(1) Following cycle routes taken forward to detailed design and construction as part of the County Council’s 2014/15 capital programme for local transport improvement initiatives: a. University to Town Centre and Seafront b. Town Centre to Seafront c. Horsey Way Section 1 (2) Agreement in principle, and subject to agreement by the Secretary of State for Communities and Local Government that the byelaw can be amended, that the Seafront cycle route along the promenade between the Wish Tower and Fisherman’s Green being taken forward by the County Council to detailed design with construction taking place as part of a future year’s capital programme beyond 2014/15. (3) Full Council recommended to authorise officers to take all necessary steps to seek and obtain approval from the Secretary of State for Communities and Local Government to an amendment to the current byelaw to enable the Council to allow, where appropriate, both un-segregated as well as segregated shared use of the seafront promenade by cyclists and pedestrians. (4) Agreement to the Horsey Sewer Route Section 3 being taken forward by the County Council to detailed design with construction taking place as part of a future year’s capital programme beyond 2014/15. (5) In view of the comments received during the consultation on the Town Centre to Hospital route, delegated authority given to the Senior Head of Development in consultation with the lead Cabinet member to agree to an adjusted route.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
COMMITTEE CABINET DATE 19 March 2014 SUBJECT Priority Cycle Routes
REPORT OF Senior Head of Development
Ward(s) All Purpose To inform Members of the results of the consultation undertaken by East Sussex County Council on six cycle routes identified in the adopted Cycling Strategy.
To seek approval for the routes to be taken forward to detailed design and construction.
To seek approval to amend the seafront byelaw to allow both unsegregated cycling as well as cycling in lanes on appropriate sections of the promenade .
Contact Lisa Rawlinson, Senior Specialist Advisor, 1 Grove Road, Eastbourne Tel no: (01323) 415250 E-mail: [email protected]
Recommendations 1. That Cabinet approve the following cycle routes to be taken forward to detailed design and construction as part of the County Council’s 2014/15 capital programme for local transport improvement initiatives:
a. University to Town Centre and Seafront b. Town Centre to Seafront c. Horsey Way Section 1
2. That Cabinet agree in principle, and subject to agreement by the Secretary of State for Communities and Local Government that the byelaw can be amended, that the Seafront cycle route along the promenade between the Wish Tower and Fisherman’s Green be taken forward by the County Council to detailed design with construction taking place as part of a future year’s capital programme beyond 2014/15.
3. That Cabinet recommend Full Council to authorise the officers to take all necessary steps to seek and obtain approval from the Secretary of State for Communities and Local Government to an amendment to the current byelaw to enable the Council to allow, where appropriate, both unsegregated as well as segregated shared use of the seafront promenade by cyclists and pedestrians.
4. That Cabinet agree the Horsey Sewer Route Section 3 be taken forward by the County Council to detailed design with construction taking place as part of a future year’s capital programme beyond 2014/15.
5. That in view of the comments received during the consultation on the Town Centre to Hospital route that delegated authority is given to the Senior Head of Development in consultation with the Cabinet Portfolio Holder to agree to an adjusted route.
1.0Introduction
1.1In February 2012, Cabinet approved the Cycling Strategy for Eastbourne. The principal objective of the Strategy is to identify a Borough-wide network of potential cycle routes which can then be provided as funding becomes available. This proposed network builds on both the existing cycle routes within the Borough as well as the new routes between the railway station and the eastern side of the town (the Horsey Cycle Route) and the western Seafront Cycle Route (along King Edwards Parade).
1.2The network of proposed cycle routes will provide linkages between principal employment, housing, recreational and tourist locations. The routes are prioritised in order to ensure those with the greatest potential to be delivered and those that would benefit the greatest number of people are taken forward at the earliest opportunity.
1.3The Strategy identified the following priority routes:
• University to Town Centre and Seafront • Town Centre to Seafront • Seafront (between the Wish Tower and Fisherman’s Green) • Langney to Sovereign Harbour and Sovereign Centre • Willingdon Drove • Town Centre to Hospital
1.4Of these routes the following were taken forward to preliminary design and formed the major part of the public consultation:-
• University to Town Centre and Seafront • Town Centre to Seafront • Seafront (along the promenade between the Wish Tower and Fisherman’s Green) • Town Centre to Hospital.
In addition further detailed work was undertaken on the Horsey Way Section 1 route (Railway Station to Ringwood Road) and the Horsey Way Section 3 route (Lottbridge Drove to Langney roundabout, including the Tollgate School link). These routes also formed part of the public consultation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.