(Key decision): (1) Not to proceed on the basis of the business case (Appendix 1 - Exempt) for the project known as the Former Newhaven Fire Station. (2) To use the existing delegations (as per the February 2020 Cabinet decision) to proceed with the purchase of that site. (3) To hold the site and further review its optimum use and business case. (4) To authorise the Director of Regeneration and Planning, in consultation with the Portfolio Holder for Housing, Portfolio Holder for Finance and Assets, and Chief Finance Officer, to carry out all necessary actions in relation to the review of the site’s future use on the basis that any future proposed housing development will come back to Cabinet for approval.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
2.1In February 2020, Cabinet approved the acquisition of the Former Fire Station in Newhaven to create 7 x new affordable 3-bed houses with high sustainable features, including fabric first and a zero gas (all electric) approach.
2.2In June 2022, a report was presented to Cabinet (‘Housing Development Update’) that provided an update that the scheme using modular construction was being reduced from 7 to 6 homes following feedback from the planning department. This paper also set out the economic environment and specific inflationary impacts on the construction sector nationally at that time. These unprecedented challenges, which have only increased, will continue to have significant implications to projects not already in contract and will require an ongoing review to ensure viability.
2.3Negotiations have taken place and a reduced purchase price has been agreed with the fire service that reflects the reduced number of units now being proposed in-conjunction with an independent red book valuation. Subject to Cabinet approval, the Council is now ready to complete on the purchase and progress the development.
2.4As brownfield land, there are higher challenges with associated costs impacting the site, which will need to be addressed prior to starting on site, including:
• Demolition of existing structures • Ground contamination and remediation • Retaining walls and strengthening/support works • Buried services and infrastructure adjustments
These impacts would typically limit interest from private developers and/or other Registered Providers without changes to the tenure, most commonly introducing market sale. Without LDC intervention, this site will likely remain vacant and unused to the benefit of the town and in-line with corporate objectives.
3 Market Update
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.