Resolved unanimously: (1) That the schedule of capital works set out in Table 1 of the report for progression during 2014/15 be approved, on the basis set out in the report. Officer responsible for effecting the decision: Chief Officer (Resources) Reasons for making the decision: The decision seeks to ensure that the Council’s property portfolio is fit for purpose in terms of supporting the ... view the full minutes text for item 27.
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
Corporate Non-Housing Property Portfolio Improvement Works: Year 2 Delivery Plan
29th July 2014
Report of Chief Officer (Resources)
PURPOSE OF REPORT As the Council moves into the second year of the Corporate Non-Housing Property Portfolio Improvement Works, a draft year two delivery plan has now been formulated for Cabinet’s approval in line with the basic programme originally supported by Cabinet (22 January 2013).
Key Decision Non-Key Decision Referral from Cabinet X Member
Forthcoming Key Decision Notice 24th June 2014 This report is public.
RECOMMENDATIONS OF COUNCILLOR HAMILTON COX:
(1) That Cabinet approves the schedule of capital works set out in Table 1, for progression during 2014/15 on the basis set out in the report.
1 Introduction and Background
1.1As a direct result of the comprehensive condition surveys undertaken by Property Group during 2012, the principles of the corporate property (non-housing) five year delivery programme were approved by Cabinet at its meeting back in January 2013.
1.2The Year One Delivery Programme predominantly focussed upon the prioritisation of category D repairs or urgent works that could lead to serious building failure. Progress on this work undertaken during 2013/14 was reported on a quarterly basis by way of the Property Group Quarterly Update Reports.
1.3This report sets out the proposed year two delivery programme and delivery arrangements for approval
2 Year Two Delivery Programme
2.1As the year one delivery programme focussed on the category D needs, the most urgent works are now dealt with or in hand, so the rationale behind development of the year two delivery programme has been to select buildings with a secure future and complete the category A – C works. The following table summarises the property works prioritised for delivery in year two (2014/15). Table One: Year Two (2014/15) Delivery Programme
Indicative Property General Work Type Costs
Maritime Museum & 26 S Georges Quay Structural & building works, £105K (mechanical & electrical works, sanitary works).
The Storey Building Lancaster – Phase 2 Structural & building works, (floors, £198K stairs, internal walls & doors, sanitary works).
Lancaster Williamson Park Phase 2 Structural & building works £250K identified to external areas and buildings throughout the park, bridge over the lake, toilet blocks, shelters, dell and perimeter walls. Identified works include paving, rebuilding/re-pointing stone and brickwork, ironworks, gates fence replacement, roof works to shelters Ashton Memorial – Internal & External Works Structural & building works, £324K (external doors & windows, other ceilings, electrical works).
Ashton Memorial – Paving Restoration Structural & building works £260K (external paving around memorial).
Ashton Memorial -Dome Ceiling Restoration(1) Structural & building works £100K (internal works: ceilings).
Lancaster Town Hall – Replacement Lift Mechanical services (lift £133K replacement & building).
Lancaster Town Hall – Electrical & Building Electrical & building works (first, £250K Lancaster Town hall – Banqueting Ceilings (2) ground & basement floor £100K building works, ceiling restoration, insulation, & electrical works)
Intermediate Demolition Contract Structural demolition works to £58K Ryelands Park Pavilion, Bubbles Toilet Block & Palatine Rec Buildings.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Press and PublicResolved unanimously: That in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and publi...
Reports from Overview and Scrutiny(8 Members (Councillors Bannon, Bottoms, Hart, Caroline Jackson, Peter Jackson, Riches, Stubbins & Tyldesley) voted i...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.