Community Infrastructure Levy (CIL) spending from the Strategic Pot 2026
AgreedExecutive3 papers
AI summaryLewes District Council Cabinet has approved the release of Community Infrastructure Levy Strategic Pot funds to improve bus services in the Peacehaven area and along the A259 corridor between Newhaven, Brighton Marina and Falmer.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedStrategic Pot funding for Peacehaven and A259 corridor
MoneyNot stated
What happens nextFunds released to bidderSubject to grant agreement with the council
Who it affectsNot stated
What was decided
Cabinet approved the release of funds from the CIL Strategic Pot, as recommended by the CIL Executive Board, to deliver bus service improvements in the Peacehaven area and along the A259 corridor between Newhaven, Brighton Marina and Falmer.
Why
The project aligns with the Corporate Plan by supporting a shift away from private cars, reducing vehicle emissions, and improving access to employment, health and wellbeing for residents. Report 5.1, 11.3
The CIL Executive Board recommended the bid following assessment, including a positive environmental impact evaluation, and the application follows earlier work with Brighton and Hove Buses on women's safety along the coastal strip. Report P17, 11.2
What happens next
The council will agree release of the funds with the bidder to ensure timely project delivery and minimise risk to the council. Report 7.1
Delivery will be monitored by the Senior Planning Policy Officer, with oversight from Finance, and a Grant Agreement will be managed by the council's Legal Team to prevent premature service stoppage. Report 7.2, 9.1
Options considered
Chosen: Release the CIL Strategic Pot funds to support the bus service bid. Aligns with Corporate Plan priorities, supports development, and follows recommendation of CIL Executive Board Report 5.1, 6.1
Rejected: Do not release the funds. Described as unrealistic; would not support infrastructure needed for development and communities Report 6.1
Implications
Legal: Funding must be used for infrastructure as defined in Section 216(2) of the Planning Act 2008 and regulation 59 of the CIL Regulations 2010, and decisions follow the CIL Governance Framework approved by Cabinet in November 2016. Report 8.1, 8.2, 8.3, 8.4
Equalities: Generally expected to have a positive impact on residents with protected characteristics, including younger and older residents, disabled residents and carers, and to bring health and wellbeing benefits. Report 10.1
Climate: The funded buses and route improvements are expected to reduce reliance on private cars, encourage public transport use, assist with modal shift, and reduce carbon emissions. Report 11.3
Risk: If funds are not released, required infrastructure may not be delivered, putting Local Plan and Neighbourhood Plan objectives at risk; project and service stoppage risks will be managed through a Grant Agreement. Report 9.1
Other: The Grant Agreement will seek to ensure services remain within routes in the current Lewes District geographical area after Local Government Reorganisation. Report 12.1
Who and where
Bus passengers in the Peacehaven area and along the A259 corridor between Newhaven, Brighton Marina and Falmer Report 11.4
Residents needing access to hospital facilities in Brighton, shopping in Newhaven, and wider public services and work opportunities Report 11.4
Younger and older residents, disabled residents and carers across the Lewes District Report 10.1
Women travelling on buses along the coastal strip, following earlier collaborative safety work Report P17
Timeline
23.06.26: Legal Section considered the report (reference LDC-JCS-GEN-0676)
2026-07-16: Cabinet decision to release CIL Strategic Pot funds
Plain English for the jargon
CIL: Community Infrastructure Levy, a charge that local authorities can levy on new development to fund infrastructure
Strategic Pot: The share of CIL funds held at district level for strategic infrastructure priorities
A259 corridor: The coastal road route between Newhaven, Brighton Marina and Falmer
LGR: Local Government Reorganisation, the reshaping of local authority structures
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item23
Resolved
(Key Decision): To agree the release of funds from the CIL Strategic Pot as recommended by the CIL Executive Board in order to deliver bus service provision improvements in the Peacehaven area and along the A259 corridor between Newhaven, Brighton Marina and Falmer.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Title: Community Infrastructure Levy (CIL) spending from the Strategic Pot 2026
Report of: Councillor Laurence O’Connor, Cabinet Member for Planning and Infrastructure
Robert Cottrill, Chief Executive
Ward(s): All
Purpose of report: The report seeks Cabinet approval to release CIL funds, as recommended by the CIL Executive Board, to Provide 3 new buses to allow for new and improved bus routed within the South of the District, particularly North Peacehaven.
Decision Type: Key
Officer To agree the release of funds from the CIL Strategic Pot as recommendation(s): recommended by the CIL Executive Board in order to deliver bus service provision improvements in the Peacehaven area and along the A259 corridor between Newhaven, Brighton Marina and Falmer.
Reasons for To help deliver the right level and type of infrastructure to recommendations: support development identified for the local planning authority in the adopted Joint Core Strategy (LPP1) as well as delivering on the 2018 Lower Hoddern Farm planning application.
Contact Officer(s): Name: Emma Kemp Post title: Senior Planning Policy Officer E-mail: [email protected]
1 Introduction
1.1Community Infrastructure Levy (CIL) is charged, in accordance with the Lewes CIL Charging Schedule, on new development to help raise funds to deliver required infrastructure. Developments granted permission on or after 1 December 2015 in the area of the district for which Lewes District Council is the local planning authority become liable for CIL payments when works to implement a planning permission commence.
1.2As of 3 June 2026, the Council has collected £23,545,689.50 of CIL monies since implementation in 2015. The table below sets out how the collected amount of CIL is apportioned between the different pots. This is in line with the CIL Regulations 2010 (as amended), the National Planning Practice Guidance (2014) and the Council’s bespoke CIL governance framework (2014, 2016, 2020): Total CIL Process Collected since adoption (2015) CIL Admin £1,177,284.48 Applies to cost of administrative expenses for collection and enforcement in line with Regulation 61
Neighbourhood £4,930,411.77 Passed to Town and Parish Councils Portion (with adopted neighbourhood plans) twice yearly (April, October). Spend must be in line with Regulation 59C
Strategic Pot £11,664,286.00 Infrastructure providers are invited to bid to help deliver strategic infrastructure identified as fundamental to support development. The CIL Executive Board makes spending recommendations to Cabinet. Decision to be taken by Cabinet.
Local Fund Pot £3,487,598.65 Infrastructure providers are invited to bid to help deliver local and community infrastructure. The CIL Management Board makes spending Community Pot £2,165,959.59 recommendations to be reviewed by the CIL Executive Board and subject to Cabinet’s approval Community Small £120,149.01 Projects Pot
1.3The CIL Regulations determine that CIL monies (receipts) received by the planning authority must be used towards the provision, improvement, replacement, operation or maintenance of infrastructure that is required to support development Under the Council’s governance framework, the CIL Boards assess bids submitted to the Strategic, Local, Community and Community small projects pots against the set criteria. Where necessary other stakeholders may be invited to comment as part of the assessment process. It should, however, be noted that Town and Parish Councils have more flexibility to spend their neighbourhood portion on anything else that is concerned with addressing the demands that development places on an area.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.