Eastbourne Borough Council Cabinet noted this item on Wednesday 12 December 2018. Below is the council's own wording, with the papers it was decided on.
(Key decision): (1) To delegate authority to the Chief Finance Officer and Director of Planning and Regeneration, in consultation with the Cabinet Member for Place Services to fund up to £25,000 for the commissioning of Clear Sustainable Futures to undertake the feasibility study of deploying sustainable energy generation at the Sovereign Leisure Centre (2) To delegate authority to the Chief Finance Officer in consultation with CMT and the Cabinet Member for Place Services, to proceed with the recommended sustainable energy solution for the Sovereign Leisure Centre if this is demonstrated to be a viable investment up to a value of £1.45m. (3) To note that a similar request is being made to Lewes District Council to progress viability analysis on their projects at Avis Way depot and Sutton Road and that the work is being conducted concurrently with knowledge being shared.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Report of: Ian Fitzpatrick, Director of Planning & Regeneration
Cabinet member: Councillor Jonathan Dow, Lead Member for Place Services
Ward(s): All
Purpose of report: To approve funding to commission Clear Sustainable Futures to determine if there is an investable business case for the deployment of sustainable energy generation technology at the Sovereign Leisure Centre Decision type: Key
Officer (1) Delegate authority to the Chief Finance Officer and recommendation(s): Director of Planning and Regeneration, in consultation with the Cabinet Member for Place Services to fund up to £25,000 for the commissioning of Clear Sustainable Futures to undertake the feasibility study of deploying sustainable energy generation at the Sovereign Leisure Centre
(2) Delegate authority to the Chief Finance Officer in consultation with CMT and the Cabinet Member for Place Services, to proceed with the recommended sustainable energy solution for the Sovereign Leisure Centre if this is demonstrated to be a viable investment up to a value of £1.45m.
(3) To note that a similar request is being made to Lewes District Council to progress viability analysis on their projects at Avis Way depot and Sutton Road and that the work is being conducted concurrently with knowledge being shared.
Reasons for To reduce the carbon emissions of council developments; recommendations: to enable the site to become a prosumer (a producer and consumer) of electricity and heat to reduce ongoing utility costs whilst also enabling income generation through provision of emerging grid flexibility services; to mitigate the impact of the development on the electrical grid and reduce utility costs. Contact Officer(s): Name: Jane Goodall/Kate Tradewell Post title: Strategy & Partnership Lead, Quality Environment Strategy and Corporate Projects Officer, Quality Environment E-mail: [email protected][email protected] Telephone number: 01323 415383
1 Introduction
1.1The current pipeline of redevelopment projects being undertaken by Lewes and Eastbourne councils and delivered by Clear Sustainable Futures provides an opportunity for the inclusion of clean energy generation technology that will provide for the site’s own needs, could produce an excess to generate income and potentially provide flexibility services to the grid.
This will mean that the development can negate high electrical connection costs, reduce reliance on grid supplied utilities thus insulating against future price rises, can potentially store renewably-generated energy for use at other times and even generate an income through selling the power back to the grid or to tenants.
With the accelerating decarbonising of the electric grid, gas fired combined heat and power (CHP), the current choice for on-site heat and power generation at the Sovereign Leisure Centre, will quickly be considered the high-carbon solution with related negative connotations and impact on regional carbon targets. In the 12 months to October 2018 the average carbon intensity of the UK Grid has been 260g/kWh, this figure means that gas fired CHP boilers are now the higher carbon source of heat, as essentially grid electricity is cleaner than gas. Generating electricity on-site will make the energy supply even cleaner.
1.2Sovereign Leisure Centre The project is anticipated to enter detailed design in Early Feb 2019, start on site in August 2019 and enter operation before end March 2021.
The current design has a gross internal floor area of 6,200sqm and comprises a heating system which is the ‘minimum Capex Design’ and includes a gas fired CHP engine and large gas boilers, for which the latest cost plan includes a total of £350k for this equipment.
2 Proposal
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.