Resolved
(Key decision): (1) To note the existing condition of the Fort bridge. (2) To approve that up to £350,000 be allocated from the Council’s capital programme and ring-fenced to meet the cost of replacement.
Lewes District Council Cabinet noted this item on Monday 16 September 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
(Key decision): (1) To note the existing condition of the Fort bridge. (2) To approve that up to £350,000 be allocated from the Council’s capital programme and ring-fenced to meet the cost of replacement.
Report to: Cabinet
Date: 16 September 2019
Title: Newhaven Fort
Report of: Ian Fitzpatrick, Director of Regeneration and Planning
Cabinet member: Councillor Ruth O’Keeffe, Cabinet member for tourism and devolution
Ward(s): Newhaven South
Purpose of report: For Cabinet to note the issues regarding the existing Fort bridge and agree that funds be set aside for its replacement from the Council’s capital programme.
Decision type: Key
Officer (1) To note the existing condition of the Fort bridge. recommendation(s): (2) To approve that up to £350,000 be allocated from the Council’s capital programme and ring-fenced to meet the cost of replacement.
Reasons for Newhaven Fort bridge requires replacement at the earliest recommendations: opportunity.
Contact Officer(s): Name: Mark Langridge-Kemp Post title: Head of Property, Delivery and Compliance E-mail: [email protected] Telephone number: 01323 415876
1 Introduction
1.1Newhaven Fort was built in 1871 and decommissioned in the 1960’s, it is a Scheduled Ancient Monument situated on the cliffs overlooking Seaford Bay. The Fort was run as a tourist attraction briefly in the early 1980’s before the owner went out of business and in 1988 the property passed to the Council.
1.2Since 2015 the property has been part of a management agreement with Wave Leisure Trust (WLT), the Council pays WLT £104,200 per annum for the agreement which ends in May 2025. It was entered into as a means of increasing visitor numbers and reducing the burden of property repairs on the Council. Under Wave’s management, visitor numbers for 2018-19 increased by 1.5% from the previous year to 30,720 people, annual income stood at £322,923, down from £335,141 the previous year. WLT’s costs were £290,752 (employees, premises related and supplies and services) resulting in a surplus of £32,171. 1.3 The property has received minimal investment from the Council for some time. A number of the gun emplacements have been fenced off from members of the public in order to ensure continued public safety, and other urgent repairs issues are being managed.
1.4There is an immediate issue with regards to the stability of the bridge into the Fort that now requires attention. The bridge was identified as needing replacement in 2014 and designs for a new moat bridge were incorporated within a Scheduled Ancient Monument consent application, for which consent was granted. Installation of the bridge did not occur following the granting of consent, presumably due to costs, and the bridge has been propped up ever since.
1.5It has now been 5 years since replacement of the bridge was recommended and there is no longer an option to delay decision due to the continued deterioration of the structure. Urgent additional propping has already been installed recently as a temporary measure in order to ensure that the bridge is safe for users and residents of Fort Rise who have to pass underneath the bridge in order to access their private garages.
2 Proposal
2.1A number of options have been explored.
• Do nothing – this is no longer a viable option as the structure of the bridge is in serious decline. The cost of the additional propping recently installed is around £2500 per week and this solution has a limited 3-5 years lifespan.
• Remove the bridge – this would not be permitted by Heritage England without a new structure going in place due to the property being designated a Scheduled Ancient Monument.
• Repair the bridge – the bridge was declared ‘beyond economical repair’ in 2014. Costs for repair are likely to be at least £160,000, with a 5-10 year life expectancy. However, this option comes with a lot of uncertainty as there are a number of unknowns and therefore there is considerable risk that the required budget would increase.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Newhaven FortReport | 63 KB | DownloadRead as text |
Follow Lewes District Council Cabinet at Lewes and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | Asset Management - Asset Devolution and North Street Quarter(Key Decision): 1) To note the update on asset devolution, including ongoing discussions with Town and Parish Council... | Noted | Open |
| 16 Jul 2026 | Portfolio Progress and Performance Report 2025/26 - Quarter 4(Non-Key Decision): 1) To note progress and performance for Quarter 4 2025/26. 2) To note the Corporate Plan update f... | Noted | Open |
| 16 Jul 2026 | Housing Services Progress and Performance Report - 2025/26 - Quarter 4(Non-Key Decision): 1) To note progress and performance for housing services for Quarter 4 2025/26. 2) To approve the... | Noted | Open |
| 16 Jul 2026 | Revenue and Capital Outturn Report 2025/26 - Quarter 4(Key Decision): 1) To note the final outturn position for 2025/26 and the associated financial risks and pressures. 2... | Noted | Open |
| 16 Jul 2026 | Treasury Management Annual Report 2025/26(Budget and Policy Framework): To recommend to Full Council: 1) To approve the Treasury Management Annual Report 2025... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.