Resolved unanimously: (1) That, subject to receiving an offer of grant from the Environment Agency, the Chief Officer (Regeneration & Planning) be given delegated authority to accept the offer in order to fund the works as described, subject to agreement with the Chief Officer (Resources) and there being no further impact on City Council resources than those set out in the report. (2) That, subject to receipt of the grant, approval be given to appoint suitably experienced local contractors to carry out the works, in accordance with the City Council’s contract procedure rules. (3) That subject to (1) above, the Chief Officer (Resources) be given delegated authority to update the General Fund Revenue and Capital Budgets accordingly, to allow the works to progress. Officers responsible for effecting the decision: Chief Officer (Regeneration & Planning) Chief Officer (Resources) Reasons for making the decision: The decision was consistent with the Clean, Green and Safe Places corporate priority (maintaining standards of flood protection) and with the Health and Wellbeing corporate priority (minimising the risk of flooding) and was indicative of the key theme which underpinned the Council’s priorities: to manage the Council’s resources efficiently and effectively.
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
Grant assisted alleviation of shingle migration and flooding, Teal Bay, Morecambe.
Cabinet, 23 July 2013
Report of Head of Regeneration and Planning PURPOSE OF REPORT
To highlight the problems with the Bare Beck outfall at Scalestones Point in Morecambe and to inform Members of a potential offer of grant funding from the Environment Agency to help rectify the situation and reduce the risk of flooding for nearby properties.
Key Decision Non-Key Decision Referral from Cabinet X Member Date of notice of forthcoming Monday 24th June key decision This report is public
RECOMMENDATIONS OF Cllr Janice Hanson.
(1) That subject to receiving an offer of grant from the Environment Agency the Head of Regeneration & Planning be given delegated authority to accept the offer in order to fund the works as described, subject to agreement with the Head of Resources and there being no further impact on City Council resources than those set out in this report.
(2) That, subject to receipt of the grant, approval is given to appoint suitably experienced local contractors to carry out the works, in accordance with the City Council’s contract procedure rules.
(3) That subject to (1) above, the Head of Resources be given delegated authority to update the General Fund Revenue and Capital Budgets accordingly, to allow the works to progress.
1.0Introduction
The section of coastal defences abutting the A5105 to the east of Scalestones Point, Morecambe, comprises a sloping concrete revetment that has been protected by two forms of new construction. Across the eastern half of the frontage the wall has been protected by a rock armour revetment, which terminates in a rock groyne adjacent to the VVV Leisure complex. On the western part of the frontage a shingle beach has been imported to reinforce the defence. This continues up to the Scalestones Point rock groyne.
Towards the eastern end of the rock armour a 1.2m diameter land drainage discharge, which drains the golf course and housing developments to the rear of Happy Mount Park, has been extended through the rock armour and terminates at the toe of the rock revetment.
Problem Definition The shingle beach on the western part of frontage is mobile with the drift taking place from west to east. Since the recharge took place in 2008, the shingle has migrated easterly across the foreshore in front of the main revetment, eventually ending up in front of the outfall where it has blocked the flap valves preventing them from opening (see photo) This causes flooding along the length of the open ditch initially affecting the golf club and then extending into the housing area to the rear of Happy Mount Park. Over the last few months the shingle build up in front of the outfall has been periodically removed by excavation. It has not always been possible to act quickly due to the difficulty of current access arrangements and availability of specialist contract plant.
This behaviour is having two major effects:
• Over time more shingle is being moved into the armour section of frontage, requiring more frequent clearance from in front of the outfall to maintain drainage and prevent backing up. • Shingle is being lost from the westerly section of frontage reducing the standard of protection being provided here. Outfall when blocked with 8 tonnes of shingle after a spring/ rough high tide. Bare Beck outfall after clearance.
2.0Proposal Details
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Press and PublicResolved unanimously: That in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and publi...
Reports from Overview and Scrutiny(8 Members (Councillors Bannon, Bottoms, Hart, Caroline Jackson, Peter Jackson, Riches, Stubbins & Tyldesley) voted i...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.