(Key decision): (1) To approve the strategic approach presented and agreed as follows: a. To continue to provide governance, support and resource to the Natural Flood Management (NFM) programme beyond the current end date of March 2023 and to delegate authority to the Director of Service Delivery in consultation with the Cabinet member for recycling, waste and open spaces to negotiate the terms of and enter into any necessary agreements to facilitate this provision. b. To build upon the NFM approach (as outlined in the report) and support inter-linked projects with partners and stakeholders such as habitat restoration and nature recovery in the Ouse catchment. (2) To endorse the approach set out at Appendix 1 ‘Lewes District Council (LDC) Briefing: Natural Flood Management within the Ouse and Eastern Adur catchment’ and Appendix 2 ‘Wilder Ouse, Vision & Targets’. (3) To approve a waiver to the Contract Procedure Rules (CPR) as set out in paragraph 2.4.1 (a) of the CPR to enable the Council to enter into agreements with partners in relation to this strategic approach.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Title: Natural Flood Management within the Ouse and Eastern Adur catchment
Report of: Tim Whelan, Director of Service Delivery
Cabinet member: Councillor Matthew Bird, Cabinet member for sustainability
Ward(s): All
Purpose of report: This report sets out the next steps for Natural Flood Management in Lewes district, which encompasses the Ouse and Eastern Adur catchments.
Decision type: Key
Officer (1) That Cabinet approves the strategic approach presented recommendation(s): and agrees as follows:
a. To continue to provide governance, support and resource to the Natural Flood Management (NFM) programme beyond the current end date of March 2023 and to delegate authority to the Director of Service Delivery in consultation with the Cabinet member for waste and recycling to negotiate the terms of and enter into any necessary agreements to facilitate this provision.
b. To build upon the NFM approach (as outlined in this report) and support inter-linked projects with partners and stakeholders such as habitat restoration and nature recovery in the Ouse catchment.
(2) That Cabinet endorses the approach set out at Appendix 1 ‘Lewes District Council (LDC) Briefing: Natural Flood Management within the Ouse and Eastern Adur catchment’ and Appendix 2 ‘Wilder Ouse, Vision & Targets’.
(3) Approve a waiver to the Contract Procedure Rules (CPR) as set out in paragraph 2.4.1 (a) of the CPR to enable the Council to enter into agreements with partners in relation to this strategic approach. Reasons for LDC has been successfully working in partnership recommendations: delivering Natural Flood Management (NFM) projects with the Sussex Flow Initiative (SFI) and Ouse & Adur Rivers Trust (OART) since 2016. This approach has delivered a raft of benefits on which to build in a collaborative effort to improve climate resilience in the coming years.
Contact Officer(s): Name: Ellen Miller Post title: Specialist Advisor Coastal Projects (Green Consultancy) E-mail: [email protected] Telephone number: Tel: [phone removed]
Name: Tim Bartlett Post title: Specialist Advisor Coastal and Flood Risk Management (Green Consultancy) E-mail: [email protected] Telephone number: Tel: [phone removed]
Name: Jane Goodall Post title: Environment Lead E-mail: [email protected] Telephone number: Tel: [phone removed]
1 Introduction
1.1In 2016, LDC entered into a partnership with the Sussex Flow Initiative (SFI) and Ouse & Adur Rivers Trust (OART) to deliver a range of initiatives to use natural processes to make space for water and thus reduce the risk of flooding in the Ouse Catchment. 1.2 This pioneering lowland Natural Flood Management project aims to create a climate resilient landscape. OART is the primary delivery organisation of river enhancements across the entire catchment with over £5m of enhancements in the past nine years. The SFI small team of experts also works with communities and landowners to help people and wildlife to adapt better to extreme flooding and drought. 1.3 The project is a collaboration between Sussex Wildlife Trust, the Woodland Trust, the Environment Agency, and Lewes District Council with OART as an equal delivery partner. The present agreements end in March 2023. 1.4 In 2019, Lewes District Council committed to reduce council greenhouse gas emissions to net zero and to become fully climate resilient by 2030 and to address the ecological disaster (Feb 2021). Meaningful nature-based solutions are at the heart of these ambitions. 2 Proposal
2.1Proposals can be summarised as: ✓ To continue with this important area of work, learning from our experience and adopting new and emerging ideas around climate resilience that align with this project and LDC’s strategies and policies.
✓ To provide baseline funding from April 2023 to 2028 to support the partnership approach to NFM and associated nature-based solution projects across the catchments.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.