Resolved
That the Grants report for 2013/14 be noted.
Eastbourne Borough Council Audit and Governance Committee noted this item on Wednesday 11 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Grants report for 2013/14 be noted.
EASTBOURNE BOROUGH COUNCIL GRANT CLAIMS AND RETURNS CERTIFICATION Year ended 31 March 2014
12 January 2015 INTRODUCTION Purpose of the report Fees This report summarises the main issues arising from the certification of grant claims and 2012/13 2013/14 2013/14 returns for the financial year ended 31 March 2014. FINAL PLANNED OUTTURN Audit Commission regime CLAIM OR RETURN FEE £ FEE £ FEE £
We undertake grant claim and return certification as an agent of the Audit Commission, in Audit Commission regime accordance with the Certification Instructions (CI) issued by them after consultation with Housing benefit subsidy 17,140 11,062 11,062 the relevant grant paying body. Our work is undertaken in accordance with the Statement of Responsibilities issued by the Audit Commission. National non domestic rates return 3,480 - - For those claims with a value of between £125,000 and £500,000, we conduct only a Pooling of housing capital receipts 1,730 1,530 1,530 limited review of the overall control environment before certifying the claim. Grant claims below £125,000 are not subject to audit arrangements. TOTAL AUDIT COMMISSION REGIME FEES 22,350 12,592 12,592 After completion of the tests contained within the CI the grant claim or return can be certified with or without amendment or, where the correct figure cannot be determined, may be qualified as a result of the testing completed. Sample sizes used in the work on Other certification work the housing and council tax benefit subsidy return and the methodology for the Decent Homes Backlog Funding - - 2,000 certification of all grant claims are prescribed by the Audit Commission. Other certification work TOTAL CERTIFICATION FEES 22,350 12,592 14,592
We have also been asked to certify the Decent Homes Backlog Funding return on behalf of the Council, for submission to the Homes and Community Agency (HCA). The work does We were able to reduce the fee for our certification work on the housing benefit subsidy not form part of the certification regime with the Audit Commission. This work was an in 2013/14 as the claim no longer included amounts for council tax benefits, and we were agreed upon procedures review to test a sample of amounts claimed by the Council from able to better coordinate the work undertaken by internal audit. the HCA funding allocation. The National non domestic rates return did not require certification in 2013/14 following Fees changes to the arrangements for retaining local shares of non domestic rates income.
A summary of the fees charged for certification work for the year ended 31 March 2014 is shown to the right. Appendix I of this report shows the action plan to improve the arrangements for preparing grants and other returns as a result of the 2013/14 findings. We recognise the value of your co-operation and support and would like to take this opportunity to express our appreciation for the assistance provided during the course of our certification work.
1 Key findings Below are details of each grant claim and return subject to certification by us for the financial year to 31 March 2014. Where our work identified issues which resulted in either an amendment or a qualification (or both), further information is provided. An action plan in respect of these matters is included at Appendix I of this report.
CLAIM OR RETURN VALUE (£) QUALIFIED? AMENDED? IMPACT OF AMENDMENTS (£) Audit Commission regime
Housing benefit subsidy 49,369,623 Yes No See note below on qualification and potential DWP recovery
Pooling of housing capital receipts 1,479,555 No No -
Other certification work
Decent Homes Backlog Funding 2,667,372 N/A No -
HOUSING BENEFIT SUBSIDY FINDINGS AND IMPACT ON RETURN
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Grants Report 2013/14.Report | 79 KB | DownloadRead as text |
Follow Eastbourne Borough Council Audit and Governance Committee at Lewes and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Item 11 (part) - Scrutiny Committee Work Programme, update on Local Government Reorganisation programme1) That the Committee continue to maintain oversight of Local Government Reorganisation developments; 2) A standing L... | Decided | Open |
| 9 Sep 2026 | Date of the next meetingResolved to note that the next meeting of the Audit & Governance Committee was scheduled to be held on 25 November 20... | Noted | Open |
| 24 Jun 2026 | Treasury Management Annual Report 2025/26Resolved to note the . | Noted | Open |
| 24 Jun 2026 | Annual Report of Eastbourne Borough Council's Audit and Governance Committee 2025-26RESOLVED to approve the recommendations set out in the Annual Report of the Audit and Governance Committee for submis... | Approved | Open |
| 24 Jun 2026 | Draft Internal Audit Plan for 2026/27Resolved to agree the proposed Internal Audit Plan ... view the full minutes text for item 11. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.