appointments to outside bodes and partnerships as appended to the report be confirmed ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies