Heat Decarbonisation Programme: Baseline Capital Funding

Approved Executive 1 paper

Cabinet approved this item on Tuesday 7 June 2022. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Resolved unanimously: (1) That Cabinet refer the capital growth requested to Council for approval in order to ensure the buildings remain fit for purpose and deliver on the projects listed within the Building Heat Decarbonisation Plan, should funding become available. Officer responsible for effecting the decision: Chief Executive Reasons for making the decision: The project currently sits outside of the Council’s approved Capital Programme and Treasury Management Strategy and so will require approval by Council in order to bring it within the Budget & Policy Framework. The decision is consistent with the following priorities and cross-cutting themes: · An inclusive and prosperous local economy. A proportion of the overall evaluation will include an element of social value, in line with the procurement strategy and contract procedure rules. · Climate Emergency – Net zero 2030 ambition.
Word for word from the decision Lancaster published for this meeting. Source: committeeadmin.lancaster.gov.uk

Follow this further

Built from Lancaster's papers

What the report saysPro

Report to Cabinet

Lancaster City Council | Report Cover Sheet Meeting Cabinet Date 7th June 2022 Title Heat Decarbonisation Programme: Baseline Capital Funding Report of Chief Executive Purpose of the Report

To seek approval for £300k capital growth in the 22/23 – 25/26 capital programme to cover essential gas boiler replacements at The Storey, Palatine Hall and Williamson Park and refer to the matter to full council for approval and to make the necessary budget adjustments.

Capital contributions will be needed to support future Public Sector Decarbonisation Scheme (PSDS) funding opportunities, should applications be successful.

Key Decision (Y/N) Y Date of Notice 03/05/22 Exempt (Y/N) N

Report Summary

In Jan 2019, the Council declared a climate change emergency. The Council’s priorities include the theme of ‘Taking action to meet the challenges of the climate emergency’. Specific actions include-

 Net zero carbon by 2030 while supporting other individuals, businesses and organisations across the district to reach the same goal.

 Increasing the amount of sustainable energy produced in the district and decreasing the district’s energy use.

In 2019/20 the council’s natural gas emissions (heating) accounted for 59.6% of direct (Scope 1) emissions. The remainder of which came from the vehicle fleet.

Since then, the council has approved a comprehensive fleet electrification programme and with £6.8M Public Sector Decarbonisation Scheme (PSDS) funding delivered a project to decarbonise Salt Ayre Leisure Centre, reducing natural gas emissions by as much as 35%.

The decarbonisation of heating systems remains one of the key challenges in reaching net zero by 2030. Significant funding from central government is being channelled in this direction.

The council has been fortunate to receive funds from PSDS, Low Carbon Skills Fund (LCSF) and the BEIS Heat Network Delivery Unit (HNDU) to deliver, explore and create a strategy for heat decarbonisation. The council’s Building Energy Decarbonisation Plan (BEDP) was completed in March 2022.

Officers expect further PSDS schemes to be announced over the coming months and intend to apply for funding to deliver two sites (Palatine & The Storey) in 22/23, should the opportunity arise.

The BEDP suggests the boilers at Williamson Park should be replaced in 25/26 however should the opportunity of external funding arrive and plans to redevelop the buildings on site reach an advanced stage, this could be brought forward by 12 – 24 months. Since the initial £1b of funding through ‘Phase 1 PSDS’ was made available to local authorities there have been two more rounds of funding – PSDS 2 & PSDS 3. The funding criteria in each has changed.

For all new PSDS opportunities Local Authorities now have to make a funding contribution, equivalent to the replacement gas boiler costs. Only sites with boilers reaching end of life are eligible and it is expected that LA’s will have capital funding available to contribute. This is expected to come from existing budgets.

The expected costs for replacement gas boilers has been included in the council’s Building Energy Decarbonisation Plan and equates to £295,665 over the next four years (Excl. £43,290 for HRA).

In order to support the council’s priorities around the climate emergency and take advantage of imminent funding opportunities, officers seek to establish a £300k capital budget to cover boiler replacements between 22/23 – 25/26. Should PSDS funding be successful, the capital funding would be used as contributions.

Across the three sites, up to £3.5M of decarbonisation measures have been identified, much of which has the potential to be funded from future Public Sector Decarbonisation Schemes, should future applications be successful.

It is expected that the full range of decarbonisation measures listed in the report would reduce energy consumption and generate modest revenue savings. See ‘financial implications’ for further details.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Heat Decarbonisation Programme: Baseline Capital FundingReport 670 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Lancaster

Search all
  1. Heat Decarbonisation Programme: Baseline Capital FundingThis decision
  2. Heat Decarbonisation - Boiler Replacement ProgrammeApproved

More from Lancaster Cabinet

All decisions
MeetingDecisionOutcome
28 Jul 2026 Provisional Revenue, Capital and Treasury Management Outturn 2025/26Resolved unanimously: (1) That the provisional outturn for 2025/26 be endorsed, including the transfers to and from R... Approved Open
28 Jul 2026 Exclusion of the Press and PublicResolved unanimously: That in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and publi... Decided Open
7 Jul 2026 Exclusion of press and publicResolved unanimously: (1) That, in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and ... Decided Open
9 Jun 2026 Reports from Overview and Scrutiny(8 Members (Councillors Bannon, Bottoms, Hart, Caroline Jackson, Peter Jackson, Riches, Stubbins & Tyldesley) voted i... Approved Open
9 Jun 2026 Appointments ReportResolved unanimously: That the appointments to outside bodes and partnerships as appended to the report be confirmed ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies