Eastbourne Borough Council Cabinet approved this item on Wednesday 10 December 2014. Below is the council's own wording, with the papers it was decided on.
(1) Option 3, formation of a new internal drainage board to include the Pevensey Levels, approved, and officers authorised to commence planning work with key partners. (2) D elegated authority given to the Senior Head of Infrastructure, in consultation with Leader of the Council, to take all necessary steps to contribute to the setting up of a new board.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Report Of: Henry Branson, Senior Head of Infrastructure
Ward(s) All
Purpose To consider the options appraisal regarding a new Internal Drainage Board (IDB) for Pevensey Levels, following the proposed Environment Agency dissolution of existing East Sussex IDD.
Decision Type: Key decision
Recommendation: That Cabinet ; a) approves Option 3: formation of a new IDB to include the Pevensey Levels, and authorises officers to commence planning work with key partners.
b) Delegated authority to be given to the Senior Head of Infrastructure in consultation with the Leader of the Council to take all necessary steps to contribute to the setting up of a new Board.
Contact: Sue Oliver, Manager, Specialist Advisory Team Telephone 01323 415360 or internally on extension 5360. E-mail address [email protected]
1.0Introduction
1.1Historically, the Environment Agency (EA) has acted as the Internal Drainage Board (IDB) for a number of Internal Drainage Districts (IDDs) in the South East. In 2011, the Chief Executive of the EA confirmed their intention to dissolve internally administered IDDs due to the view that arrangements for drainage districts should have a greater degree of local accountability. 1.2 There are three EA-administered IDDs in East Sussex: Pevensey Levels IDD, Ouse IDD and Cuckmere IDD. Part of Eastbourne sits within the Pevensey Levels IDD. There are 15,486 residential properties within Pevensey Levels IDD, and under current IDD management the majority are at a 1:200 or less risk of flooding (from the main river). 700 of these properties in the Langney area are at significant risk of surface water flooding. There are 533 businesses within Pevensey Levels IDD, the majority are at 1:200 or less risk of flooding (from main river) under the current IDD. Whilst IDBs are not responsible for main rivers (the EA retains management of these), IDBs pay annual
Page 1 of 7 precepts to the EA as a contribution to work on main rivers from which the IDD(s) benefits. For example, in the 2013/14 fiscal year, the East Sussex IDB paid the EA £109,370 for maintenance of main rivers. 1.3 The EA have asked the East Sussex Local Authorities about their views to dissolve the IDDs and the options for the future management of these drainage areas. The options under consideration are:
Option Description Additional Detail Option 1 No Local Authority Likely that Defra imposes IDB consensus as to what for Pevensey IDD drainage arrangement should be put in place Option 2 No Objection to IDB Drainage areas revert back to Dissolution; land-owner control; No Replacement IDB alternatively, recommend community-led water-level management. Option 3 New IDB New, independent Board to take over drainage area(s).
2.0Internal Drainage Boards
2.1An Internal Drainage Board is an independent local public authority that manages water levels within IDDs. Much of their work involves the maintenance of rivers, weirs, sluices, culverts, embankments, drainage channels, outfalls and pumping stations, facilitating drainage of new developments and advising on new planning applications. They have permissive powers with the IDDs to undertake such works as well as a statutory duty in regard to the environment and recreation when exercising their powers. They have a specific duty to further the conservation and enhancement of all designated environmental sites within their districts such as Sites of Special Scientific Interest (SSSIs) and RAMSAR sites (internationally protected wetland sites).
2.2There are currently 120 IDBs in England covering 1.2 million hectares (9.7% of England’s total land area). Defra is responsible for IDBs who work closely with the following: the EA, Lead Local Flood Authorities (LLFAs; ESCC is the LLFA for our area), and with LAs in regard to planning issues. 3.0 Options Appraisal
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.