Eastbourne Borough Council Cabinet approved this item on Wednesday 19 March 2014. Below is the council's own wording, with the papers it was decided on.
(1) Approval of capital allocation of no more than £350,000 from the £18m Housing Regeneration capital allocation for the purchase and refurbishment of retail and commercial elements of properties being purchased for the SHEP initiative, subject to the application of the conditions and procedures previously agreed for SHEP funding delegations. (2) Revised budget for the Eastbourne 2013-2015 LANB, of £4,758,000 agreed, to include: · 23 affordable rented homes made up of sixteen at Coventry Court, 3 at Tenterden Close and 4 at Belmore Road. · An additional 6 houses for shared ownership as part of the Coventry Court scheme, made up of 3 three bedroom houses and 3 two bedroom houses. · An additional 4 homes for market sale as part of the Belmore Road scheme made up of 4 two bedroom homes. (3) Delegated authority granted to Senior Head of Community, in conjunction with lead Cabinet member for finance and Chief Finance Officer, for purchase of site adjacent to Belmore Road ( Longstone Road) subject to final risk/financial appraisal. (4) Allocation of up to £850,000 as a loan facility in the Council’s capital programme to support economic development initiatives at Sovereign Harbour approved.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Subject: Eastbourne Housing and Economic Development Project (HEDP).
Report Of: Ian Fitzpatrick, Senior Head of Community.
Ward(s) All.
Purpose This report provides an update on the Eastbourne 2013-2015 Local Authority New Build programme and the Supporting Housing and Economic Progress initiative.
Decision Type: Key Decision.
Recommendation: Cabinet is recommended to: • Approve a capital allocation totalling no more than £350,000 from the £18m Housing Regeneration capital allocation for the purchase and refurbishment of retail and commercial elements of properties being purchased for the SHEP initiative, subject to the application of the conditions and procedures previously agreed for SHEP funding delegations. • Approve a revised budget for the Eastbourne 2013-2015 LANB, of £4,758,000 to include: o Twenty three affordable rented homes made up of sixteen at Coventry Court, three at Tenterden Close and four at Belmore Road o An additional six houses for shared ownership as part of the Coventry Court scheme, made up of three (3) x three bedroom houses and three (3) x two bedroom houses o An additional four homes for market sale as part of the Belmore Road scheme made up of four (4) x two bedroom homes • Delegate authority to the Senior Head of Community in conjunction with the Portfolio Holder for Finance the purchase of a site adjacent to Belmore Road (Longstone Road) subject to final risk/financial appraisal • Allocate up to £850,000 as a loan facility in the Council’s capital programme to support economic development initiatives at Sovereign Harbour
1.1This report considers a range of inter-linked housing and economic development projects and opportunities. All are related to the Housing and Economic Development Partnership (HEDP), a joint project set up in February 2013 by the Council and Eastbourne Homes Limited (EHL). The HEDP has a small team of officers working exclusively on projects for the initiative but also being used, as required, by the Housing Services team to help the wider strategic housing work of the Council as a whole.
1.2The HEDP team has been tasked with delivering a number of strategic projects for the Council, including the programme to develop new Council- owned homes. There has now arisen an opportunity to further expand this programme. This report requests approval for the appropriate resources and policy decisions to be in place to be able to take advantage of these new development and funding opportunities.
1.4In taking forward its work over the past year, the HEDP team has increasingly found itself needing to be able make use of both Housing Revenue Account (HRA) and General Fund (GF) resources. Current delegations of authority, agreed in September 2013 need to be revised to allow the project to operate more effectively as there is a risk that opportunities may be lost if this flexibility is not available for use when it is most needed. This report sets out and requests approval for those revisions.
1.5The Council has been working with development partners in order to secure development of sites that have extant planning permission for business use on Sovereign Harbour.
2.0Funding Mechanisms for HEDP
2.1At this early stage in the development of the HEDP’s work, it has not yet had cause to ask for consent from Members to draw upon the General Fund £20m capital allocation agreed in February 2013. This is because the nature of the work envisaged for the HEDP includes complex investment projects which have long lead in times.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.