[KD] (1) Key activities and progress made against the Future Model Programme Plan (Phase Two) and key programme milestones for February 2014 – May 2014 noted. (2) Budget of £15,000 approved to investigate the opportunities, costs and issues of developing shared corporate services with Lewes District Council.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Purpose To update Members on the progress made within the SSDS programme, with particular reference to the Future Model Programme Plan (Phase Two) as at January 2013, this being one of the key projects under the Corporate Plan Sustainable Performance theme (Project 2 – Efficiency).
Recommendation: Members are asked to:
i) Note key activities and progress made against the Future Model Programme Plan (Phase Two). ii) Note key programme milestones for February 2014 – May 2014 iii) To approve a budget of £15k to investigate the opportunities, costs and issues of developing shared corporate services with Lewes District Council
Contact: Julian Osgathorpe, Deputy Chief Executive, Telephone 01323 415008 or internally on extension 5008. [email protected]
or
Henry Branson, Senior Head of Infrastructure, Telephone 01323 415155 or internally on extension 5155. [email protected]
1.0Background/Introduction
1.1The Sustainable Service Delivery Strategy (SSDS) is a key response to the increasing cost and demand pressures facing the Council. It is a programme that was developed to promote a range of solutions, including internal transformation as well as increasing effective partnership working with other organisations.
In July 2013 Cabinet approved the adoption and implementation of Phase Two of the Future Model under Option 5 of the SSDS and delegated authority to the DRIVE Programme Board to run the programme within the allocated resources. The scope of Phase Two is:
• CMT/ Senior management • Housing
Page 1 of 7 • Revenues • Benefits • Fraud • Strategic performance • Democratic/ Civic services • Electoral services and local land charges • Community development, involvement and crime reduction • Tourism development marketing • Seafront services • Events • Sports and leisure • Finance – payments and income • Finance – procurement • Digital mail room • Customer contact activity currently carried out by Capita for revenues and benefits • Asset Management
This is the first update to Cabinet on the progress of Phase Two.
The Future Model Programme aims to improve service delivery whilst delivering savings estimated at £1.7m to £2m across the organisation. The current phase, Phase Two, is estimated to save £1.2m - £1.5m.
The Future Model describes a new way of organising and delivering council services, delivering efficiencies at the same time as putting the customer at the heart of all we do. Further details are available in the July 2013 Cabinet report.
2.0Sharing Corporate Services
2.1In addition to the current activity under Phase Two of the Future Model, an opportunity has arisen to explore the development of shared corporate services with Lewes District Council. It is proposed that iESE are instructed to work with the Councils to develop a brief for the piece of work which should provide a view on the following areas with regard to any proposal: • Options • Costs • Benefits (financial and non-financial) • Risks • Issues • Likely implementation pathway
The anticipated cost of this work will be capped at £15k to each council. A further report to Cabinet will outline the findings and recommend a way forward in due course.
Lewes District Council approved both the initiative and the budget for this piece of work at their Cabinet on 6th January 2014.
Page 2 of 7 3.0 Future Model Programme Highlights
3.1Summary of programme status
A key priority for August and September was mobilising the programme and ensuring that the appropriate contracts were in place. This was completed successfully and we will be working once more with Civica and Ignite as our principle implementation partners.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.