(6 Members (Councillors Hamilton-Cox, Evans, Hanson, Hartley, Lewis & Whitehead) voted in favour, 4 Members (Councillors Brookes, Dowding, Frea and Jackson) voted against.) (1) That an Expression of Interest nominating a site for the Spherical Tokamak for Energy Production (STEP) project be submitted to the United Kingdom Atomic Energy Authority (UKAEA) prior to the deadline of 31 March 2021. Officer responsible for effecting the decision: Director for Economic Growth & Regeneration Reasons for making the decision: STEP (Spherical Tokamak for Energy Production) is an ambitious programme to design and build a prototype fusion power plant. In Autumn 2020, there was an open call to communities across the UK to host the prototype. UKAEA will make a recommendation to the Secretary of State for BEIS on the most suitable locations for STEP following a rigorous process of assessment using a defined set of key criteria. The decision enables an Expression of Interest to be submitted prior to the deadline on 31 March 2021.
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
Lancaster City Council | Report Cover Sheet Meeting Cabinet Date 23rd March 2021 Title STEP Site Nomination – Expression of Interest (EOI) Report of Head of Property, Investment & Regeneration Purpose of the Report: Cabinet to Approve the Submission of the EOI
Key Decision (Y/N) Y Date of Notice Exempt (Y/N)
Report Summary To approve the submission of an Expression of Interest nominating a site for the Spherical Tokamak for Energy Production (STEP) project to the United Kingdom Atomic Energy Authority (UKAEA)
In accordance with the Constitution Part 3, Section 3 of Overview and Scrutiny Procedure Rule 17 the Chief Executive has consulted with the Chair of Overview and Scrutiny in relation to Urgency and Call-in regarding this item. The reason for the urgency is that the Expression of Interest needs to be provided before the 31 March and if the report was called in the deadline would pass for the submission of the expression.
Recommendations To submit the Expression of Interest by the deadline 31st March 2021 Relationship to Policy Framework
Conclusion of Impact Assessment(s), where applicable Climate Not known at this stage Wellbeing & Social Value See Introduction below Digital Not known at this stage Health & Safety Not known at this stage Equality Not known at this stage Community Safety Not known at this stage
Details of Consultation The portfolio holder has been consulted.
Legal Implications None
Financial Implications None
Other Resource or Risk Implications None
Section 151 Officer’s Comments The s151 has been consulted and has not comments to make at this stage
Monitoring Officer’s Comments The Monitoring Officer has no comments to make at this stage
Contact Officer Iain Robertson Tel [phone removed] Email [email protected] Links to Background Papers None
1.0Introduction STEP (Spherical Tokamak for Energy Production) is an ambitious programme to design and build a prototype fusion power plant.
It is a UKAEA programme, currently with £222million funding from the UK Government to produce a concept design by 2024.
Beyond 2024, the UKAEA will move into the engineering design and build phases of the programme and will work with a range of partners to deliver the prototype of a commercially viable fusion plant.
The STEP prototype will demonstrate the commercial viability of fusion. The learning from this will enable the future development of a fleet of commercial fusion plants.
Once constructed, STEP will produce net energy and prove electricity can be predictably and stably produced in a fusion power station.
In Autumn 2020, there was an open call to communities across the UK to host the prototype. UKAEA will make a recommendation to the Secretary of State for BEIS on the most suitable locations for STEP following a rigorous process of assessment using a defined set of key criteria.
More information can be found on the siting process on the website step.ukaea.uk.
2.0Site Requirements With the plant still in design phase it’s not possible to be too precise about what buildings and facilities will be needed on site. This will become increasingly clear in the coming years as the design develops and a site is established. STEP will have the many features of a fully operational power station, including infrastructure and associated research and development facilities. It is likely to be of a comparable scale and value as any major power station.
The basic site criteria are: Minimum site area of 100 hectares Access to National Grid Local skills base - nuclear supply chain, design engineering, high-tech manufacturing, power station operations, fusion and high-tech R&D Transport & Infrastructure – access to strategic road network, rail line a port Close proximity to a significant mass of water
3.0Community Benefits There will be long term and enduring economic benefits to the host community.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Press and PublicResolved unanimously: That in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and publi...
Reports from Overview and Scrutiny(8 Members (Councillors Bannon, Bottoms, Hart, Caroline Jackson, Peter Jackson, Riches, Stubbins & Tyldesley) voted i...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.