(1) Updates to future model programme plan (phase 2) including revised programme milestones noted. (2) Progress made in relation to alternative service delivery models for corporate services noted and approval given to the development of a detailed business case and implementation plans as outlined in the report.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Purpose To update Members on the progress made within the SSDS programme, with particular reference to the Future Model Programme Plan (Phase Two) and work on alternative service delivery models for Corporate Services.
Recommendation: Members are asked to:
i) Note the updates to the Future Model Programme Plan (Phase Two) including revised programme milestones. ii) Note the progress made in relation to alternative service delivery models for Corporate Services and approve the development of a detailed business case and implementation plans as outlined.
Contact: Henry Branson, Senior Head of Infrastructure, Telephone 01323 415155 or internally on extension 5155. [email protected]
1.0Background/Introduction
1.1The Sustainable Service Delivery Strategy (SSDS) is a key response to the increasing cost and demand pressures facing the Council. It is a programme that was developed to promote a range of solutions, both internal transformation and effective partnership working with other organisations.
This report presents an update on key initiatives carried out under the SSDS, namely:
In July 2013 Cabinet approved the adoption and implementation of Phase Two of the Future Model under Option 5 of the SSDS and delegated authority to the DRIVE Programme Board to run the programme within the allocated resources.
The Future Model Programme aims to improve service delivery whilst delivering savings estimated at £1.7m to £2m across the organisation. The
Page 1 of 6 current phase, Phase Two, is estimated to save £1.2m - £1.5m.
The Future Model describes a new way of organising and delivering council services, delivering efficiencies at the same time as putting the customer at the heart of all we do. Further details are available in the July 2013 Cabinet report.
1.3SSDS: Corporate Landlord
In December 2013 Cabinet approved the implementation of a corporate landlord model for strategic asset management and the development of a detailed implementation plan.
1.4SSDS: Shared Corporate Services
In February 2014 Cabinet approved work to investigate the opportunities, costs and issues of developing shared corporate services with Lewes District Council. Lewes District Council also approved this piece of work at their Cabinet on 6th January 2014.
2.0Future Model Programme Update
2.1Summary of programme status
In February 2014 we reported Future Model programme progress to Cabinet. In that report, it was noted that the Business Process Create and Construct workstream was progressing on schedule, but that there was work left over from Phase 1 to complete. It was also reported that two of the ten technology projects were behind schedule. The report updated Cabinet on key milestones in the next quarter, including activities to address the Phase 1 overrun and the technology issues.
In the next quarter leading to 31 May 2014 good progress has been made against a number of the scheduled programme milestones, including:
• Channel Shift Plan • Ongoing channel shift activities • Detailed plan for consultation with residents and tenants • First data migration for revenues and benefits • Induct EHL staff into Future Model programme • Further development of organisation design including both corporate management structures.
However, during February and March 2014, progress on the areas of the programme that were behind schedule was not satisfactory. This, allied with a range of technology questions that arose from the ‘create’ workshops, and needed to be answered before the ‘construct’ activity could continue, led the Programme Board to agree to suspend the Business Process Create and Construct workstream whilst detailed plans and solutions were developed to address these issues.
During April and May, the Senior Head of Infrastructure worked closely with
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.