CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Lancaster City Council
Cabinet, Tuesday 13 March 2012

Referral from Audit Committee - Council Housing RMS Partnering Contract

Decided Executive 1 paper

Cabinet decided this item on Tuesday 13 March 2012. Below is the council's own wording, with the papers it was decided on.

Item104

Resolved

(7 Members (Councillors Blamire , Bryning , Hamilton-Cox, Hanson, Leytham , Sands and Smith) voted in favour, 1 Member (Councillor Barry) abstained. (1) That Cabinet note that having considered a detailed report and having had the opportunity to raise concerns with officers at the meeting, Audit Committee Members were satisfied that sufficient assurance had been provided regarding the RMS partnering contract and the outcome of the Hala Flats pebbledashing project, and that no further action or analysis was recommended to Cabinet. (2) That Cabinet note that the Internal Audit Manager would liaise with managers to develop an action plan arising from the report and that progress would be reported to a future meeting of the Audit Committee in accordance with established procedures. Officers responsible for effecting the decision: Internal Audit Manager Reasons for making the decision: The report addresses the concerns raised by Cabinet at its meeting on 6 December 2011 (Minute 67 refers) and provides for progress reports to the Audit Committee.
Word for word from the decision Lancaster published for this meeting. Source: committeeadmin.lancaster.gov.uk

Follow this further

Built from Lancaster's papers

What the report saysPro

Report to Cabinet

Purpose of report

To request Cabinet to consider a recommendation from the Audit Committee in relation to the Council Housing RMS partnering contract and the Hala Flats pebbledashing project.

Key Decision Non-Key Decision Referral from Audit Committee x This report is public

RECOMMENDATION OF AUDIT COMMITTEE

(1) That having considered in detail a report to Audit Committee, and having had the opportunity to raise concerns with officers at the meeting, Members are satisfied that sufficient assurance has been provided regarding the RMS partnering contract and the outcome of the Hala Flats pebbledashing project, and that no further action or analysis is recommended to Cabinet.

(2) That the Internal Audit Manager liaise with managers to develop an action plan arising from this report and that progress be reported to a future meeting of the Audit Committee in accordance with established procedures.

1.0Introduction

1.1At its meeting on 6th December 2011 Cabinet considered a report by the Head of Environmental Services which provided information on the Council Housing Planned Maintenance Partnering arrangement. 1.2 The report was for noting and comment and provided information on:-  Experience of partnering to date  Hala rendering project  Leaseholder issues 1.3 It was noted that an internal audit report into the partnering agreement was due to be considered by the Audit Committee in January 2012. 1.4 Cabinet resolved: That Cabinet notes the report and requests that the Audit Committee look more closely at the Hala project specifically and this may entail the need for expert independent advice with regard to the pricing of the Hala project. 2.0 Report

2.1In light of this resolution, internal audit undertook further work in connection with the Hala flats rendering project and produced a second report which was submitted to Audit Committee on 15th February 2012, the meeting scheduled for 18th January 2012 having been postponed. 2.2 The Internal Audit Manager’s report, produced jointly with the Head of Environmental Services, sought to address those questions raised by Cabinet as well as further questions raised by Budget and Performance Panel Members, and points raised by other Councillors following the issuing of the initial internal audit report. . The agenda item and report is available for online viewing via the Mod.Gov system. 2.3 At the meeting on 15th February 2012, members of the Audit Committee considered an in-depth presentation of the internal audit report’s findings and conclusions in the following areas:  The form of partnering contract used;  Pricing and payment mechanisms;  The Hala pebbledashing project and leaseholder charges;  Training;  Quality of work;  Preliminary costs; and  Benefits of the partnership. 2.4 Following discussion, the Committee resolved as follows: (1) That, having considered the report and appendices in detail, and having had the opportunity to raise concerns with officers at the meeting, Members are satisfied that sufficient assurance has been provided regarding the RMS partnering contract and the outcome of the Hala Flats pebbledashing project, and that no further action or analysis be recommended to Cabinet. (2) That the Internal Audit Manager liaise with managers to develop an action plan arising from this report and that progress be reported to a future meeting of the Audit Committee in accordance with established procedures. 2.5 A copy of the Audit Committee’s full draft minute is attached to this report as Appendix A.

RELATIONSHIP TO POLICY FRAMEWORK

Not applicable

CONCLUSION OF IMPACT ASSESSMENT (including Diversity, Human Rights, Community Safety, Sustainability and Rural Proofing)

None identified in relation to this report FINANCIAL IMPLICATIONS

None directly arising from this report

SECTION 151 OFFICER’S COMMENTS

The Section 151 Officer has been consulted and has no further comments.

None arising from this report

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Referral from Audit Committee: Council Housing RMS Partnering ContractReport 104 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Lancaster

Search all
  1. Referral from Audit Committee - Council Housing RMS Partnering ContractThis decision
  2. Referral from Audit Committee – Length of MeetingsApproved

More from Lancaster Cabinet

All decisions
MeetingDecisionOutcome
28 Jul 2026 Provisional Revenue, Capital and Treasury Management Outturn 2025/26Resolved unanimously: (1) That the provisional outturn for 2025/26 be endorsed, including the transfers to and from R... Approved Open
28 Jul 2026 Exclusion of the Press and PublicResolved unanimously: That in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and publi... Decided Open
7 Jul 2026 Exclusion of press and publicResolved unanimously: (1) That, in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and ... Decided Open
9 Jun 2026 Reports from Overview and Scrutiny(8 Members (Councillors Bannon, Bottoms, Hart, Caroline Jackson, Peter Jackson, Riches, Stubbins & Tyldesley) voted i... Approved Open
9 Jun 2026 Appointments ReportResolved unanimously: That the appointments to outside bodes and partnerships as appended to the report be confirmed ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies