Revenue and Capital Outturn Report 2025/26 - Quarter 4
NotedExecutive4 papers
AI summaryLewes District Council Cabinet notes a balanced 2025/26 outturn: General Fund even, Housing Revenue Account £138,000 underspend, and capital spending £0.15 million under a £56.5 million budget. Virement authority delegated to the Director of Finance.
Written from the decision and the officer reportPDF Pro
OutcomeNotedGeneral Fund balanced, HRA £138k underspend
Money£56.3m capital spend, £0.15m net underspendAgainst revised capital budget of £56.5 million
What happens nextStatement of Accounts due by November 2026Final accounts adjustments to follow
Who it affectsLewes District Council services and housing tenants. Including regeneration and housing stock
What was decided
Cabinet noted the final 2025/26 outturn position and the financial risks and pressures set out in the report. Report P9
Authority was delegated to the Director of Finance and Performance and the finance portfolio holder to apply budget virements to manage the overall budget.
Cabinet noted Appendices 1 to 3 covering capital programme monitoring, reserves and a glossary. Report P72
Why
The Council has a legal duty to produce annual accounts; the outturn supports openness and accountability ahead of the November 2026 audit. Report P1
The General Fund was balanced through lower service spending after Quarter 3, allowing the budgeted transfer from reserves to be met from contingencies and preserving the General Reserve. Report P5, P11
The HRA outturn improved after a 30-year Business Plan review cut the budget by £447k, a one-off backdated Feed-in Tariff receipt and £40k of efficiencies offset a £434k repairs and £106k disrepair overspend. Report 8.2, 8.3, 8.4
What happens next
The Statement of Accounts will be audited and published by November 2026, with any material adjustments reflected in that process. Report P1, P3
Capital variances will be reviewed by the Capital Programme Oversight Board as part of 2026/27 financial planning, with some budgets reprofiled into 2026/27. Report P48
The Council will need to deliver significant savings by 2027/28 to maintain a sustainable financial position, with continued budget discipline and monitoring of approved savings. Report P68
The money
£138,000 HRA provisional outturn underspend against revised budget Report P7, P29, 8.2
£152,000 HRA provisional surplus versus a budgeted £14,000 contribution to reserves Report P7, P29
£56.3 million Total capital programme outturn expenditure Report P8, 9.1, P59
£56.5 million Revised capital programme budget Report P8, 9.1
£0.15 million Net capital programme underspend Report P8, 9.1, P59
£0.84 million General Fund capital underspend, mainly regeneration slippage Report P8, 10.1
£0.7 million HRA capital overspend from accelerated major works Report P8, 11.1
£447,000 Reduction to the HRA original budget after 30-year Business Plan review Report 8.2
£434,000 Repairs and maintenance overspend (responsive and void repairs) Report 8.4
£106,000 Disrepair compensation and legal costs within HRA Report 8.4
£2.4 million HRA Major Works and Improvements overspend Report 11.2
£1.9 million HRA Development Schemes underspend (new build and acquisitions) Report P46
£2.7 million Regeneration programme underspend against a £32.2 million revised budget Report 10.3
£1.66 million General Fund Housing overspend, mainly Warm Homes Local Grant Report 10.2
£1.1 million Community Infrastructure Levy programme overspend Report 10.4
£500,000 Increase in LDC earmarked reserves at year end Report P53
£2,039,000 General Fund balance (unchanged) Report P53
£0.749 million Council Tax collection fund closing balance surplus Report 14.1
£0.471 million Business Rates collection fund closing balance surplus Report 14.1
Options considered
Chosen: Apply budget virements to support effective management of the overall budget. Delegated to Director of Finance and Performance and portfolio holder for finance to allow in-year flexibility
Chosen: Note the final outturn position and associated financial risks and pressures. Statutory accountability ahead of the November 2026 audit Report P1, P9
Implications
Financial: General Fund balanced; HRA £138k underspend with £152k provisional surplus adds limited resilience to the ring-fenced account. Report P5, P7, P58
Financial: Capital programme £0.15m net underspend against £56.5m revised budget, with some schemes reprofiled into 2026/27. Report P8, P48, P59
Financial: Significant savings are required by 2027/28 to maintain a sustainable financial position. Report P68
Risk: Recurring service pressures, demand-led expenditure and reliance on in-year mitigations present medium-term financial risk. Report P9, P61, P65
Risk: Ongoing HRA pressures in repairs, voids and disrepair costs require close monitoring despite the favourable year-end position. Report P66
Risk: Capital programme risks remain where delivery depends on external funding, procurement timetables and multi-year scheme profiling. Report P67
Legal: No legal implications arise directly from the report. Report 16.1
Equalities: No Equality and Fairness implications. Report 18.1
