(KEY) (1) That the achievements and progress against Corporate Plan priorities for 2017/18, as set out in Part A of the report be noted. (2) That the general fund, housing revenue account and collection fund financial performance for the quarter ended December 2017, as set out in part B of the report, be agreed. (3) That the amended capital programme as set out in appendix 4 of the report be agreed. (4) That the Treasury Management performance as set out in section 5 in part B of the report be agreed. (5) That the write offs as set out in the exempt appendix be approved.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
1.1The performance of the Council is of interest to the whole community. People expect high quality and good value for money services. Performance monitoring, and a strong performance culture helps us to ensure we continue to deliver excellent services and projects to our communities in line with planned targets.
1.2This report sets out the Council’s performance against its targets and projects for the third quarter of 2017/18 (October to December 2017).
1.3The Council has an annual cycle for the preparation, delivery and monitoring of its corporate and service plans. This cycle enables us regularly to review the Council’s work, and the targets it sets for performance, to ensure these continue to reflect customer needs and Council aspirations.
2.0Themes and Priority Visions
2.1The Corporate Plan was developed with four themes to focus delivery of improvement activity for the borough. Each of these themes had its own priority vision for how the authority and its stakeholders wanted Eastbourne to develop. Performance is measured against these themes and objectives.
3.02017/18 Q3 Performance Overview
3.1Appendix 1 provides detailed information on progress and performance for Members’ consideration, clearly setting out where performance and projects are ‘on track/on target’ and where there are areas of under-performance/concern. Where performance or projects have not achieved target, an explanation is provided, together with a summary of the management action that has been taken to address this. The Appendix is structured around the key theme areas. 3.2 The Council uses a Project and Performance Management System (Pentana - formerly known as Covalent) to record, monitor and report progress and performance. The system uses the following symbols to indicate the current status of projects and performance targets:
Performance that is at or above target Project is on track Performance that is slightly below target but is within an agreed (usually +/- 5%) tolerance Projects where there are issues causing significant delay or change to planned activities Performance that is below target Projects that are not expected to be completed in time or within requirements Project has completed, been discontinued or is on hold
4.0Summary of Progress and Performance – Q3 2017/18
4.1Prosperous Economy
Achievements 13 units at Pear Tree Court and 4 units at Tideswell Rd were completed this quarter. Improvement in town centre vacancy rates at 5.51% against a target of 7.1%. Arndale Centre Extension is progressing well and the front two units are to be handed over to Next and H&M for fit out in May. Work on the access road to serve the next phase of the Sovereign Harbour Innovation Park (SHIP) and the community centre was completed in December. Successfully delivered The Eastbourne Beer Festival, Eastbourne Bonfire Society Procession, Beachy Head Marathon and 10K and Remembrance Sunday Service this quarter.
Issues / missed targets A total of 49 net additional homes were provided in Q3 against a target of 61. The annual target of 245 homes is unlikely to be met and it is estimated that 114 dwellings will be completed by year end.
4.2Quality Environment
Achievements 100% of major planning applications were processed within 13 weeks. Tenders have been received and reviewed for the Town Centre Public Realm Improvements. Wooden bollards were installed in Hampden Park in December. This project has been completed. Issues Percentage of Other planning applications processed within 8 weeks has reduced to 73% against a target of 80%.
4.3Thriving Communities
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.