Having considered an open and a confidential officer report, and a presentation by the Cabinet Member for Health & Adult Social Care, Councillor Chris Best, the Mayor and Cabinet agreed that the award of contract for the supported living service at Mayow Road be made to PLUS (Providence Linc United Services) for a contract period of 4 years, at a total value of approximately £3,453,561 following a mini-competition carried out under Lot 1: Supported Living of the Framework Agreement for Adults with Learning Disabilities 2019-2023.
Word for word from the decision Lewisham published for this meeting.Source: councilmeetings.lewisham.gov.uk
Report title: Learning Disability Framework Agreement - Mayow Road Supported Living – Award of Contract Date: 12 January 2022
Key decision: Yes.
Class: Part 1
Ward(s) affected: All wards
Contributors: Executive Director, Community Services
Director of Law
Director of Finance
Outline and recommendations This report sets out the process and outcome for procuring a supported living service for 6 adults with learning disabilities and / or autism to be delivered within specialist accommodation as part of the new social housing development in Mayow Road. It includes the background and history to the development of this service.
Mayor and Cabinet are recommended to:
Agree the award of contract for the supported living service at Mayow Road to PLUS (Providence Linc United Services) for a contract period of four years.
This contract is a call off under Lot 1: Supported Living of the Framework Agreement for the Provision of Services to Adults with Learning Disabilities.
The cost of this contract is approximated at £3.5 million. Actual contract values will be determined on confirmation of the individuals placed in the service. Timeline of engagement and decision-making On 13th February 2019 Lewisham’s Mayor and Cabinet approved that the Council should pursue the development of new high-quality Supported Living and temporary accommodation homes at the Mayow Road Warehouse site.
On 7th August 2019 Lewisham’s Mayor and Cabinet authorised the scheme be submitted for Planning Approval
On 1st November 2019 Planning Permission was granted
A capital grant agreement between NHSE and Lewisham Council was finalised and signed in February 2020 to confirm the NHS funding contribution towards the cost of the build of the 6 supported living flats that would form the supported housing element of the Mayow Road development.
Approval to procure a provider for the delivery of the supported living service at Mayow Road was given by Mayor & Cabinet on 10th March 2021 (report entitled Learning Disability Framework - Request for permission to procure a contract for Supported Living through call off from the Framework (Mayow Road Supported Living units))
Two organisations bid and were shortlisted for interviews which were held on 17th November 2021. The evaluation panel for the interview comprised Council officers, Health professionals plus a person with lived experience supported by an Advocacy worker from Lewisham Speaking Up within the interview.
1. Summary 1.1. The purpose of this report is to seek agreement from Mayor and Cabinet to award the contract for the new Mayow Road supported living service to PLUS (Providence Linc United Services) following a procurement process carried out as a call off under the Framework Agreement for the Provision of Services to Adults with Learning Disabilities. The contract will start in February 2022.
1.2The service will be delivered to the 6 new Supported Living homes for residents with learning disabilities which is part of the new Mayow Road social housing development.
1.3The development of this new supported living scheme is strategically supported by the Council and the CCG. NHS England have made grant funding available for the development of the Supported Living element of the Mayow Road scheme as a part of the ‘Transforming Care’ programme (now the Learning Disability & Autism programme). A grant of c. £900k has been made available following the award of planning approval for the scheme in November 2019.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.