Climate: No environmental sustainability implications arise directly from the report. Report 19.1
Who and where
Lewes District Council taxpayers and service users Report P4, 14.1
Council housing tenants, affected by accelerated major works, repairs, voids and disrepair costs Report 8.4, 11.2
Precepting authorities (county, police and fire) and central government, who share the Collection Fund surplus and deficit Report P54, 14.1
Areas covered by Town Deal and Levelling Up Fund regeneration schemes, with delivery extended into 2026/27 Report 10.3
Recipients of Warm Homes Local Grant-funded housing improvements Report 10.2
Timeline
2025/26: Outturn period covered by the report Report P2
During 2025/26: 30-year HRA Business Plan review completed, reducing budget by £447k Report 8.2
31 March 2026: Council Tax and Business Rates collection fund balance date Report 14.1, P54
2026/27: Council Tax surplus share of £109k and Business Rates share of £188k expected Report 14.1
By November 2026: Statement of Accounts to be audited and published Report P1
By 2027/28: Significant savings required to maintain a sustainable financial position Report P68
Plain English for the jargon
General Fund: The council's main revenue account for non-housing services.
Housing Revenue Account (HRA): A ring-fenced account for managing the council's own housing stock, including rents, maintenance and borrowing costs.
Outturn: The actual income and expenditure recorded at the end of the financial year.
Virement: Moving budget between headings to manage the overall budget.
Collection Fund: A statutory account recording council tax and business rates collected and distributed to the council and precepting authorities.
Feed-in Tariff: A government payment for electricity generated by solar panels and other renewables, paid to the generator.
Community Infrastructure Levy (CIL): A charge on new development used to fund local infrastructure.
Capital Programme Oversight Board (CPOB): The council's body that reviews capital scheme delivery and profiling.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item21
Resolved
(Key Decision): 1) To note the final outturn position for 2025/26 and the associated financial risks and pressures. 2) To delegate authority to the Director of Finance and Performance and the portfolio holder for finance to apply the required budget virements to support effective management of the overall budget. 3) To note Appendices 1 to 3 to the Cabinet Report.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
All local authorities have a legal duty to produce annual accounts in support of openness and accountability. The Statement of Accounts is due to be audited and published by November 2026. This report therefore presents the year-end outturn position for management reporting purposes, subject to any final accounts’ adjustments.
This report summarises the Council’s financial performance and use of resources in 2025/26 against the revised budget. It precedes the production of the formal Statement of Accounts, so any material final accounts adjustments will be reflected through that process.
As with all outturn reports, some balances may change as year-end balance sheet reviews are completed and reflected in the Statement of Accounts. The statutory audit opinion will apply to the final Statement of Accounts.
Lewes District Council continues to deliver a wide range of statutory and discretionary services in a challenging financial environment. The 2025/26 outturn reflects ongoing demand, inflationary and delivery pressures, alongside the impact of active budget management across services.
The General Fund outturn is balanced. This has been achieved through lower service expenditure since Q3, enabling the budgeted transfer from reserves to be met from contingencies and preserving the General Reserve position.
Service pressures reported during the year reduced by year end, and remaining pressures set out in this report are largely addressed within the 2026/27 budget.
The HRA Outturn is a £138k underspend against the revised budget, with a £152k provisional surplus compared with a £14k budgeted contribution to reserves. This follows a review of the 30-year Business Plan, which reduced the budget by £447k. The improved position reflects a one-off backdated Feed-in Tariff receipt from solar panels and £40k of wider efficiencies, which helped offset significant pressures in repairs and maintenance, including responsive and void repairs and disrepair-related legal costs, avoiding a draw on working balances.
The capital programme delivered broadly in line with the revised budget, with total expenditure of £56.3 million against a budget of £56.5 million, giving a small net underspend of £0.15 million. The General Fund underspent by £0.84 million, mainly due to slippage on regeneration schemes, while the HRA overspent by £0.7 million because of accelerated major works. Overall variances were largely timing-related, requiring some budgets to be reprofiled into 2026/27, rather than reflecting underlying financial pressures.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.