Resolved
Variation to the capital programme of £500,000 for continued work on Devonshire Park, ahead of the final scheme being brought back to Cabinet in December, approved.
Eastbourne Borough Council Cabinet approved this item on Wednesday 21 October 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Variation to the capital programme of £500,000 for continued work on Devonshire Park, ahead of the final scheme being brought back to Cabinet in December, approved.
1.1This report recommends that funding for some of Stage 4 of the Devonshire Park design works is started before the December Cabinet decision on the overall scheme, in order that the procurement of the main contractor can be managed as effectively as possible. This forward funding will allow the professional team to prepare some of the detailed designs which will be essential part of the tender documents. By advancing the work it will be possible to engage a contractor as early as possible and gain their input into how the project is delivered. This will mitigate risk and encourage the most cost effective tenders.
1.2In advance of a decision on the main project due in December the Council can set aside funding from reserves.
Page 1 of 4 2.0 Proposal
2.1The proposal is to advance fund a total of £498,000 for design and procurement work for the period November to December 2015. This represents some 35% of the total approved Stage 4 fees.
2.2This cost is based on fee rates which the Council tendered previously and has contracted for with Levitt Bernstein (multi-disciplinary design team), Neill Woodger Associates (theatre consultant and acoustician), Huntley Cartwright (quantity surveyor) and Focus (project manager).
2.3The Council can fund this work using the capital programme (revenue) reserve which had a balance of £1.583m as at 31 March 2015.
3.0Relationship with Corporate Plan and other Council policies
3.1The Devonshire Park scheme is a key Corporate Priority with the objective of creating a cultural destination which is one of the most iconic locations in the South East.
4.0Consultations and communications
4.1The scheme has been the subject of ongoing consultation with a wide range of partners and stakeholders. The governance structure includes a Partnership Group which includes representatives of the Chamber of Commerce, Conference Bureau, LTA, Historic England and other internal and external stakeholders.
4.2This proposal was discussed and agreed at the 8th September 2015 meeting of the Project Board.
5.0Business case
5.1A delivery programme for the construction works has been carefully developed to take advantage of the quieter business periods where feasible, to minimise disruption generally, and keep the construction periods as condensed as possible and therefore limit, as much as practicable, the impact on the income generation of the site.
5.2Additionally, the works have been scheduled to take place at the earliest opportunities to minimise the impact of inflation on the project and therefore optimise the budget available.
5.3This careful planning has driven a necessarily tight programme where if certain windows of opportunity are missed they will not recur for 12 months. To de-risk the project where there is opportunity to do so, a schedule of enabling works has been identified to take place during 2016.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Devonshire Park redevelopment: forward funding of design work (KD).Report | 60 KB | DownloadRead as text |
Follow Eastbourne Borough Council Cabinet at Lewes and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes of the meeting held on 15 July 2026Resolved – That the minutes of the meeting held on 15 July 2026 be approved and the Chair authorised to sign them as ... | Approved | Open |
| 16 Sep 2026 | Housing Services Progress and Performance Report - 2026/27 - Quarter 1(Non-Key Decision): To note the Quarter 1 2026/27 housing services progress and performance position, including areas... | Noted | Open |
| 16 Sep 2026 | Portfolio Progress and Performance Report 2026/27 - Quarter 1(Non-Key Decision): 1) To note progress and performance for Quarter 1 2026/27. To enable Cabinet Members to consider ... | Noted | Open |
| 16 Sep 2026 | Revenue and Capital Financial Monitoring Report - Quarter 1 2026/27(Key Decision): 1) To note the Quarter 1 forecast financial position for 2026/27 and the associated risks. 2) To dele... | Noted | Open |
| 16 Sep 2026 | Eastbourne Local Plan (Proposed Submission Version Plan) Regulation 19(Key Decision): Cabinet is asked to Recommend to Full Council that it: 1) Agrees the Proposed Submission Local Plan (... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.