Cabinet, Tuesday 2 December 2025

Projects and Performance: Q2 2025-26

Noted Executive 3 papers

AI summaryLancaster City Council Cabinet noted the Q2 2025-26 projects and performance report. [D] It covers July - September 2025 and links project and performance updates to the Council Plan 24-27, with no direct financial implications. [P4] [P32] [P35]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQuarter two performance and strategic project update [P2] [P4]
MoneyNo direct financial implications [P35]
What happens nextFurther benchmarks sought [P20]Target figures will be added to future reports as available [P20]
Who it affectsStrategic projects and performance [P4] [1.1]Progress updates linked to the Council Plan 24-27 [P32]

What was decided

Lancaster City Council Cabinet noted the Projects and Performance: Q2 2025-26 report. It covered corporate performance and strategic projects for July - September 2025. Report P2, P4

Why

The report gave members an update on corporate performance and strategic projects. Report P4

Monitoring strategic projects and key performance indicators provides a link to the Council Plan 24-27 through progress updates. Report P32

What happens next

Further benchmarking and target figures are being sought and will be added to future reports as they become available. Report P20

Project review reports are awaited for two recently closed projects. Report P30

Implications

  • Risk: Five projects report minor delays to their project plans, and three report minor cost deviations. Four projects report minor scope concerns, meaning one or more benefits of each may not be realised. Report P27, P28, P29
  • Financial: There are no financial implications directly arising, and the Section 151 Officer had no further comments. Report P35, P37
  • Legal: There are no legal implications directly arising. Report P34
  • Other: No direct Health and Safety, Equality and Diversity, Human Rights, Community Safety, HR, Sustainability or Rural Proofing impacts were identified because the report is high level. The Monitoring Officer had no comments. Report P33, P38
  • Risk: Two projects have recently closed and their project review reports are awaited. All other statuses are green, or the relevant project could not provide an update this quarter. Report P30, P31
  • Other: Residual waste benchmarking was added, and figures for all quarters were updated. The major planning applications indicator returned to 100%, and gas and electricity use in council buildings reduced against the like quarter. Report P17, P18, P19
  • Other: Most indicators are compared with the previous quarter, while asterisked indicators are compared with the like quarter from the previous year. Some measures report one quarter behind because of data delays. Report P12, P16
  • Staffing: No further Human Resources, Information Services, Property or Open Spaces implications directly arise. Report P36

Who and where

  • Fifteen strategic projects providing full update reports Report 3.2
  • Projects with minor plan, cost and scope concerns Report P27, P28, P29
  • Two recently closed projects awaiting review reports Report P30
  • Cabinet members receiving the performance update Report P4
  • Major planning applications Report P18
  • Households covered by the residual waste measure Report P17
  • Council buildings covered by the energy use measure Report P19

Timeline

  • quarter two of 2025 - 26 (July - September 2025): Corporate performance and strategic project reporting period. [P4] [1.1] Report P4, 1.1
  • 02 December 2025: Date shown for the Cabinet report. [P2] Report P2
  • 24-27: Period of the Council Plan linked to progress monitoring. [P32] Report P32
  • 24/25: Comparison for gas and electricity use in council buildings. [P19] Report P19
  • Q1: Earlier report whose residual waste benchmarking data was updated. [P17] Report P17

Plain English for the jargon

  • Key Performance Indicator (KPI): A performance measure with targets or benchmarking figures where available. [P13]
  • Quarter behind: A measure reporting one quarter behind because data is delayed. [P16]
  • Red, amber and green status: Status updates for project plan, cost and scope. [P23]
  • Low is good / High is good: A note showing the preferred direction of travel. [P15]
  • On hold: A project status with a short explanation of the reason. [P24]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item85

Resolved

That the report be noted. Reasons for making the decision: Monitoring of strategic projects and key performance indicators provides a link between the Council Plan 24-27 by providing progress updates.
Word for word from the decision Lancaster published for this meeting. Source: committeeadmin.lancaster.gov.uk

Follow this further

Built from Lancaster's papers

What the report saysPro

Report to Cabinet, 3 pages

CABINET

Projects and Performance: Q2 2025-26 02 December 2025

Report of Chief Executive PURPOSE OF REPORT

To provide members with an update on corporate performance and strategic projects during quarter two of 2025 - 26 (July - September 2025).

Key Decision Non-Key Decision Referral from Cabinet N Member Date of notice of forthcoming N/A key decision This report is public

RECOMMENDATIONS OF PORTFOLIO HOLDER FOR FINANCE AND RESOURCES

That Cabinet (1) Consider the update on Projects and Performance for Quarter 2 2025-26.

1.0INTRODUCTION

1.1The primary purpose of this report is to present information relating to the council’s strategic projects and key performance indicators for the period July to September 2025, which can be found within the appendices.

2.0PERFORMANCE REPORTING

2.1Guidance on how to read appendix A.

2.1.1 The majority of indicators should be compared to the previous quarter. Those marked with an asterisk comparing to the like quarter from the previous year is advised.

2.1.2 Our KPI (Key Performance Indicator) data is typically shown using a blue line. Where measures have targets or bench marking figures, they are shown on the using an orange or green line. Each chart contains a key for ease of reading.

2.1.3 The comments provided by KPI owners give further explanation on each indicator.

2.1.4 Within the ‘Comments’ column it is either marked ‘Low is good’ or ‘High is good’. This is included to guide the reader on the preferred direction of travel.

2.1.5 Due to delays in the availability of the data, some measures report one quarter behind. These are clearly marked. 2.2 Summary of key changes in performance report.

2.2.1 A benchmarking figure has now been added for the KPI “KG of residual waste per household (quarter behind)”. In the Q1 report, the benchmarking data was for KG of residual waste per household (quarter behind)”, but our data was her head, not per household. Our figures for all quarters on the report have now been updated.

2.2.2 In this quarter it is notable that the KPI for “Percentage of major planning applications determined within 13 weeks or agreed time” is back up to 100%

2.2.3 It is also notable that Gas and Electricity KWH usage in council buildings (quarter behind): Consumption has reduced compared to like quarter in 24/25

2.2.4 Further benchmarking and target figures are being sought and will be added future reports as they become available.

3.0STRATEGIC PROJECT REPORTING

3.1Guidance on how to read appendix B.

3.1.1 The Programmes and Projects highlight report shows a short narrative and “Red – Amber – Green” status updates for three elements of the project, these being Plan, Cost and Scope.

3.1.2 The ‘Update’ column shows a summary of the projects progress over the last quarter. Where projects are ‘on hold’ a short explanation as to why the project has this status is included.

3.1.3 The ‘Updated’ column shows the date when the update was received. This is included as some projects progress quickly, so it is useful to understand when the update (a snapshot of progress) was taken.

3.2Key points on the progress of strategic projects. Fifteen projects have provided full update reports. Of these:

3.2.1 Five projects are reporting ‘amber’ (minor) delays with the progress of their project plans.

3.2.2 Three projects are reporting ‘amber’ (minor) deviations to the cost of the project.

3.2.3 Four projects are reporting ‘amber’ (minor) concerns with the scope, meaning it is anticipated that one or more benefits of each project may not be realised.

3.2.4 Two projects have recently closed and we are awaiting project review reports for these (this is unchanged from the previous quarter).

3.2.5 All other statuses are either green or have not been able to provide an update this quarter. RELATIONSHIP TO POLICY FRAMEWORK

Monitoring of strategic projects and key performance indicators provides a link between the Council Plan 24-27 by providing progress updates.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Projects and Performance: Q2 2025-26Report 3 pages DownloadRead as text
PDF
Q2 Performance Report 2025-26: IntranetReport 6 pages Download
PDF
Q2 Projects Report 2025-26: Intranet V2Report 4 pages Download

At this meeting

Whole meeting

On this subject at Lancaster

Search all
  1. Projects and Performance: Q2 2025-26This decision
  2. Projects and Performance: Q4 2025-26Noted
  3. Projects and Performance Q3 2025-26Noted
  4. Projects and Performance Quarter 3 2025-26Noted
  5. Projects and Performance: Q2 2025-26Noted
  6. Projects and Performance: Q1 2025-26Noted

More from Lancaster Cabinet

All decisions
MeetingDecisionOutcome
28 Jul 2026 Provisional Revenue, Capital and Treasury Management Outturn 2025/26Resolved unanimously: (1) That the provisional outturn for 2025/26 be endorsed, including the transfers to and from R... Approved Open
28 Jul 2026 Exclusion of the Press and PublicResolved unanimously: That in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and publi... Decided Open
7 Jul 2026 Exclusion of press and publicResolved unanimously: (1) That, in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and ... Decided Open
9 Jun 2026 Reports from Overview and Scrutiny(8 Members (Councillors Bannon, Bottoms, Hart, Caroline Jackson, Peter Jackson, Riches, Stubbins & Tyldesley) voted i... Approved Open