(Key decision): (1) To note and approve the updated Lewes Town & Ringmer Council Housing Infill programme, as laid out at appendix 1 to the report, subject to a final costed plan being approved by Cabinet. (2) To approve an in principle programme of Council housing on infill land in Newhaven, as laid out at appendix 2 to the report, subject to a final costed plan being approved by Cabinet. (3) To note the updated development scheme at Anchor Field, Ringmer. (4) To approve the sale of Housing Revenue Account (HRA) land to Aspiration Homes LLP (AHLLP) for the construction of 11 affordable rented homes at Anchor Field, Ringmer and associated loan to deliver the affordable housing. The delegations for the sale of HRA land and loan facilities are as contained in the Cabinet report of 23 rd April 2018 entitled “Housing Development Update”.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Report of: Ian Fitzpatrick, Deputy Chief Executive and Director of Regeneration and Planning
Cabinet member: Councillor William Meyer, Cabinet member for housing
Ward(s): Newhaven Denton and Meeching, Newhaven Valley, Ouse Valley and Ringmer, Lewes Bridge, Lewes Castle, Lewes Priory.
Purpose of report: To gain approvals for a new sustainable Council housing project and to amend plans for ongoing housing developments schemes, ensuring they have a focus on sustainable design and delivery.
Decision type: Key
Officer (1) To note and approve the updated Lewes Town & recommendation(s): Ringmer Council Housing Infill programme, as laid out in appendix 1, subject to a final costed plan being approved by Cabinet.
(2) To approve an in principle programme of Council housing on infill land in Newhaven, as laid out in appendix 2, subject to a final costed plan being approved by Cabinet.
(3) To note the updated development scheme at Anchor Field, Ringmer
(4) To approve the sale of HRA land to Aspiration Homes LLP (AHLLP) for the construction of 11 affordable rented homes at Anchor Field, Ringmer and associated loan to deliver the affordable housing. The delegations for the sale of HRA land and loan facilities are as contained in the Cabinet report of 23rd April 2018 entitled “Housing Development Update”. Reasons for The overarching reason for the recommendations is to recommendations: maximise the Council’s ability to provide affordable housing within the District, partly through the full utilisation of receipts received from Council homes sold under the Right to Buy.
Contact Officer(s): Name: Leighton Rowe Post title: Development Project Manager E-mail: [email protected] Telephone number: 01323 415367
1 Introduction
1.1The background to the Council’s responsibility to supply affordable housing and the reasoning behind selling land to AHLLP are covered in a Cabinet Report of 23rd April 2018 entitled “Housing Development Update”. There was an appendix to the report that identified various housing development programmes including the Lewes & Ringmer Infills Programme and the development at Anchor Field.
1.2A further programme of new Council homes being delivered on infills sites is now also ready to be progressed.
2 Proposals
2.1Lewes and Ringmer Infill Programme (Infills Phase 2)
The Council’s second phase of Infill developments for Council housing was outlined in the January 2018 and April 2018 Cabinet Reports entitled “Garage Sites Redevelopment Phase 2” and “Housing Development Update”. During the period since then, a main contractor has been appointed and worked upon the feasibility of developing the sites, which has taken much longer than was originally anticipated. There were originally 9 sites approved for progression by the Cabinet, of which:
Three remain with very good potential for development and will be put forward for local consultation and planning applications submissions during the autumn 2019.
One site remains available for a community led housing scheme
Two sites are being reviewed as also being made available for community led housing schemes
Three sites have been removed from the programme, assessed as being unfeasible
The April 2018 report approved a plan to sell the above sites to AHLLP to develop, however national changes the borrowing capacity of the Council’s Housing Revenue Account (HRA) now mean that it is more financially viable to develop these homes within the HRA. There is also now a more rigorous requirement from LDC for its new homes to be sustainable, both in the way they are constructed and through the long-term use of the buildings.
Further details of the changes to the Infills Phase 2 programme can be found in appendix 1.
A report will be brought back to Cabinet with the fully costed programme with planning permission for final approval, which would include details of whether the programme would take place within the HRA or AHLLP.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.