(1) That outline Planning Permission be granted with the following conditions: 1. Standard outline condition with all matters reserved 2. Drawings illustrative only (in particular the delineation of the PROW) 3. Height of the dwelling limited to two storeys only 4. Design principles of the dwellings as set out in the Noise and Vibration Statement 5. Highway design to be agreed 6. Visibility splays (including speed survey) to be determined and provided 7. Access design and construction to be agreed 8. Completion of approved access arrangements 9. Provision of a Construction Method Statement and undertaking in accordance with agreed scheme 10. Hours of Construction 11. No vegetation clearance works, demolition work or other works that may affect nesting birds should take place between 1st March and 31st August inclusive, unless surveys by a competent ecologist show that nesting birds would not be affected. 12. Scheme for the disposal of foul and surface 13. No tree/hedges within the site or on any immediately adjacent property or land shall be cut-down, up-rooted, topped, lopped or destroyed, nor any hedge within the site cut-down or grubbed out, other than those identified within the approved application, without the prior written approval of the local planning authority and before any site activity is commenced in association with the development. 14. Submission of a tree protection plan 15. Site landscaping to be agreed 16. No impact pile driving, except in accordance with a scheme for noise control 17. Finished floor and site levels
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
Land At Outline application for the development of up to 6 Carnforth Brow residential dwellings Carnforth Lancashire
Name of Applicant Name of Agent
[name removed] Richard Riall
Decision Target Date Reason For Delay
15 October 2014 Referral back to committee following a change in national planning policy
Case Officer [name removed] No
Summary of Recommendation Approval subject to conditions
(i) Procedural Matters
On 28 November 2014 Government made changes to Paragraph 12 of the National Planning Practice Guidance (NPPG) where contributions for affordable housing and tariff style planning obligations should not be sought from small-scale and self-build development. These changes relate to developments of 10 residential units or less, and which have a maximum combined gross floorspace of no more than 1000 sq.m. The only exception is for developments of between 6 and 10 units in Areas of Outstanding Natural Beauty or National Parks (where affordable housing and tariff style contributions should be sought in the form of payments which are commuted until after completion of the units within the development). These changes took immediate effect.
The change in legislation affects this application, which Planning Committee resolved to approve on 10 November 2014 subject to a Section 106 Agreement to deliver upto 40% affordable housing (details to be agreed at the Reserved Matters stage). However, as the required legal agreement has yet be signed and completed, and the change in legislation is now effective, the application remains ‘pending’. It therefore needs to be reconsidered under the aforementioned changes to national guidance and the offer made by the applicant (see Section 7.6 of this report). The report is predominantly unchanged from the one previously reported to Planning Committee with the expectation of the recommendation that now modifies the requirements of the planning obligation to reflect the offer form the applicant to provide a financial contribution.
This form/scale of development would normally be dealt with under the Scheme of Delegation. The application was originally referred to Planning Committee by Councillor Gardner. The reason for the request is because it is considered the application warrants examination as to the effect of the development on the local area and its access.
1.0The Site and its Surroundings
1.1The application site comprises a triangular field approximately 0.4 ha in area located on the north- eastern edge of Carnforth fronting North road (Carnforth Brow). The field lies to the north of North Road within land designated as Countryside Are in the Lancaster District Local Plan. A local rail-line runs along the northern boundary of the site and a small open field to the west. Residential housing is located directly opposite part of the site frontage and to the west of the site. Open agricultural land lies to the north beyond the rail line.
1.2The site is located on the eastern side of rising land and falls both to the east and to the north. The rail-line reflects this change in ground levels along the northern boundary with the rail line crossing from shallow cutting to embankment as it travel west to east. A public footpath accesses the western boundary of the site form North Road follows the western edge of the field (site0 and connects to a rail crossing point. The footpath continues having crossed the rail cutting into fields finally emerging onto Scotland Road north of the bridged rail crossing.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Car Park Nelson Street LancasterResolved : That the application be approved subject to the following conditions: 1. Development in accordance with Ap...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.