Cabinet, Tuesday 13 July 2021

Release of Capital Programme – Development Pool allocation for the purchase of an electric van for the Engineering Team within Property, Investment and Regeneration

Approved Executive 1 paper

Cabinet approved this item on Tuesday 13 July 2021. Below is the council's own wording, with the papers it was decided on.

Item22

Resolved

Resolved unanimously: (1) That Cabinet approves the release of £15,000 from the development pool section of the general fund capital programme for the purchase of an electric van for the Engineering team and notes that the purchase cost is likely to be in the region of £18,000. (2) That the general fund revenue and capital budgets are updated as appropriate, as part of the forthcoming budget exercise. Officer responsible for effecting the decision: Director for Economic Growth & Regeneration Chief Finance Officer Reasons for making the decision: The decision is consistent with Council Priorities as switching from diesel aligns with the Council’s aim towards carbon zero. The engineering team currently have access to a Peugeot Partner diesel van on a long-term hire agreement. Transferring to its electric van equivalent on hire is not cost effective so an allocation was made in the GF Capital Programme Pool of £15,000 to purchase a van outright as part of the council’s vehicle capital programme. This will generate annual revenue savings within the coast protection budget area of approximately £3,000 per annum, subsequently leading to a minimal cost over the life expectancy of the vehicle.
Word for word from the decision Lancaster published for this meeting. Source: committeeadmin.lancaster.gov.uk

Follow this further

Built from Lancaster's papers

What the report saysPro

Report to Cabinet

Lancaster City Council | Report Cover Sheet Meeting Cabinet Date 13 July 2021 Title Release of Capital Programme – Development Pool allocation for the purchase of an electric van for the Engineering Team within Property, Investment and Regeneration Report of Director for Economic Growth & Regeneration Purpose of the Report: To request the release of allocated budget within the Capital Programme – Development Pool Key Decision (Y/N) N Date of Notice N/A Exempt (Y/N)

Report Summary Report to request release of the allocated budget of £15,000 from the Capital Programme – Development Pool.

Recommendations (1) That Cabinet approves the release of £15,000 from the development pool section of the general fund capital programme for the purchase of an electric van for the Engineering team and notes that the purchase cost is likely to be in the region of £18,000 (2) That the general fund revenue and capital budgets are updated as appropriate, as part of the forthcoming budget exercise Relationship to Policy Framework

Conclusion of Impact Assessment(s), where applicable Climate the switch from diesel to EV aligns with the Wellbeing & Social Value n/a Councils aim towards Carbon Zero Digital n/a Health & Safety the van will help to ensure the coastal strip and other LCC flood/drainage assets are monitored and maintained. Equality n/a Community Safety the van will help to ensure the coastal strip and other LCC flood/drainage assets are monitored and maintained.

Details of Consultation Budget request made as part of 2021-25 budget process Q4 2020-21.

Legal Implications There are no legal implications stemming from this report.

Financial Implications The purchase of an electric vehicle for the engineers team was included in the development pool section of the general fund capital programme, as approved by Council on 24th February 2021. An initial estimate of £15,000 was submitted however quotes have now been sought and it is likely that the purchase price will be in the region of £18,000. As detailed in the report, this will generate annual revenue savings of £3,000 so given a minimum life expectancy of six years the whole life cost should be minimal.

The general fund revenue and capital budgets will be updated as appropriate.

Other Resource or Risk Implications

Section 151 Officer’s Comments

The releasing of capital expenditure items from the Council’s development pool is rests with Cabinet.

Monitoring Officer’s Comments

The Monitoring Officer has no further comments to add.

Contact Officer Justin Shaw Tel 01524 582375 Email [email protected] Links to Background Papers General Fund Capital Programme as approved by Council 24 Feb 2021 Appendix A Capital Programme Appendix A.pdf

1.0Introduction

The engineering team currently have access to a Peugeot Partner diesel van on a long-term hire agreement. Transferring to its electric van equivalent on hire is not cost effective so an allocation was made in the GF Capital Programme Pool of £15,000 to purchase a van outright as part of the council’s vehicle capital programme.

This will generate annual revenue savings within the coast protection budget area of approximately £3,000 per annum, subsequently leading to a minimal cost over the life expectancy of the vehicle.

The electric vehicle will require access to charge points at Morecambe Town Hall and occasionally White Lund Depot.

2.0Options and Options Analysis (including risk assessment)

Options Analysis Option 1 – Continue with current diesel van hire arrangement (do nothing) Advantages: Current van is fit for purpose for transportation, maintenance, and monitoring activities.

Disadvantages: Takes no action to tackle climate emergency and the goal of being net zero carbon by 2030. Risks: The approach is different to that being applied to other fleet/hire vehicles and the Council is not seen to lead by example by switching to EV.

Options Analysis Option 2 – Switch to a EV hire vehicle

Advantages: Helps to achieve the Councils zero carbon priorities

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Release of Capital Programme: Development Pool allocation for the purchase of an electric van for the Engineering Team within Property, Investment and RegenerationReport 551 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Lancaster

Search all
  1. Release of Capital Programme – Development Pool allocation for the purchase of an electric van for the Engineering Team within Property, Investment and RegenerationThis decision
  2. Release of Capital Reserves for the South Lancaster Growth Catalyst (HIF Programme)Agreed

More from Lancaster Cabinet

All decisions
MeetingDecisionOutcome
28 Jul 2026 Provisional Revenue, Capital and Treasury Management Outturn 2025/26Resolved unanimously: (1) That the provisional outturn for 2025/26 be endorsed, including the transfers to and from R... Approved Open
28 Jul 2026 Exclusion of the Press and PublicResolved unanimously: That in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and publi... Decided Open
7 Jul 2026 Exclusion of press and publicResolved unanimously: (1) That, in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and ... Decided Open
9 Jun 2026 Reports from Overview and Scrutiny(8 Members (Councillors Bannon, Bottoms, Hart, Caroline Jackson, Peter Jackson, Riches, Stubbins & Tyldesley) voted i... Approved Open
9 Jun 2026 Appointments ReportResolved unanimously: That the appointments to outside bodes and partnerships as appended to the report be confirmed ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies