CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Lancaster City Council
Cabinet, Tuesday 15 April 2014

Funding for Wave Reflection Wall Replacement

Decided Executive 1 paper

Cabinet decided this item on Tuesday 15 April 2014. Below is the council's own wording, with the papers it was decided on.

Item103

Resolved

Resolved unanimously: (1) That delegated authority be given to the Chief Officer (Resources) to accept the grant offer from the Environment Agency (EA) to enable reconstruction of the Wave Reflection Wall (WRW) from Happy Mount Park to the Town Hall when received. (2) That delegated authority be given to the Chief Officer (Resources) to accept further grant offers from the EA for future phases of WRW reconstruction as and when received. (3) That the Chief Officer (Resources) be authorised to make the necessary adjustments to the General Fund Capital Programme and General Fund Revenue Budget, subject to there being a nil impact on the Council’s resources. (4) That existing resources be redirected to fund an additional engineering post as set out in the report. Officers responsible for effecting the decision: Chief Officer (Regeneration & Planning) Chief Officer (Resources) Reasons for making the decision: The decision is consistent with two Corporate Priorities namely; Health and Wellbeing and Clean, Green and Safe Places. The offer of funding from the EA enables the City Council to maintain an extremely important asset which provides flood protection to approximately 12,000 properties within the town. The proactive maintenance of this important infrastructure shows the City Councils commitment to regeneration in Morecambe.
Word for word from the decision Lancaster published for this meeting. Source: committeeadmin.lancaster.gov.uk

Follow this further

Built from Lancaster's papers

What the report saysPro

Report to Cabinet

CABINET

Funding for the Wave Reflection Wall Replacement 15th April 2014

Report of Chief Officer (Regeneration and Planning) PURPOSE OF REPORT

To enable Cabinet to consider the acceptance of grant offers from the Environment Agency to replace the existing Wave Reflection Wall, and the establishment of an additional engineering post.

Key Decision Non-Key Decision Referral from Cabinet X Member Date of notice of forthcoming key decision 10 February 2014 This report is public

RECOMMENDATIONS OF Councillor Janice Hanson

(1) That delegated authority be given to the Chief Officer (Resources) to accept the grant offer from the Environment Agency (EA) to enable reconstruction of the Wave Reflection Wall (WRW) from Happy Mount Park to the Town Hall when received.

(2) That delegated authority be given to the Chief Officer (Resources) to accept further grant offers from the EA for future phases of WRW reconstruction as and when received.

(3) That the Chief Officer (Resources) be authorised to make the necessary adjustments to the General Fund Capital Programme and General Fund Revenue Budget, subject to there being a nil impact on the Council’s resources.

(4) That existing resources be redirected to fund an additional engineering post as set out in the report.

1.0Introduction Wave Reflection Wall

1.1The wave reflection wall was built during the period 1981 to 1986 following the major storm and flooding events in 1977 and 1983. Because of the intrusive nature of this wall a great deal of effort was put into an exposed aggregate finish on the landward side of the wall. Unfortunately despite the best advice available at the time the selection of materials in the concrete mix gave rise to alkali-silica reaction in the concrete which has caused extensive cracking limiting its serviceable life. Whilst further improvements to the coastal defences have subsequently been constructed in the form of rock armour, breakwaters and imported beach material the wave reflection wall remains as an essential part of the overall flood defence. As a substantial portion of the town of Morecambe is below the highest attainable tide levels during storm events it is imperative to undertake a programme of replacement of this element of the coastal defences to maintain the current level of protection from flood risk.

1.2Recent events on the 5th December and early January have emphasised the importance of this element of our sea defences. The town was protected from flooding during these events from the combination of sea defences built over the last 30 years including the WRW. The deteriorating condition of the existing wall WRW necessitates a planned replacement to ensure the continued protection that Morecambe needs from these extreme events.

1.3The engineering section within Regeneration and Planning has been working with consultants to bid for funds to replace the entire length of wave reflection wall. A Project Appraisal Report (PAR) has been submitted to the Environment Agency (EA) proposing a project estimated at £9.9m for the total replacement of the Wave Reflection Wall. This has now been approved by their local Project Appraisal Board and funding for the scheme is now shown in the EA allocated funding for 2014-15 and also within their indicative funding over the next five years for the remainder of the approved project. The first stage programmed for 2014-2015 is Bare to Lord Street with a funding allocation of £1.96m with £1.3m allocated by the EA for 2014-15.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Funding for Wave Reflection Wall ReplacementReport 87 KB DownloadRead as text

At this meeting

Whole meeting

More from Lancaster Cabinet

All decisions
MeetingDecisionOutcome
28 Jul 2026 Provisional Revenue, Capital and Treasury Management Outturn 2025/26Resolved unanimously: (1) That the provisional outturn for 2025/26 be endorsed, including the transfers to and from R... Approved Open
28 Jul 2026 Exclusion of the Press and PublicResolved unanimously: That in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and publi... Decided Open
7 Jul 2026 Exclusion of press and publicResolved unanimously: (1) That, in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and ... Decided Open
9 Jun 2026 Reports from Overview and Scrutiny(8 Members (Councillors Bannon, Bottoms, Hart, Caroline Jackson, Peter Jackson, Riches, Stubbins & Tyldesley) voted i... Approved Open
9 Jun 2026 Appointments ReportResolved unanimously: That the appointments to outside bodes and partnerships as appended to the report be confirmed ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies