Approved Planning 1 paper

AI summaryLancaster Planning Regulatory Committee approved replacement roofs, windows, doors and other external works at Jobcentre Plus, Mitre House, Church Street, subject to five conditions covering heritage details, slate samples and protected species mitigation.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFive conditions on time, plans, details, slate, species
MoneyNot stated
What happens nextPre-commencement conditions firstDetails of windows, RWG, and slate needed before work
Who it affectsJobcentre Plus, Mitre House, LancasterBuilding in Conservation Area near listed buildings

What was decided

The application was approved subject to five conditions: time limit, development in accordance with approved plans, submission of details of windows and rainwater goods, submission of slate, and protected species mitigation. Report P6, P71, P72

The case was reported to committee because the council has an interest in the land, taking it outside the scheme of delegation. Report P8

No Section 106 planning obligations were required. Report 8.2

Why

The refurbishment is considered a sympathetic alteration in a conservation area, with a neutral impact on the setting of surrounding listed buildings including the Grade I Judges Lodgings, and the Conservation Officer raised no objection subject to detail conditions. Report 2.1, P48

Surveys recorded common pipistrelle, soprano pipistrelle and noctule bats using the building, with two summer day roosts at risk. Mitigation including two bat boxes, five swift boxes and three smaller bird boxes, supervised by an ecologist, is considered sufficient to satisfy the Habitats Regulations. Report P50, P55, P56, P57, P60

The proposal aligns with the regeneration priority area policy EC5.2 by refurbishing the building for continued office use, and no trees are to be removed. Report P40, 9.1

What happens next

Pre-commencement conditions require submission and approval of window and rainwater goods details and a slate sample before works begin. Report P72, P26

The applicant will need a bat mitigation class licence from Natural England before licensable works proceed. Report P50, P51, P53, P54

Separate Scheduled Monument Consent may be required from Historic England if scaffolding or footings are placed on the scheduled monument, and this can be addressed by an advice note. Report P26

Options considered

  • Chosen: Approve with conditions. Sympathetic refurbishment, neutral heritage impact, sufficient bat mitigation, no amenity harm Report P6, P71, 9.1

Implications

  • Legal: The Habitats Regulations three tests must be considered; a Natural England Low Impact Class Licence and a method statement are required for works affecting bat roosts. Report P51, P52, P53, P54
  • Legal: If scaffolding or footings encroach on the adjacent Scheduled Monument, separate Scheduled Monument Consent from Historic England is required. Report P26
  • Equalities: Public Sector Equality Duty considered; no unjustified adverse impacts on protected characteristic groups identified. Report P65, P66
  • Other: The Local Planning Authority will obtain clarification on the conflicting rainwater goods material description (uPVC heritage versus powder coated aluminium) and update members before the meeting. Report P46

Who and where

  • Jobcentre Plus building and its continued use as office space Report P3, 9.1
  • Common pipistrelle and soprano pipistrelle bats using two summer day roosts in the building Report P50, P55
  • Nesting birds using the building Report P50, P57
  • Setting of the Lancaster Conservation Area and nearby listed buildings including the Grade I Judges Lodgings Report 2.1, P48
  • Adjacent Scheduled Monument (remains of a Roman bathhouse) Report 2.1, P26
  • Neighbouring residential and commercial properties in the Castle area Report P62, P63
  • Mature trees along the north-eastern elevation, to be retained and pruned under a separate Section 211 Notification Report P59

Timeline

  • 2025: Bat and bird surveys carried out at the building Report P50
  • 06/02/2023: Previous application 23/0018/TCA for tree works closed Report P23
  • 22 January 2025: Strategic Policies and Land Allocations DPD and Development Management DPD adopted Report 6.3, P35
  • Standard time limit condition: Development must commence within the standard period set by condition 1 Report P72

Plain English for the jargon

  • BauderFlex: A brand of flat roof membrane used to replace flat roofs
  • DOFF cleaning: A steam-based system for cleaning building exteriors such as render
  • DPD: Development Plan Document, a formal local plan document forming part of the Development Plan
  • Fascia: The board running along the lower edge of a roof where it meets the outer wall
  • Mansard: A roof with two slopes, the lower slope being steeper than the upper
  • NPPF: National Planning Policy Framework, central government planning policy
  • RWG: Rainwater goods, meaning gutters, downpipes and similar fittings
  • S106: Section 106 planning obligation, a legal agreement between a developer and the council
  • Scheduled Monument: A nationally important archaeological site given legal protection under the Ancient Monuments and Archaeological Areas Act
  • uPVC: Unplasticised polyvinyl chloride, a rigid plastic used in window frames and pipes
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

Resolved : That the application be approved subject to the following conditions: 1. Time limit. 2. Development in accordance with approved plans. 3. Submission of details (windows and RWG). 4. Submission of slate. 5. Protected species mitigation.
Word for word from the decision Lancaster published for this meeting. Source: committeeadmin.lancaster.gov.uk

Follow this further

Built from Lancaster's papers

What the report saysPro

Report to Planning Regulatory Committee

Agenda Item A8

Application Number 26/00268/FUL

Installation of replacement roofs, windows, doors, fascias, rainwater Proposal goods and other external decoration, new covered enclosure to external ventilation plant Jobcentre Plus Mitre House Application site Church Street Lancaster

Applicant [name removed] M Wakeman

Case Officer [name removed] No

Summary of Recommendation Approve with conditions.

