Lancaster City Council
Council, Wednesday 24 February 2021

Capital Programme and Capital Strategy 2021/22-2024/25

Approved Committee 3 papers

Council approved this item on Wednesday 24 February 2021. Below is the council's own wording, with the papers it was decided on.

Item115

Resolved

(1) That the General Fund Capital Programme be approved, as set out at Appendix A of the report, subject to recommendation 2 below. (2) That the Portfolio Holder for Finance be given delegated authority to update the capital programme and associated documents to reflect the outcome of the current external funding bid. (3) That the Capital Strategy, at Appendix B of the report, be approved. (The Mayor called for an adjournment at this point, in accordance with Council Procedure Rule 10. The time was 8.15pm. The meeting re-convened at 8.25pm.)
Word for word from the decision Lancaster published for this meeting. Source: committeeadmin.lancaster.gov.uk

Follow this further

Built from Lancaster's papers

What the report saysPro

Report to Council

Purpose of report

To present Cabinet’s final budget proposals in order that the City Council can approve a General Fund Capital Programme for 2021/22 to 2024/25 and a Capital Strategy 2021/22.

This report is public.

Recommendations

(1) That the General Fund Capital Programme be approved, as set out at Appendix A subject to recommendation 2 below

(2) That the Portfolio Holder for Finance be given delegated authority to update the capital programme and associated documents to reflect the outcome of the current external funding bid.

(3) That the Capital Strategy at Appendix B be approved.

1.0INTRODUCTION

1.1Following its meeting on 09 February Cabinet has now finalised its budget framework proposals for the General Fund Capital Programme. These are all now reflected in the recommendations of this report.

Background

2.1Capital expenditure generally comprises the buying, construction, or improvements of physical assets such as buildings, land, vehicles, and other miscellaneous items. The expenditure can also include grants and advances which the Council pays to other bodies or individuals for capital spending purposes.

2.2There are several funding resources available to support the Capital Programme which can include:

 Capital receipts – monies received from the sale of a capital asset.

1  Revenue contributions – monies set aside in specific reserves to support and fund schemes.

 External grants and contributions – monies received from third parties to fund schemes. These monies normally include conditions on what they can be used for.

 External borrowing – the Council is free to make its own borrowing decisions according to what is affordable, sustainable, and prudent as set out in the Prudential Code.

3.0CAPITAL PROGRAMME

3.1The proposed General Fund investment programme for the period to 2024/25 is included at Appendix A and summarised in table 1 below.

Table 1 2020/21 2021/22 2022/23 2023/24 2024/25 Total £M £M £M £M £M £M Approved Schemes 11.968 9.518 3.227 0.755 2.021 27.489 Development Pool 0.298 33.820 22.523 6.900 5.065 68.606 Total 12.266 43.338 25.750 7.655 7.086 96.095

3.2The current year’s revised net programme now stands at £12.266M. During the next 4 years, a further £83.829M of investment is currently planned, giving a total net 5- year programme from 2020/21 to 2024/25 of £96.095M.

3.3Recent changes to Public Works Loan Board (PWLB) borrowing have had significant implications for the Capital Programme, with investment primarily for yield now being constrained. These changes may require a different approach to capital investment, and while, given the social motives of the Council, the majority of the planned schemes appear eligible, further work is being undertaken to ensure the alignment of the programme with the new criteria. Should any revisions to the programme, or supporting strategies be required these will be brought forward for approval in line with the Council’s constitutional requirements.

3.4Development pool schemes provision is included where work is being undertaken to develop schemes, but the provision will not be dispersed until full business cases have been considered and approved via the relevant decision-making governance

3.5A number of significant schemes are included in the development pool including Canal Quarter, general fund housing schemes, Heysham Gateway development as well as investment in solar and renewable energy. All these schemes will require significant capital expenditures and borrowing but each business case will have to show that income arising from the capital investment is capable of covering all borrowing costs and delivering a positive return to the Council.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Appendix AAppendix 255 KB Download
PDF
Capital Programme and Capital Strategy 2021/22-2024/25Report 255 KB DownloadRead as text
PDF
Capital Strategy Appendix BAppendix 776 KB Download

At this meeting

Whole meeting

On this subject at Lancaster

Search all
  1. Capital Programme and Capital Strategy 2021/22-2024/25This decision
  2. Capital Programme 2026/27 - 2035/36 & Capital Strategy (Invested in the Future)Approved
  3. Capital Programme 2026/27 – 2035/36 & Capital Strategy (Investing in the Future)Noted
  4. Capital Programme 2026/27 – 2035/36 & Capital Strategy (Investing in the Future)Approved
  5. Capital Programme Mid Year Review 2025/26Approved
  6. Capital Programme Mid-Year Review 2025/26Noted

More from Lancaster Council

All decisions
MeetingDecisionOutcome
22 Jul 2026 Leader's reportThat the report be noted. Having declared an interest, Councillor Keith Budden left the Council Chamber for the durat... Noted Open
22 Jul 2026 Morecambe Business Improvement District (BID) Renewal Ballot - City Council's Voting IntentionResolved (unanimously) that: 1) The Council’s voting allocation be used to vote in favour of Morecambe BID’s Renewal ... Decided Open
22 Jul 2026 Allocation of seats to political groupsResolved (unanimously): That the Council note the establishment of the Independent Group of Councillors and approve t... Noted Open
22 Jul 2026 Minutes of cabinetThat the minutes be noted. Noted Open
25 Jun 2026 Leader's reportThat the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies