(Non-key decision): (1) To agree that Wealden District Council be nominated as the lead authority. (2) To agree that Lewes District Council pilots 75% business rates retention, resulting in an additional anticipated gain of £0.1m over current pooling arrangements. (3) To agree the basic principle that no authority would receive a lower level of funding than they would have received without the pool. (4) To agree to split resources gained on the growth in business rates on the basis of the split being 26% to East Sussex County Council, 5% to the Fire authority and the remaining 44% split amongst the District/Borough Councils; (5) To agree the financial stability and economic development split of funding. (6) To agree that the finalisation of the Memorandum of Understanding is delegated to the Chief Finance Officer.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Cabinet member: Councillor Bill Giles, Cabinet Member for Finance
Ward(s): All
Purpose of report: To update members on the East Sussex Business Rates Pilot bid for 2019/20.
Decision type: Non Key
Officer 1. The Cabinet agrees that Wealden District Council be recommendation(s): nominated as the lead authority; 2. Agree that Lewes District Council pilots 75% business rates retention resulting in an additional anticipated gain of £0.1m over current pooling arrangements; 3. Agree that the basic principle that no authority will receive a lower level of funding than they would have received without the pool; 4. Agree to split resources gained on the growth in business rates on the basis of the split being 26% to ESCC, 5% to the Fire authority and the remaining 44% split amongst the District/Borough Councils; 5. Agree the financial stability and economic development split of funding; and 6. Agree that the finalisation of the Memorandum of Understanding is delegated to the Chief Finance Officer.
Reasons for The Government has invited councils to apply to be pilots of recommendations: 75% rates retention. Based on the independent assessment carried out by LG Futures, the Council is anticipated to benefit from the proposed arrangements. This report sets out the background to the pilot and informs Cabinet of the latest position.
1.1A new funding regime was introduced on 1 April 2013 whereby local authorities effectively retain a proportion of any additional business rate income collected (above inflation) or conversely will experience a reduction in resources if the business rates base declines.
1.2Under the scheme 50% of business rates is localised through a system of top- ups and tariffs that fix an amount to be paid to high yield authorities and distributed to low yield authorities – the amount being increased annually by inflation (RPI). The proportion retained by individual collection authorities in East Sussex is 40%, 9% is payable to East Sussex County Council, and 1% to the Fire and Rescue authority.
1.3The 50% central government share is distributed through the formula grant process (now termed Settlement Funding Assessment) – this enabling the government to control the overall amount received by local authorities. Where there is disproportionate growth this will be used to provide a safety net for those authorities experiencing little or negative growth and allows the treasury to top slice business rates income. A reset mechanism will be in the place with the first reset in 2020 and periods of 10 years thereafter.
2 Business Rates Retention Pilot
2.1The Government continues to work towards transferring control to local authorities over the locally generation business rate income. In December 2017, the government announced the aim of increasing the level of business rates retained by local government from the current 50% to the equivalent of 75% in April 2020.
2.2In order to test increased business rates retention and aid understanding of how to transition into a reformed business rates retention system in April 2020, the government invited local authorities in England to apply to become 75% business rates retention pilots in 2019/20.
2.3To ensure that piloting in 2019/20 closely reflects the government’s proposals to date for a reformed business rates retention system, authorities selected as pilots in 2019/20 will be expected to forego Revenue Support Grant (RSG) and Rural Services Delivery Grant (RSDG).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.