Resolved
- That, in accordance with S106 (A) of the Town and County Planning Act, the proposed application to modify and discharge the terms of the original agreement in relation to the applicant’s land only be granted .
Planning Regulatory Committee agreed this item on Monday 8 February 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
- That, in accordance with S106 (A) of the Town and County Planning Act, the proposed application to modify and discharge the terms of the original agreement in relation to the applicant’s land only be granted .
Agenda Item Committee Date Application Number
A9 8 February 2016 15/01568/VLA
Application Site Proposal
Site Of Former Pontins Holiday Camp Variation of legal agreement on planning permission Carr Lane 00/00156/OUT to remove the age restriction on Middleton occupants and the requirements for car-free design, a Lancashire bus service and use of on-site facilities by on-site residents only, and to vary the requirements for affordable housing provision and its phasing, and the requirements for a Travel Plan
Name of Applicant Name of Agent
The Glory Hole Ltd [name removed] Target Date Reason For Delay
8 February 2016 Not applicable
Case Officer [name removed] No
Summary of Recommendation Approve
1.0The Site and its Surroundings
1.1Middleton Towers is a 23 hectare site of the former Pontins Camp that closed in 1994. It is located to the west side of Carr Lane, 1km west of the village of Middleton. Heysham lies approximately 3km to the north and Morecambe Town Centre is located approximately 3.5 km along the coast line.
1.2It is a previously developed site located within the countryside area surrounded by other tourism and leisure uses, such as Ocean Edge Leisure Park and Greendales Leisure Park. Heysham Power Station is located north of the site beyond which lies Morecambe Bay and Middleton Sands Special Area of Conservation (SAC), Special Protected Area (SPA), Site of Special Scientific Interest (SSSI) and a Ramsar Site.
1.3The only vehicular access to the site is via Middleton village along Carr Lane, which is a narrow country road with substandard alignment and no footways. There are no public bus services which run along Carr Lane towards the appeal site. The entrance to the site is gated.
1.4The site benefits from planning consent for the construction of a self-contained retirement village. Construction has occurred on Parcel 1 (land administered by Moorfields Corporate Recovery LLP): whilst the quality of the buildings constructed and landscaped areas are good and represent high quality design, the environmental condition of the site for the existing residents is not particularly appealing. This is a consequence of the site running into commercial difficulties and the development stalling, leaving areas of undeveloped land and large hoardings around the remaining parcels of land.
2.0The Proposal
2.1An application under Section 106A of the Town and Country Planning Act to vary the legal agreement (as amended in September 2005) on planning permission 00/00156/OUT in relation to Parcel 1 only was approved on appeal in October 2014 (13/00805/VLA). The legal agreement (as amended in September 2005) remains in force on Parcel 2 (land within the ownership of The Glory Hole Ltd). The Glory Hole Ltd has submitted an application to secure amendments to the legal agreement as those secured for Parcel 1, namely: Sch.1, para 1: delete. Paragraph 1 relates to construction of a maximum of 650 dwellings on the Site (including the residential care home) of which not less than 20% of the total number shall be of ‘car free’ design.” Sch.1, para 2: insert new paragraph: “2.8 10% of dwellings must be affordable units”. Sch.1, para 3: delete. Paragraph 3.1 requires the head of household to a minimum of 55 years old; and paragraph 3.2 imposes an age restriction on the occupation of the residential care home. Sch.1, para 5: delete. Paragraph 5 restricts use of the facilities on the site to residents on the site and residents in the Parish of Middleton via a membership scheme Sch.1, para 6: delete. Paragraph 6 relates to the operation of a bus service for 5 years from the occupation of the first dwelling unit.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Site Of Former Pontins Holiday Camp, Carr Lane, MiddletonReport | 257 KB | DownloadRead as text |
Follow Planning Regulatory Committee at Lancaster and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Bus Station Central Drive MorecambeResolved : That prior approval for demolition is required and is granted. | Approved | Open |
| 1 Sep 2026 | Car Park Nelson Street LancasterResolved : That the application be approved subject to the following conditions: 1. Development in accordance with Ap... | Approved | Open |
| 1 Sep 2026 | Auction Mart Car Park Thurnham Street LancasterResolved : That the application be approved subject to an additional condition regarding additional ground investigat... | Approved | Open |
| 1 Sep 2026 | Delegated ListThat the report be noted. | Noted | Open |
| 27 Jul 2026 | Land at Ashton Road LancasterResolved : That the application be approved subject to the following conditions: · the satisfactory completion of a L... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.