- (6 Members voted in favour ( Councillors Eileen Blamire, Janice Hanson, Tim Hamilton-Cox, Karen Leytham, Ron Sands and David Smith ) and 1 Member voted against (Councillor Barry). That the Chief Executive be asked to request the Mayor to allow the matter to be considered as an item of urgent business at the meeting of Council to be held on 18 th July 2012. Officers responsible for effecting the decision: Chief Executive. Head of Financial Services (Resources). Reasons for making the decision: On the basis that the available options were to do nothing (option 1), which would not require any actual decision, or to proceed with option 2, which would require Council approval, and because of the urgency of the matter, Cabinet resolved to ask the Chief Executive to request the Mayor to allow the matter to be considered as an item of urgent business at the meeting of Council to be held on 18 th July 2012. This would enable Council to proceed with Option 2 should it be so minded.
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
EXTRACT FROM CABINET MINUTES – MINUTE 26 - STOREY CREATIVE INDUSTRIES CENTRE
Cabinet Member with Special Responsibility Councillor Hanson)
Cabinet received a report from the Chief Executive to provide an update on the Storey Creative Industries Centre (SCIC) Ltd’s current financial position and to determine the way forward regarding the Council’s involvement in the Centre. An exempt version of the report that included commercially sensitive information had been produced to support Cabinet’s decision-making.
The options, options analysis, including risk assessment and officer preferred option, were set out in the report as follows:
OPTIONS FOR THE WAY FORWARD
The way forward therefore depended on whether the Council wished to provide a creative industries centre or whether it wished to pursue an alternative future for the building.
In terms of the Council’s Corporate Plan, there was nothing specific regarding the continuation of a creative industries centre although having a successful operation could contribute to:
− maximising the district’s cultural offer − increasing participation in arts, culture and entertainment events.
The Council has committed to working with the Duchy to consider options for the long term use of Lancaster Castle. The Storey building occupies a prominent position and in future there may be other potential avenues to be explored regarding its use.
The Council still had service level agreements in place with Litfest and the Storey Gallery but these placed no obligations on the Council in connection with the Storey building itself.
Options for consideration were as follows: Option1 Withdraw support for the Storey being used as a creative industries centre, and request a report back on all future options for the building.
Advantages Disadvantages Risks
Avoids the need to set up Loss of creative industries At a strategic level, there is a risk management arrangements centre and any spin off that an acceptable future alternative and other work involved, as benefits for the local use (or disposal) of the building well as the risks attached in economy or community. could not be identified or secured taking on the running of the and this would exacerbate the facility. Major disruptions for various substantial financial, existing tenants, including reputational and operational risks Allows consideration and VIC potentially. that exist whichever option is development of alternative chosen. uses for the building in Likely short to medium term future. Such options and operational implications and any opportunities may be difficulties subject to influenced by the future reaction of current tenancy plans for Lancaster Castle. base, until such time the council is able to gain vacant possession.
No clear alternative use of building at present. It would be empty (or virtually so) for a period at least.
Involves formal legal action, which could be protracted and would tie up staff resources, as would development of alternatives for the building. This would have adverse impact on other workloads and priorities.
Option 2 Continue to support the Storey being used as a creative industries centre but under the Council’s direct management and control, authorising the Chief Executive to take actions as necessary, prior to reporting back to Cabinet.
Advantages Disadvantages Risks
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Press and PublicResolved unanimously: That in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and publi...
Reports from Overview and Scrutiny(8 Members (Councillors Bannon, Bottoms, Hart, Caroline Jackson, Peter Jackson, Riches, Stubbins & Tyldesley) voted i...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.