That the application be approved subject to the conditions set out in the Committee Report and subject to the additional conditions: 1. Standard 3 year timescale. 2. Approved plans. 3. Landscaping and management scheme/implementation. 4. Details of colours/materials. 5. Drainage including no intrusive system unless approved. 6. Construction Vehicle Management Plan. 7. Works outside nesting bird season. 8. Tree protection plan and method statement to be submitted prior to commencement. 9. Solar panels to be removed after 25 years and restoration scheme to be submitted, approved and implemented.
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
Installation of arrays of 2.96 metres high PV panels, underground cabling, battery containers, inverter and associated cabins and kiosks, Proposal construction of 2.1 metres high security fencing, CCTV mounted on 6m masts, construction compound and construction of internal temporary access track with associated landscaping to form Solar Farm Land Adjacent Salt Ayre Leisure Centre, Salt Ayre Landfill Site, Salt Application site Ayre Lane
Applicant Lancaster City Council
Agent [name removed] Officer [name removed] No
Summary of Recommendation Approve
1.0Application Site and Setting
1.1This proposal relates to a 4.3ha part of the former waste disposal site off Salt Ayre Lane. It is located in the south east corner of the restored landfill site, adjacent to the south western boundary of Salt Ayre Sports Centre (nearest a grass football pitch). The landfill site has been capped under control of the Environment Agency with a suitable layer to prevent the tipped material from emitting air or water borne contaminants.
1.2Access will be gained through the existing waste recycling centre off Ovangle Road via Salt Ayre Lane using existing informal tracks on the former landfill site. Beyond and immediately adjacent to the southern boundary is a cycle and pedestrian route with the River Lune beyond.
1.3The site is part of the Key Urban Landscape local landscape designation.
2.0Proposal
2.1The proposal is to install a solar farm of photovoltaic (PV) panels arranged in rows on an east-west axis facing south. To retain the integrity of the landfill capping layer it is important there is nothing penetrating the ground surface. Therefore, the panels will be supported by ballast blocks which will sit on the land surface. The rows will be spaced enabling pedestrian access between the panels and around the outside. These accesses will not be permanently surfaced as no vehicles will be required to enter the site once installed. All ground around the panels will be planted to support grass growth. The maximum height of the panels will be approximately 2.96m above ground.
2.2Supporting infrastructure of a compound containing electrical switchgear and battery storage, security fencing and pole mounted CCTV will be provided. The compound will be located in the north east corner of the site and contain 2 switchgear kiosks of approximate dimensions 4.25m x 4.25m x 3.9m high to ridge and 5 battery storage containers measuring 6m long x 2.4m wide x 2.6m high. The site security fencing will be 2m high and made of galvanised lattice style metal supported on ballast blocks. 6m CCTV poles will also be supported on ballast blocks. All cabling will be surface Page 1 of 7 CODE 21/00256/FUL mounted apart from the supply cable to the sports centre which will be below ground where it runs through the sports centre grounds.
2.3A temporary construction compound will be needed during installation which will be located north of the site and contain an office and storage cabins.
3.0Site History
3.1A number of relevant applications relating to this site have previously been received by the Local Planning Authority. These include:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Car Park Nelson Street LancasterResolved : That the application be approved subject to the following conditions: 1. Development in accordance with Ap...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.