Resolved
That the Annual Audit Plan for 2014/15 be noted.
Eastbourne Borough Council Audit and Governance Committee noted this item on Wednesday 11 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Annual Audit Plan for 2014/15 be noted.
EASTBOURNE BOROUGH COUNCIL AUDIT PLAN TO THE AUDIT AND GOVERNANCE COMMITTEE Audit for the year ending 31 March 2015
27 February 2015 EXECUTIVE SUMMARY We are pleased to present our Audit Plan for the year ending 31 March 2015. This plan Fees summarises the work that we propose to undertake in respect of our audit of Eastbourne Borough Council for the 2014/15 financial year. The proposed core audit fee for the year is £90,374 plus VAT. Our Planning Letter 2014/15 had previously proposed a fee of £88,920. We have revised Significant Risks this to include an adjustment of £1,454 for work previously undertaken as part of the Our audit is designed to respond to significant risks and identify where we intend to focus certification work on NDR income (£900) and the council tax support schemes (£554) our resources in providing our opinion on the financial statements and our value for money which we are now required to undertaken as part of the audit of the accounts. conclusion. Summarised below are the significant risks we are currently aware of: Key outputs FINANCIAL STATEMENTS The key reports, opinions and conclusions from the audit will be: Auditing standards presume that a risk of management override of controls is present in REPORT DATE all entities and require us to respond to this risk by testing the appropriateness of accounting journals and other adjustments to the financial statements, reviewing Report on any significant deficiencies in internal controls, if June 2015 accounting estimates for possible bias and obtaining an understanding of the business required, based on the results of our interim audit visit rationale of significant transactions that appear to be unusual. 23 September 2015 Final report to those charged with governance Auditing standards presume that there are risks of fraud in revenue recognition. These Audit & Governance Ctte risks may arise from the use of inappropriate accounting policies, failure to apply the Independent auditor’s report including: By 30 September 2015 stated accounting policies or from an inappropriate use of estimates in calculating revenue. • Opinion on the financial statements • Value for money conclusion The Council has replaced its housing benefits system from Northgate Iworld to Civica OpenRevenues during the year. There is a risk that benefit claimant data may not have • Certificate been accurately and completely transferred between the systems, which could affect the calculations of on-going benefit expenditure awarded to claimants. Assurance statement on the Whole of Government Accounts By 7 October 2015 return The Code of practice for Local Authority Accounting 2014/15 includes the new Summary of findings from the audit in the Annual Audit October 2015 consolidation suite of accounting standards (IFRS 10, 11 and 12). This introduces a new Letter definition of control, which should be used to determine whether entities and joint arrangements should be consolidated into Group financial statements, along with the basis of accounting for the Council’s and Group accounts.
USE OF RESOURCES
The Medium Term Financial Strategy has identified further savings requirement of £0.5 million in each of the three years from 2016/17, to be met from efficiencies and procurement savings. Identifying the required level of savings from 2016/17 will be a challenge and is likely to require difficult decisions around service provision and alternative delivery models.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Audit Plan 2014/15.Report | 94 KB | DownloadRead as text |
Follow Eastbourne Borough Council Audit and Governance Committee at Lewes and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Item 11 (part) - Scrutiny Committee Work Programme, update on Local Government Reorganisation programme1) That the Committee continue to maintain oversight of Local Government Reorganisation developments; 2) A standing L... | Decided | Open |
| 9 Sep 2026 | Date of the next meetingResolved to note that the next meeting of the Audit & Governance Committee was scheduled to be held on 25 November 20... | Noted | Open |
| 24 Jun 2026 | Treasury Management Annual Report 2025/26Resolved to note the . | Noted | Open |
| 24 Jun 2026 | Annual Report of Eastbourne Borough Council's Audit and Governance Committee 2025-26RESOLVED to approve the recommendations set out in the Annual Report of the Audit and Governance Committee for submis... | Approved | Open |
| 24 Jun 2026 | Draft Internal Audit Plan for 2026/27Resolved to agree the proposed Internal Audit Plan ... view the full minutes text for item 11. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.