Eastbourne Borough Council Cabinet agreed this item on Wednesday 10 December 2014. Below is the council's own wording, with the papers it was decided on.
(1) D raft budget proposals agreed for consultation. (2) Approach to dealing with changes in the expected resources available for the 2015/16 budget detailed in paragraph 5.3 of report agreed. (3) Subject to there being no material change in the government settlement, Cabinet minded to propose a council tax freeze for 2015/16.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Purpose: To summarise the main elements of the emerging 2015/16 revenue budget and capital programme that have arisen from the corporate and service financial planning process to date.
Contact: Alan Osborne, Chief Finance Officer, Tel 01323 415149 or internally on ext 5149
Recommendations: Members are asked to:
i) Agree the draft budget proposals for consultation.
ii) Agree the approach to dealing with changes in the expected resources available for the 2015/16 budget as detailed in 5.3.
iii) Agree that subject to there being no material change in the government settlement that Cabinet is minded to propose a council tax freeze for 2015/16.
1.0Introduction
1.1Each year the Council consults with a range of stakeholders on its detailed draft budget proposals for the following financial year. This follows consultation on the corporate plan and Medium Term Financial Strategy (MTFS), which is carried out over the summer and autumn. The results of the corporate plan consultation are reported elsewhere on this agenda.
1.2The Cabinet will consider initial responses to the consultations at this meeting and finally on 4 February 2015 in order to recommend a final budget for 2015/16 and amended capital programme to the Council on 18th February 2015.
1.3The process of service and financial planning is an integral part of the corporate planning cycle that looks over a medium term horizon. The corporate change programmes under DRIVE pick up the challenge of the MTFS.
1.4The MTFS agreed in July 2014 modelled the overall reduction in Government support by 40% in cash terms over the whole CSR period (2013/17) which equates to around 50% in real terms at past and projected levels of inflation.
1.5At the time of writing this report the Chancellors autumn statement is not
1 available, However last year the Government signalled a further 5 years of reductions in public spending over the life of the next parliament. Although there is an election next year all the main political parties are working on similar deficit reduction plans.
1.6In addition to changes in the amount of funding for local government, there were two significant changes that came into force in 2013/14 that give a greater volatility to local government finance over the medium term. These changes were the retention of a proportion business rates and the localisation of council tax support. The Council tax and Non Domestic rate tax bases are the subject of another report on this agenda.
1.7The Council has applied with other East Sussex authorities to be part of a single business rates pool which could see the Council increase its business rates retention increase by around £200k in 2015/16.
2.0Integrated corporate planning process
2.1In July 2014, the Council adopted its latest MTFS that set the platform for the service and financial planning process during the summer and autumn. The strategy set out a further 4 year rolling programme with savings targets of £2.7m recurring by 2018/19 (in addition to the £4.5m achieved in setting the 2011-2015 budgets)
2.2The overarching DRIVE programme forms the basis of Councils efficiency agenda and the sustainable service delivery strategy (SSDS) is a major component of the programme, which will deliver savings over the life of the MTFS. The Council’s move towards the ”future operating model” is set to contribute a further £1.2m of savings over the next two years to the general fund. Together with savings from procurement and shared services this provides the main emphasis of the current corporate efficiency programme.
2.3The Service and financial planning process is now a rolling three year period to reflect the MTFS and as well as providing £500,000 per annum of additional capital resource the savings programme is well developed to meet the overall target of £2.7m over the current cycle.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.