That Cabinet authorises officers to redirect funds to procure and award a contract for the installation of Solar PV panels to 35 sheltered bungalows, which is estimated to deliver a CO2 saving of 35 tonnes per year. Officer responsible for effecting the decision: Director for Communities and the Environment Reasons for making the decision: The Council has a target to be Carbon Neutral by 2030. The installation of Solar PV panels is one of a range of measures designed to improve the thermal comfort of homes, lower customers energy bills and reduce the impact of harmful carbon dioxide into the atmosphere and thus increasing the overall EPC rating of these properties. A further benefit of this will be a reduction in energy bills for residents in our sheltered bungalows, supporting health and wellbeing.
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
The HRA capital programme includes £120,000 for Whole House Refurbishment within this financial year. Redirection of this amount to Carbon Zero Plus measures, for which the programme already includes provision of £70,000, will allow for the required £175,000 to undertake the installation of Solar PV panels on 35 sheltered scheme properties.
Other Resource or Risk Implications None Section 151 Officer’s Comments
The use of virements to realign or refocus existing funds from one expenditure head to another is permitted subject to the limits set out in the Council’s Medium-Term Financial Strategy. The value requested does not require full cabinet approval under the Council’s existing virement policy. However, current COVID delegations require the new or recommencement of capital projects to be approved by Cabinet irrespective of the financial level and so for clarity approval by full Cabinet is sought for both expenditure and funding reallocation.
Monitoring Officer’s Comments
The Monitoring Officer has been consulted and has no further comments.
Contact Officer Dennis Graham Tel 01524 582453 Email [email protected] Links to Background Papers
NA
1. Introduction
1.1The Council’s approved HRA capital budget for 2020/2021 included provision for the undertaking of whole house refurbishment works (sufficient funding for 4 properties). Full Council 26th Feb 2020 – Capital Programme Item no. 137
1.2The impact of Covid-19 has restricted the delivery of some internal works to Council house stock. This is due to the duration of time required to undertake specific works, to reduce the risk of infection, and also due to staff being reallocated to support the pandemic response.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Press and PublicResolved unanimously: That in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and publi...
Reports from Overview and Scrutiny(8 Members (Councillors Bannon, Bottoms, Hart, Caroline Jackson, Peter Jackson, Riches, Stubbins & Tyldesley) voted i...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.