(Key decision): (1) To approve the business case outlining the investment potential and development opportunities at Downs Leisure Centre, Sutton Road, Seaford. (2) To approve the capital investment of £17,200,000 (including professional fees ) to fund the project up to and including construction, subject to sign off of the proposed leases on terms no less favourable than set out at exempt appendix D to the report. (3) To delegate authority to the Director of Regeneration and Planning in consultation with the Lead Member for Finance, the Chief Finance Officer, and the Assistant Director – Legal and Democratic Services, to progress the project through the Energy & Sustainability Joint Venture if they consider it appropriate and at an appropriate future stage to decide if the project should be put forward to the JV Steering Board for inclusion as a Part 1 and/or Part 2 project. (4) To delegate authority to enter into a lease (or leases) of the properties to the Director of Regeneration and Planning, in consultation with the Strategic Property Board; such delegation to include authorisation not to dispose by auction or invitation of tenders following public advertisement (sought under Contract Procedure Rule 18.1) for those leases. (5) To delegate authority to the Director of Regeneration and Planning to exercise the break clause, or enter into a surrender of the lease in respect of Age Concern.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Title: Regeneration and Development: Sutton Road, Seaford
Report of: Ian Fitzpatrick, Director of Regeneration and Planning
Cabinet member: Councillor Andy Smith, Regeneration and Business Councillor Bill Giles, Finance
Ward(s): Seaford South
Purpose of report: This report sets out development proposals at the combined site on Sutton Road, Seaford known as Downs Leisure Centre. The report also includes a summary of the programme and concludes with a breakdown of the project costs and a financial summary, together with an outline of the status of potential new lettings and negotiations with the existing tenants.
Decision type: Key decision
Officer (1) To approve the business case outlining the investment recommendation(s): potential and development opportunities at Downs Leisure Centre, Sutton Road, Seaford.
(2) To approve the capital investment of £17,200,000 (including professional fees) to fund the project up to and including construction, subject to sign off of the proposed leases on terms no less favourable than set out in Appendix D.
(3) To delegate authority to the Director of Regeneration and Planning in consultation with the Lead Member for Finance, the Chief Finance Officer, and the Assistant Director – Legal and Democratic Services, to progress the project through the Energy & Sustainability Joint Venture if they consider it appropriate and at an appropriate future stage to decide if the project should be put forward to the JV Steering Board for inclusion as a Part 1 and/or Part 2 project.
(4) Delegate authority to enter into a lease (or leases) of the properties to the Director of Regeneration and Planning, in consultation with the Strategic Property Board; such delegation to include authorisation not to dispose by auction or invitation of tenders following public advertisement (sought under Contract Procedure Rule 18.1) for those leases. (5) Delegate authority to the Director of Regeneration and Planning to exercise the break clause, or enter into a surrender of the lease in respect of Age Concern.
Reasons for A strategic opportunity has arisen to provide a ground- recommendations: breaking mixed-use development of the Council’s landholdings within the Sutton Road site in Seaford known as Downs Leisure Centre. The proposed scheme will create new health space, employment opportunities, and a holistic approach to health and wellbeing for residents.
Contact Officer(s): Name: Bee Lewis Post title: Head of Capital Development (Interim) E-mail: [email protected] Telephone number: 01323 415521
1 Information
1.1LDC owns the freehold of the site at Sutton Road, Seaford known as Downs Leisure Centre. A plan of the site is attached at Appendix A.
1.2The site is subject to several leasehold interests, including:
(a) Downs Leisure Centre, including car parking, leased to Wave Leisure
(b) Downs 60+ Club, leased to Age Concern. The lease contains a landlord’s break clause on providing 6 months’ notice.
1.3Seaford is the largest town in the district with a population of 24,000. The Town Council is currently developing the Neighbourhood Plan which sets out key objectives for the parish. Seaford has a higher than average instance of over 65s (30% compared to 18% nationally) and a high proportion of jobs in the town are in the health and education sectors.
1.4It is clear from comments within the local community that the provision of health services is an ongoing concern, with both GP surgeries struggling to meet the current demand. Much of the capacity issue relates to the space the two surgeries have available to work in. As new houses are built, the demand for services will increase.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.