(Key decision): (1) To delegate authority to the Chief Finance Officer and Director of Planning and Regeneration, in consultation with the Cabinet Member for Environmental Impact, to fund up to £25,000 for the commissioning of Clear Sustainable Futures to undertake the feasibility study of deploying sustainable energy generation at the Avis Way and Sutton Road development sites (2) To note that a similar request is being made to Eastbourne Borough Council to progress viability analysis on their project at the Sovereign Leisure Centre and that the work is being conducted concurrently with knowledge being shared.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Report of: Ian Fitzpatrick, Director of Planning & Regeneration
Cabinet member: Councillor Isabelle Linington, Cabinet Member for Environmental Impact
Ward(s): All
Purpose of report: To approve funding to commission Clear Sustainable Futures to determine if there is an investable business case for the deployment of sustainable energy generation technology on 2 projects at Sutton Road and Avis Way. Decision type: Key
Officer (1) Delegate authority to the Chief Finance Officer and recommendation(s): Director of Planning and Regeneration, in consultation with the Cabinet Member for Environmental Impact to fund up to £25,000 for the commissioning of Clear Sustainable Futures to undertake the feasibility study of deploying sustainable energy generation at the Avis Way and Sutton Road development sites
(2) To note that a similar request is being made to Eastbourne Borough Council to progress viability analysis on their project at the Sovereign Leisure Centre and that the work is being conducted concurrently with knowledge being shared.
Reasons for To reduce the carbon emissions of council developments; recommendations: to enable the sites to become a prosumer (a producer and consumer) of electricity and heat to reduce ongoing utility costs whilst also enabling income generation through provision of emerging grid flexibility services; to mitigate the impact of each development on the electrical grid and reduce utility costs.
Contact Officer(s): Name: Jane Goodall/Kate Tradewell Post title: Strategy & Partnership Lead, Quality Environment Strategy and Corporate Projects Officer, Quality Environment E-mail: [email protected][email protected]
Telephone number: 01273 085383 1 Introduction
1.1The current pipeline of redevelopment projects being undertaken by Lewes and Eastbourne councils and delivered by Clear Sustainable Futures provides an opportunity for the inclusion of clean energy generation technology that will provide for the site’s own needs, could produce an excess to generate income and potentially provide flexibility services to the grid.
This will mean that the development can negate high electrical connection costs, reduce reliance on grid supplied utilities thus insulating against future price rises, can potentially store renewably-generated energy for use at other times and even generate an income through selling the power back to the grid or to tenants.
In the 12 months to October 2018 the average carbon intensity of the UK Grid has been 260g/kWh, which is the figure that moves gas fired CHP (combined heat and power boilers) to being the highest carbon source of heat. This essentially means that grid electricity is now cleaner than gas.
1.2Lewes District Council Projects
Sutton Road, Seaford This project is at an early stage of development. Detailed design is expected to start in April 2019, start on site in November 2019, with completion of work in summer 2021. This site has similar energy requirements to the Sovereign Centre in Eastbourne so the business case at section 6 provides the energy solution proposed at this site for background and to illustrate that a similar solution incorporating heat pumps and solar panels could be financially viable here.
Avis Way Waste Depot As with Sutton Road, this project is at an early stage of development, detailed design is expected to start in March 2019, start on site in summer 2019 and completion at the end of 2020. This site could incorporate energy generation technology, such as PV panels, see business case at section 6.
2 Proposal
2.1It is proposed that CLEAR Futures (LDC and Clear Sustainable Futures together) complete a business case for Sutton Road and Avis Way to consider the technical, financial and contractual aspects of a suitable energy generation solution at each site.The cost for non LDC resources, CSF and external parties, would be up to £25,000.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.