Having considered an officer report and a presentation by the Mayor, the Mayor and Cabinet agreed that: (1) the strategy for the redevelopment of Mayow Road Warehouse be approved; (2) subject to planning consent for demolition being obtained, Mayow Road Warehouse be demolished and the Council seek to deliver new high quality council homes on the site; (3) a statutory S105 consultation be undertaken to consult with secure tenants regarding the demolition process; (4) authority be delegated to the Executive Director for Customer Services to consider any responses to the S105 consultation and to make any necessary decision in this respect; (5) officers submit a bid to NHS England Transforming Care Programme Capital Fund for the Supported Living element of the Mayow Road scheme; (6) officers submit a bid to the GLA Supported Housing and Specialist Housing Capital Fund for the Supported Living element of the Mayow Road scheme; (6) 2.6. Subject to the bids referred to above being successful, authority be delegated to the Executive Director for Customer Services in consultation with the Head of Law to negotiate the final terms and conditions of the funding agreements with both NHS England and the GLA, and to enter into the funding agreements; (7) the strategy for the redevelopment of 118 Canonbie Road be noted; (8) subject to planning consent being obtained, the existing property at 118 Canonbie Road be demolished and that the Council seek to deliver new high quality council homes on the site; (9) authority be delegated to the Executive Director for Customer Services to approve the submission of these two schemes ( Mayow Road Warehouse & 118 Canonbie Road) for planning approval; (10) a post planning funding and delivery strategy be presented to Mayor and Cabinet for approval prior to the commencement of demolition and construction works for the Mayow Road scheme and prior to the commencement of demolition and construction works at 118 Canonbie Road.
Word for word from the decision Lewisham published for this meeting.Source: councilmeetings.lewisham.gov.uk
Report Title Demolition of Mayow Road Warehouse & 118 Canonbie Rd to build new Council Homes Key Decision Yes Item No.
Ward Perry Vale & Forest Hill
Contributors Executive Director of Customer Services, Head of Law, Head of Finance
Class Part 1 Date: 13 February 2019
1. Summary & Purpose
1.1This report sets out the rationale and strategy for the demolition of Mayow Road Warehouse and 118 Canonbie Rd to provide c.39 new council homes in Lewisham. The report provides outline details of each scheme and the indicative programme to completion.
1.2These two sites represent the first iteration of the Councils new 1000 social homes house building target and are anticipated for completion at the end of 2020.
1.3Demolition and redevelopment of each site will allow for the Council to optimise its assets for the provision of new homes for those in housing need in Lewisham. To achieve these aims this report seeks authority to demolish these structures (dependent on achieving the necessary planning consents).
1.4Mayow Road will deliver c.33 units of new social housing. This will be made up of c.27 new Temporary Accommodation (TA) family sized homes for homeless families, as well as 6 new Supported Living homes for residents with learning disabilities.
1.5118 Canonbie Road will provide 6 new Temporary Accommodation (TA) family sized homes.
1.6Particular attention should be drawn to the Mayow Road development which is supported by NHS England. NHS England have made grant funding available for the Supported Living element of this scheme as a part of their ‘Transforming Care’ programme1. Securing this grant of c. £900k is dependent on submitting a planning application. Officers are working towards the submission of a planning application in April 2019 so to take advantage of early entry into the NHS grant funding programme for the 2019-2020 financial year.
1.7Whilst officers are confident that access to grant funding will be achieved, it is not guaranteed. Officers are therefore working through alternative funding models. This includes early conversations with the GLA to identify potential funding opportunities through their Supported Housing and Specialist Housing Capital Fund.
2.2Note the strategy for the redevelopment of Mayow Road Warehouse;
2.1Agree that subject to planning consent for demolition being obtained, Mayow Road Warehouse should be demolished and that the Council should seek to deliver new high quality council homes on the site;
2.2Note that a statutory S105 consultation will be undertaken to consult with secure tenants regarding the demolition process;
2.3Delegate authority to the Executive Director for Customer Services to consider any responses to the S105 consultation and to make any necessary decision in this respect;
2.4Authorise officers to submit a bid to NHS England Transforming Care Programme Capital Fund for the Supported Living element of the Mayow Road scheme;
2.5Authorise officers to submit a bid to the GLA Supported Housing and Specialist Housing Capital Fund for the Supported Living element of the Mayow Road scheme;
2.6Subject to the bids referred to at recommendations 2.4 and 2.5 being successful, delegate authority to the Executive Director for Customer Services in consultation with the Head of Law to negotiate the final terms and conditions of the funding agreements with both NHS England and the GLA, and to enter into the funding agreements;
2.7Note the strategy for the redevelopment of 118 Canonbie Road presented as part of this report;
2.8Agree that subject to planning consent being obtained, the existing property at 118 Canonbie Road should be demolished and that the Council should seek to deliver new high quality council homes on the site;
2.9Delegate authority to the Executive Director for Customer Services to approve the submission of these two schemes (Mayow Road Warehouse & 118 Canonbie Road) for planning approval;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.