What was decided
The Cabinet approved the draft Lewes Local Plan (Phase 2) Regulation 18 document for public consultation, as set out in Appendix 1 and in line with the 2012 Regulations and the March 2025 Local Development Scheme. Report 1.2, 4.1, 4.2
The Cabinet delegated authority to the Chief Executive, in consultation with the Cabinet Member for Planning and Infrastructure, to make minor editorial corrections before publication.
The plan will deliver about 8,570 new homes through 21 new housing allocations, against a government calculated need of about 15,000, with sites drawn from densification of coastal towns, Peacehaven and Newhaven expansion, Haywards Heath and Burgess Hill urban extensions, and sustainable low weald villages. Report P3, 1.5, 2.4, 2.24, 2.18
Why
The plan is needed to meet statutory duties under the Planning and Compulsory Purchase Act 2004, to respond to a housing need of about 15,000, and to address climate, ecological and sustainable growth challenges. Report 1.1, 1.2, 1.4, P1
Officers argue the 8,570 home figure is a realistic acknowledgement of physical and financial constraints, especially the South Downs National Park, the High Weald National Landscape and limited transport funding. Report 1.6, 1.7, 1.8, 2.17
Public consultation is required to engage communities, stakeholders and statutory bodies before the Regulation 19 submission stage, and to reduce the risk of legal challenge at examination. Report P4, 4.1, 6.1, 9.3
What happens next
Run an 8 to 10 week public consultation, with briefings for town and parish councils, notifications, press and social media, and public drop-in events in settlements where development is proposed. Report 4.2, 4.3, 4.4
Analyse consultation responses and work with statutory bodies and site promoters, with a further Regulation 19 round expected in mid 2026 and a final Cabinet decision on submission later in 2026. Report 3.1, 3.2, 3.3, 4.6
Keep the call for sites open and continue Duty to Co-operate discussions, including with Brighton and Hove on employment need, while updating the Infrastructure Delivery Plan and evidence base. Report 2.18, 2.22, 2.27, 2.29
The money
- 9,818 sqm Office floorspace requirement identified in the Lewes Economic Needs Assessment (April 2023) Report 2.19
- 230,058 sqm Existing industrial floorspace across Lewes District Report 2.21
- 18,829 sqm Projected net decrease in industrial floorspace demand by 2040 Report 2.21
Options considered
- Chosen: Consult on the Phase 2 draft (spatial strategy, green gaps, housing allocations). Matches the Phase 1 commitment, fits the March 2025 Local Development Scheme, and meets the Regulation 18 duty to consult. Report 6.1, 4.1, 1.2
- Rejected: Do not consult on a draft version of the Local Plan at this stage. Would risk failure at examination and contradict the Local Development Scheme, leaving communities and partners unable to comment. Report 6.2
- Rejected: Consult on a full draft including the Phase 1 policies again. Phase 1 policies were already consulted on, national policy is still moving, and the National Development Management Policies are expected to override local policies. Report 6.3
Implications
- Legal: Consultation is a statutory duty under Regulation 18 of the 2012 Regulations; the Council will need a new Equality and Fairness Analysis and Sustainability Appraisal at the Regulation 19 stage, with Full Council approval before submission to the Secretary of State. Report 8.2, 8.3, 10.2
- Financial: Existing budgets cover preparation and consultation. The spatial strategy will affect Council Tax, Section 106 contributions, Community Infrastructure Levy income and infrastructure funding needs through the Infrastructure Delivery Plan. Report 7.1, 2.27
- Risk: A significant unmet housing need shortfall is flagged. The Council may add or drop site allocations after consultation, and final sites will only be confirmed in the 2026 Regulation 19 version. Report 2.18, 3.3
- Equalities: The Council has had regard to the Public Sector Equalities Duty, with engagement shaped by the Statement of Community Involvement (July 2020); a fuller analysis is required at the next stage. Report 10.1, 10.2, 8.2
- Climate: The plan responds to the climate and ecological emergencies through green infrastructure, strategic green gaps and a vision-led sustainable transport strategy, although the Phase 1 climate policies will be consulted on later at Regulation 19. Report P1, 2.5, 2.11, 11.1
- Other: Local Government Reorganisation: once adopted, the plan will remain the basis for planning decisions until a new plan is made under any new structure. Report 12.1
Who and where
- Residents and communities across the Lewes Local Plan area, including coastal towns, Peacehaven, Newhaven, Haywards Heath, Burgess Hill and low weald villages Report 1.1, 2.4
- Statutory consultees such as East Sussex County Council, Natural England, the Environment Agency and South Downs National Park Authority Report 3.2, 1.6
- Site promoters and developers with land in or near allocated settlements Report 2.23, 2.24, 3.3
- Neighbouring authorities, in particular Brighton and Hove City Council under the Duty to Co-operate Report 2.18, 2.22
- Town and parish councils Report 4.3
Timeline
- 2025-12-11: Cabinet approves draft Lewes Local Plan 2042 Phase 2 for public consultation
- After Cabinet approval: Public consultation runs for 8 to 10 weeks, accounting for Christmas and New Year closures Report 4.2
- mid 2026: Final round of consultation on the Publication draft Local Plan (Regulation 19) Report 3.1
- 2026: Final Cabinet decisions on what to include in the Regulation 19 Submission version Report 3.2
- Plan period 2020-2042: Overall plan period for the Lewes Local Plan 2042 Report P17, 1.2
Plain English for the jargon
- Regulation 18: Stage of local plan preparation under the Town and Country Planning (Local Planning) (England) Regulations 2012 where the council consults on a draft plan before publishing a proposed submission version.
- Regulation 19: The next statutory stage, known as the proposed submission plan, when the council publishes the plan it intends to submit to the Secretary of State for examination.
- Local Development Scheme: The council's published project plan and timetable for preparing its Local Plan, last updated in March 2025.
- Duty to Co-operate: Legal duty on local planning authorities to work with neighbouring councils and prescribed bodies on strategic cross-boundary issues such as housing and employment need.
- Strategic green gaps: Designated areas of open land between settlements used in the plan to prevent coalescence and protect countryside character.
- Section 106 / CIL: Developer contribution mechanisms: Section 106 planning obligations and the Community Infrastructure Levy, used to fund infrastructure supporting new development.