Resolved
(Non-key decision): To note progress and performance for quarter 1 2024/25.
Lewes District Council Cabinet noted this item on Thursday 26 September 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
(Non-key decision): To note progress and performance for quarter 1 2024/25.
Report to: Cabinet
Date: 26 September 2024
Title: Portfolio progress and performance report 2024/25 - Quarter 1
Report of: Homira Javadi, Director of Finance and Performance
Cabinet member: Councillor Chris Collier, Cabinet member for innovation, delivery and people
Ward(s): All
Purpose of report: To consider the council’s progress and performance in respect of service areas for the First Quarter of the year (April – June 2024) as shown in Appendix 1.
Decision type: Non-key
Officer To note progress and performance for Quarter 1 2024/25 recommendation(s):
Reasons for To enable Cabinet members to consider specific aspects of recommendations: the council’s progress and performance.
Contact Officer(s): Luke Dreeling: Performance Lead Tel: [phone removed] or email: [email protected]
1 Introduction
1.1The council has an annual cycle for the preparation, implementation and monitoring of its business plans and budgets. This cycle enables us regularly to review the council’s work, and the targets it sets for performance, to ensure these continue to reflect customer needs and council aspirations.
1.2It is important to monitor and assess progress and performance on a regular basis, to ensure the council continues to deliver priority outcomes and excellent services to its customers and communities.
1.3Appendix 1 of this report sets out details of the key performance indicators for 2024/25 which were agreed by Cabinet in July 2024.
1.4As is usual, alongside the reporting of quarterly performance, this report also sets at section 3 progress with the recovery and reset programme addressing our digital transformation work, and at section 4 an update on our solution sprints improvement work. 2 Appendix 1 Review
2.1Within Appendix 1 we have 30 PIs, this quarter we have had: 7 PIs achieve target, 2 slightly below target, 11 below target, 12 Data only points. We have 7 positive trends and 12 negative trends from Q4 to Q1.
3.0Recovery and Reset Programme
3.1This quarter, the following has been the focus of the digital transformation programme: • Finalising the next phase of implementation for the new revenues and benefits system – the Citizen Portal – this will enable residents to engage with the council and update their personal information via a self-service platform. • Readying the next phase of development for the new council website – member engagement will be taking place in the next quarter. • Exploring options for the council’s next generation chatbot – ELLIS – officers are working with the council’s
The Transformation Review Programme Board provides the overarching governance arrangements for the three workstreams, feeding into the Recovery & Reset portfolio and interfacing with CMT accordingly.
4 Solution Sprints
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Portfolio progress and performance report quarter 1: 2024-2025: Appendix 1Appendix | 217 KB | Download |
PDF |
Portfolio progress and performance report quarter 1: 2024-2025Report | 83 KB | DownloadRead as text |
Follow Lewes District Council Cabinet at Lewes and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | Asset Management - Asset Devolution and North Street Quarter(Key Decision): 1) To note the update on asset devolution, including ongoing discussions with Town and Parish Council... | Noted | Open |
| 16 Jul 2026 | Portfolio Progress and Performance Report 2025/26 - Quarter 4(Non-Key Decision): 1) To note progress and performance for Quarter 4 2025/26. 2) To note the Corporate Plan update f... | Noted | Open |
| 16 Jul 2026 | Housing Services Progress and Performance Report - 2025/26 - Quarter 4(Non-Key Decision): 1) To note progress and performance for housing services for Quarter 4 2025/26. 2) To approve the... | Noted | Open |
| 16 Jul 2026 | Revenue and Capital Outturn Report 2025/26 - Quarter 4(Key Decision): 1) To note the final outturn position for 2025/26 and the associated financial risks and pressures. 2... | Noted | Open |
| 16 Jul 2026 | Treasury Management Annual Report 2025/26(Budget and Policy Framework): To recommend to Full Council: 1) To approve the Treasury Management Annual Report 2025... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.