Resolved unanimously: (1) That Cabinet supports the application for further schemes and approve the PSDS funding should an offer be forthcoming noting that any final acceptance by a Director is subject to S151 officer consent following due diligence checks, in accordance with the Council’s own financial procedure rules. (2) That, subject to the acceptance of an offer for external funding, Cabinet approves the reallocation of £2M unspent funding in respect of further decarbonisation projects across the HRA and approve the necessary adjustments between the General Fund and HRA capital programmes. (3) That Cabinet supports the request to provide delegated authority to the Chief Executive to award the associated contracts when a decision is ready to be made. Officers responsible for effecting the decision: Chief Executive Director for Communities and the Environment Chief Finance Officer Reasons ... view the full minutes text for item 29.
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
Lancaster City Council | Report Cover Sheet Meeting Cabinet Date 14 September 2021 Title PSDS Decarbonisation of Sheltered Schemes Report of Director for Communities and The Environment Purpose of the Report
That Cabinet support the application for further schemes and approve the Public Sector Decarbonisation Scheme funding should an offer be forthcoming noting that any final acceptance by a Director is subject to S151 officer consent following due diligence.
Should acceptance of funding be granted it is requested that Cabinet provide the Chief Executive with delegated authority to award the contract for the solar scheme, ground source heat pumps and building upgrades following compliant procurement exercises.
Key Decision (Y/N) Y Date of Notice 23/08/21 Exempt (Y/N) N
Report Summary
In Jan 2019, the Council declared a climate change emergency. The Council’s priorities include the theme of ‘Taking action to meet the challenges of the climate emergency’. Specific actions include-
Net zero carbon by 2030 while supporting other individuals, businesses and organisations across the district to reach the same goal.
Increasing the amount of sustainable energy produced in the district and decreasing the district’s energy use.
In February 2021, the council received £6.8M of PSDS funding to decarbonise Salt Ayre Leisure Centre (SALC). Due to grid restrictions, the solar scheme was reduced from 3MWp to 1.3MWp, reducing the expected project costs to below £5M.
The scheme was resubmitted to Salix Finance / BEIS and was accepted. Officers expect construction to be completed by October 2021 and energisation completed by November 2021. The project is expected to reduce the council’s natural gas emissions by 35% The full project is expected to be delivered for £4.8M.
In June 2021, Salix Finance informed officers that the £2M underspend on SALC could be reinvested in further decarbonisation schemes providing they meet the PSDS criteria. This includes full project completion by March 2022. An application to Salix would be required to facilitate this.
In line with the grant criteria, officers commissioned desktop reviews of all properties within the council’s scope 1 (direct) emissions.
Desktop feasibility was completed on 19th August with four sheltered schemes appearing to offer the most complete solutions using a combination of Ground Source Heat Pumps and Solar PV:
Collectively the sites contribute 15% of the council’s natural gas emissions. Estimated costs for delivering all four schemes is £1.9M.
Consent has been provided by S151 Officer and Director of Communities & The Environment to submit a new application to Salix Finance and utilise the funding on these schemes.
If successful, capital costs of this project will be covered by the current PSDS grant underspend. This also means any capital provisions made in the HRA programme for boiler replacements at these sites can be removed or reallocated.
Initial estimates and modelling suggests that energy costs across the sites will reduce, on average, by £7,000 per scheme. Estimates will be confirmed following completion of detailed design, should the funding application be successful.
Engineer site visits carried out as part of the feasibility also suggests that internal upgrades to pipework and radiators are not necessary, minimising any disruption to residents and limiting it to external works only (GSHP and solar).
Directors have authority to accept funding bids approved by Cabinet/or Full Council, subject to due diligence being completed and with the written consent of the Chief Finance Officer.
The timescales of the grant funding are very tight and officers are exploring available procurement frameworks. Due to the value, a Key Decision has been submitted. Recommendations of Councillor Matthews
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Press and PublicResolved unanimously: That in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and publi...
Reports from Overview and Scrutiny(8 Members (Councillors Bannon, Bottoms, Hart, Caroline Jackson, Peter Jackson, Riches, Stubbins & Tyldesley) voted i...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.