(KEY) (1) That the progress to date of the scheme be noted. (2) To approve the proposed works to the Winter Garden and instruct the Director of Tourism & Enterprise and the Assistant Director for Legal & Democratic Services, in consultation with the lead Cabinet members for Tourism and Leisure Services and Financial Services, either to complete the relevant contract terms with Vinci Construction UK or to pursue alternative procurement arrangements as appropriate . (3) To approve the proposed revision to the capital programme, with the addition of a further £160,000 to enable refurbishments to the Winter Garden toilets to be reinstated, bringing the scheme to £53.96m gross (£48.36m net of guaranteed contributions) in order to deliver the whole scheme as recommended by the Project Board. (4) To note that the business plan is expected to meet target. (5) To note that the Council can take advantage of a VAT exemption which would increase revenues by a minimum of £250,000 per annum.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Subject: Update on the Devonshire Park Redevelopment and proposals for the refurbishment of the Winter Garden
Report of: Director of Tourism & Enterprise
Cabinet member: Cllr M Bannister
Ward(s): Meads Purpose of the To provide an update on the redevelopment of Devonshire Park report: including the budget position. To obtain agreement for the refurbishment of the Winter Garden, in order that the relevant part of the construction contract with Vinci Construction UK (Vinci) can be finalised.
Decision type: Key
Recommendation: Cabinet is recommended to: a) note the progress to date of the scheme b) approve the proposed works to the Winter Garden and instruct the Director of Tourism & Enterprise and the Asst. Director , Legal & Democratic Services to complete the relevant contract terms with Vinci Construction UK c) approve a revision to the capital programme for this scheme to £53.8m gross (£48.2m net of guaranteed contributions) in order to deliver the whole scheme as recommended by the Project Board d) note the business plan is expected to meet target e) note that the Council can take advantage of a VAT exemption which will increase revenues by a minimum of £250,000 per annum.
Reasons for When the contract for the redevelopment was let to Vinci the recommendations: work to the Winter Garden was reserved to allow more detailed investigations of the structure and an evaluation of the options. The contract with Vinci provides for this work at the Council’s discretion and it is now appropriate to finalise this element of the contract. For the reasons set out in this report the costs of the overall scheme have increased and it is necessary to make an allowance for this in the capital programme.
Contact: Graham Cook, Programme Manager, Devonshire Park Redevelopment – [email protected] [phone removed] Executive Summary
This report addresses two issues: the need to agree the works to be carried out in the Winter Garden; the need to increase the capital programme because of cost increases; it also provides an update on the progress of the overall programme and the business case.
The programme has already delivered: the external refurbishment of the Devonshire Park Theatre and the installation of modern boilers; a new building for players at the International tennis Tournament – the building was ready in time for the 2017 tournament and was well received by the players and the LTA; a new show court which will be played on at the 2018 International Tournament and a new irrigation system serving all the courts; finally, construction of two practice courts will commence in September 2018. This investment has secured the women’s tournament for 10 years and the return of the men’s tournament to Eastbourne.
The major contract with Vinci for the refurbishment of the Congress Theatre and the construction of the Welcome Building is well underway. The new mechanical and electrical systems are now being fitted in the Congress and the new seats procured. The basement of the Welcome Building is complete and the steel frame will start to be erected soon. Both these buildings will open March 2019.
This work will address the long term issues of overheating, poor lift access and limited acoustics in the Congress and provide a new 1,00m2 conference/exhibition hall with associated break out and reception spaces in the Welcome Building. The scheme will provide pedestrian access through all 3 buildings and a new Plaza which will unify and enhance the entrance to the site.
The original Business Case supporting the Council’s investment in this scheme has been reviewed and indicates that the planned return can be achieved.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.