(i) Procedural Matters

This application is reported to Planning Committee because it falls outside the Council’s Scheme of Delegation for the following reason: • The Council has an interest in the land.

1.0DESCRIPTION OF APPLICATION SITE AND SETTING

1.1Mitre House is located on Church Street in the centre of Lancaster. The site forms part of the Castle area and is surrounded by a mix of residential, commercial and municipal buildings.

2.0SITE CONSTRAINTS AND RELEVANT SITE ALLOCATIONS

2.1The site is located within the Lancaster Conservation Area and is within the setting of various listed buildings (Grade II listed Three Mariners c.15m to the east, Grade I listed Judges Lodgings c.5m to the south, Grade II listed 97-100 Church Street immediately to the west, Grade II listed Priory c.40m to the west and Grade II listed Round Tower c.15m to the west). The land adjacent to the north and west is designated as a Schedule Monument and immediately to the north of the building lies the remains of an ancient Roman bathhouse.

2.2The site is also allocated as a regeneration priority area (policy EC5.2) within the Local Plan.

Page 1 of 8 CODE Location Plan

3.0PROPOSAL

3.1This application seeks consent for the installation of replacement roofs, windows, doors, fascias, rainwater goods and other external decoration, new covered enclosure to external ventilation plant.

3.2The roofs are largely comprised of dual-pitched tiled roofs but also include mansards and flat dormers. The flat roofs will be replaced with a new BauderFlex roof membrane whilst the existing slates on the dual pitched roofs will be removed, stored and then will be provided with a new breathable felt membrane and new timber battens when required. Existing slates will then be re- used, and any new slates will be sourced to match (Burlington). Ridge tiles will be replaced with a dry ridge system and the verges will be replaced with a dry cloaked verge system.

3.3The existing windows are largely comprised of single glazed timber sliding sash throughout. The proposal will provide for double glazed timber sliding sash to the north, east and southern elevations of the building whilst the western elevation will be comprised of aluminium casement windows. Existing timber and aluminium doors will be retained or replaced like for like.

3.4The existing fascias are comprised of timber, and it is proposed to replace these with aluminium. The rainwater goods appear to be comprised of a mix of uPVC and cast iron and it is proposed to replace these with aluminium throughout. The external decoration is comprised of patch repairs to the render, light grey painting and cleansing through a DOFF cleaning system.

3.5The existing mechanical equipment is currently closed off with Heras fencing, and it is proposed that a more permanent solution is sought through a lightweight steel frame structure with a lightweight profiled metal roof.

Page 2 of 8 CODE 4.0 RELEVANT PLANNING HISTORY

4.1A number of relevant applications relating to this site have previously been received by the Local Planning Authority. These include:

Application Proposal Status Date Closed No. 23/0018/TCA Sycamore (G1) - Fell to ground level and remove all CLOSED 06/02/2023 arisings (x22 trees) Other Broadleaved Species (T1) - Fell to ground level and remove all arisings Sycamore (T3) - Sever Ivy to 1.5m above ground level reporting all structural defects Lime Species (T10) - Feel to ground level and remove all arisings

5.0CONSULTATION RESPONSES

5.1Statutory and non-statutory representations A summary of the comments received from statutory and non-statutory consultees is provided below.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Jobcentre Plus Mitre House Church Street LancasterReport 252 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 28 attended
ST
Councillor Sandra ThornberryChair, present
LB
Councillor Louise BelcherMember, present
MB
Councillor Martin BottomsMember, present
DB
Councillor Dave BrookesMember, present
KB
Councillor Keith BuddenMember, present
TF
Councillor Tom FishMember, present
AG
Councillor Alan GreenwellMember, present
JH
Councillor John HansonMember, present
JL
Councillor Jack LenoxMember, present
JL
Councillor John LivermoreMember, present
AO
Councillor Andrew OtwayMember, present
CP
Councillor Catherine PotterMember, present

All 28 on the meeting page

More from Lancaster Planning Regulatory Committee

All decisions
MeetingDecisionOutcome
1 Sep 2026 Bus Station Central Drive MorecambeResolved : That prior approval for demolition is required and is granted. Approved Open
1 Sep 2026 Car Park Nelson Street LancasterResolved : That the application be approved subject to the following conditions: 1. Development in accordance with Ap... Approved Open
1 Sep 2026 Auction Mart Car Park Thurnham Street LancasterResolved : That the application be approved subject to an additional condition regarding additional ground investigat... Approved Open
1 Sep 2026 Delegated ListThat the report be noted. Noted Open
27 Jul 2026 Land at Ashton Road LancasterResolved : That the application be approved subject to the following conditions: · the satisfactory completion of a L... Approved Open