(Key decision): (1) To approve an increase in the General Fund Capital Programme budget for the scheme from £2.2m to £2.9m, with the additional £700,000 to be funded from Right to Buy Receipts. (2) To report an amendment to a waiver previously approved to the Contract Procurement Rules (CPR), as set out in paragraph. 2.4.1( a ) of CPR to allow the direct selection of a main contractor, due to the bespoke nature of the product required and time restrictions.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Title: Housing Finance for Short Term Lettings Development
Report of: Ian Fitzpatrick, Director of Regeneration and Planning
Cabinet member: Councillor Ron Maskell (Cabinet Member for Housing)
Ward(s): Newhaven Denton & Meeching
Purpose of report: The report is to seek approval for spending Right to Buy Receipts on a development scheme to provide 13 flats to meet our need for access to short term lettings.
Decision type: Key Decision
Officer (1) To approve an increase in the General Fund Capital recommendation(s): Programme budget for the scheme from £2.2m to £2.9m, with the additional £700,000 to be funded from Right to Buy Receipts.
(2) To report an amendment to a waiver previously approved to the Contract Procurement Rules (CPR), as set out in Para. 2.4.1(a) of CPR to allow the direct selection of a main contractor, due to the bespoke nature of the product required and time restrictions.
Reasons for In October 2018 Cabinet approved a report to spend up to recommendations: £2.2m on the development of housing for temporary accommodation, following on from a £2.2m budget amendment in February 2018 at a Full Council meeting. The budget amendment was made on the basis of an appraisal for a scheme built on a flat empty site, with no specific investment in sustainability or reducing the environmental impact.
The October 2018 report included a waiver to the Contract Procedure Rules (CPR) to directly the select an appropriate modular housing contractor. Although the approved contractor is still due to deliver the scheme, a ground works contractor has been added to the waiver, by the Director of Planning and Regeneration in Consultation with Leader of the Council under CPR 2.4.1b. Contact Officer(s): Name: Leighton Rowe Post title: Development Project Manager E-mail: [email protected] Telephone number: 01323 415367
1 Introduction
1.1Following the approval of the Cabinet Report in October 2018 to develop a housing scheme for the use of short term lettings, LDC has selected the site of the Former Council Housing Office at 20 Fort Road, Newhaven for the development. The building has been vacant since the Housing team moved to the shared office space at Saxon House, Newhaven. Although the site benefits from already being in the Council’s ownership and with no existing use, it will involve demolition of the old offices and is a split level site, requiring significant retaining wall groundworks.
1.2Over the past two years LDC has been developing its targets of delivering Capital projects to meet ambitious sustainability targets. Therefore the design of the scheme at 20 Fort Road has included many sustainability features, starting with a “Fabric First” approach to insulation and air pressure and also using technology such batteries for storing self generated electricity. There will be no gas used in the homes, and the target is for 3 months a year the homes could survive without the electricity grid.
1.3Planning permission for a scheme of 13 affordable flats was granted in April 2019 (ref LW/19/0012).
2 Project Budget
2.1The project budget of £2.2m allocated by Full Council and Cabinet was not based upon specific site selection or on detailed project specification, and now that full design and planning approval have been completed a project budget has been set of up to £2.9m, including £2.7m demolition and construction costs, and £200,000 in professional fees and financing costs. 2.2 LDC have receipts that are collected from the sale of Council homes under the Right to Buy, which can be used to fund 30% of development costs of new affordable housing by the Council, which will have to be handed back to Central Government if not spent within 3 years of being received, and can boost the project budget to deliver an exemplar scheme in Newhaven
3 Procurement Waiver
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.