CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Lancaster City Council
Planning Regulatory Committee, Monday 30 January 2023

Salt Ayre Landfill Site Salt Ayre Lane Lancaster Lancashire

Agreed Planning 1 paper

Planning Regulatory Committee agreed this item on Monday 30 January 2023. Below is the council's own wording, with the papers it was decided on.

Item95

Resolved

Resolved : That Lancaster City Council object for the reasons given in the Committee Report: 1. The site is allocated as a Key Urban Landscape, an important open area proving a setting to the main urban areas. Policy EN5 seeks to safeguard these areas, preserving their open nature, and great importance is placed on protecting these areas. With no defined end date proposed, nor a restoration scheme for buildings and equipment to be removed and land restoration on a defined date or within a set number of months on cessation of use, the site would remain developed and industrial in perpetuity, detrimental to the visual amenity of the area and wholly inappropriate within the Key Urban Landscape. The existing buildings and structures are poor quality in design and contribute negatively to the character and appearance of the area, and not a feature the LPA would grant permanent consent for. Permanent planning permission cannot be supported, and a restoration scheme for any temporary permission is considered essential. Accordingly, the proposal fails to comply with Policies DM29, DM46 and EN5. 2. The red edge boundaries on the two plans submitted are inconsistent, and it is not clear which boundary defines the land forming this planning application. Furthermore, the plans also show a different boundary to that of the lease agreement between the applicant and Lancaster City Council as landowner. 3. The site lies within an Air Quality Management Area and insufficient information ( ie no Air Quality Assessment) has been submitted to enable consideration of air quality and air pollutants. Therefore the scheme fails to accord with Policies EN9 and DM31 and the Low Emissions and Air Quality Planning Advisory Note. 4. The site lies close to environmentally important areas, including the River Lune, Lune Estuary and Morecambe Bay, which are nationally and internationally designated for their ecological importance. Although the application is for a continuance of an existing use, no biodiversity report has been submitted to assess the impacts of this on the local wildlife populations and habitats. Furthermore, the supporting documents to not consider potential harm on the designated sites (protected under the Habitat Regulations), or other potential impact pathways, and no means of biodiversity net gain have been proposed. As such, the proposal fails to conserve and enhance biodiversity and the natural environment, contrary to Policies DM44 and EN7.
Word for word from the decision Lancaster published for this meeting. Source: committeeadmin.lancaster.gov.uk

Follow this further

Built from Lancaster's papers

What the report saysPro

Report to Planning Regulatory Committee

Agenda Item A15

Application Number 22/01460/CCC

County Council Consultation request for the permanent retention of Proposal the existing Salt Ayre Materials Recycling & Transfer Facility Salt Ayre Landfill Site Salt Ayre Lane Application site Lancaster Lancashire

Applicant Jonathan Wilson, SUEZ Recycling and Recovery UK Ltd

Agent N/A

Case Officer [name removed] N/A

Summary of Recommendation Lancaster City Council OBJECT to the Planning Application

(i) Procedural Matters

Consultee responses to Lancashire County Council planning applications are usually dealt with under delegated powers, however as this relates to a minerals and waste development, it must be reported to the Planning Regulatory Committee. This application has been submitted to, and will be determined by, Lancashire County Council as they are responsible for planning matters that relate to waste and minerals through their Minerals and Waste Plan. Lancaster City Council has been consulted as the proposal falls within their district, and as such this report sets out the City Council’s proposed consultation response. It will be for the County Council to determine whether planning consent should be granted or not.

1.0Application Site and Setting

1.1The site to which this application relates is a Materials Recycling & Transfer facility, on the former Salt Ayre Landfill Site, adjacent to the Household Waste Recycling Centre (HWRC). The site is allocated as green corridor open space and a Key Urban Landscape (KUL) on the Adopted Policies Map.

1.2The site lies within 900m of the Morecambe Bay Special Area of Conservation (SAC), Special Protection Area (SPA) and Ramsar internationally designated sites, and the Lune Estuary SSSI. The site is located approx. 350m north of the River Lune, and is also located within the Air Quality Management Area.

2.0Proposal

2.1The planning application submitted to the County Council seeks consent for the permanent retention of the Salt Ayre Materials Recycling & Transfer Facility. The only documents lodged with the application are a Site boundaries Plan, Site Layout Plan and Planning Supporting Statement. The Page 1 of 4 CODE 22/01460/CCC applicant’s Planning Supporting Statement anticipates that conditions for time limits and restoration schemes will not be imposed.

3.0Site History

3.1A number of relevant applications relating to this site have previously been received by the County Council. These include:

Application Number Proposal Decision 01/93/0403 Material recycling facility Approved subject to time limit 01/02/1255 Retention of material recycling facility Approved allowing operation until December 2010 01/08/1407 Variation of Condition 1 of planning permission 01/02/1255 Approved to allow operation of Materials Recycling Facility to continue until 31 December 2017 LCC/2014/0006 Vary conditions to require the facility to cease not later Approved than the 31 December 2017 and restored no later than 31 December 2018 LCC/2017/0014 Vary conditions to allow use until 31 December 2022 and Approved restoration no later than 31 December 2023

4.0Consultation Responses

4.1The following responses have been received from internal City Council consultees:

Consultee Response Planning Policy No response received Waste & Recycling No response received Salt Ayre Leisure No response received Centre Environmental Health No response received Engineers No response received Climate Emergency No response received Property Services Planning application plans inconsistent and not the same as the lease plan. Restoration scheme required, and expected that buildings removed at the end of the lease term.

5.0Analysis

5.1The key considerations in the assessment of this application are:

 Principle of Development  Landscape and Design  Air Quality  Biodiversity

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Salt Ayre Landfill Site Salt Ayre Lane Lancaster LancashireReport 231 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Lancaster

Search all
  1. Salt Ayre Landfill Site Salt Ayre Lane Lancaster LancashireThis decision
  2. The Shortfall of Income at Salt Ayre Leisure CentreNoted
  3. Salt Ayre Landfill Site Salt Ayre Lane LancasterDecided
  4. Salt Ayre Landfill Site Salt Ayre Lane LancasterDecided
  5. Salt Ayre Landfill Site Salt Ayre Lane LancasterDecided
  6. Land Adjacent Salt Ayre Leisure Centre, Salt Ayre Landfill Site, Salt Ayre LaneApproved

More from Lancaster Planning Regulatory Committee

All decisions
MeetingDecisionOutcome
1 Sep 2026 Bus Station Central Drive MorecambeResolved : That prior approval for demolition is required and is granted. Approved Open
1 Sep 2026 Car Park Nelson Street LancasterResolved : That the application be approved subject to the following conditions: 1. Development in accordance with Ap... Approved Open
1 Sep 2026 Auction Mart Car Park Thurnham Street LancasterResolved : That the application be approved subject to an additional condition regarding additional ground investigat... Approved Open
1 Sep 2026 Delegated ListThat the report be noted. Noted Open
27 Jul 2026 Land at Ashton Road LancasterResolved : That the application be approved subject to the following conditions: · the satisfactory completion of a L... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies