CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Lewisham
Mayor and Cabinet, Wednesday 5 February 2020 at 6.30pm

Surrey Canal Triangle Draft Design Framework Supplementary Planning Document

Noted Executive 7 papers

Mayor and Cabinet noted this item on Wednesday 5 February 2020. Below is the council's own wording, with the papers it was decided on.

Item252

Resolved

Having considered an officer report, and a presentation by the Mayor, the Mayor and Cabinet: (1) Noted the findings of the Strategic Environmental Assessment (SEA) screening report in Appendix 2 of the report; (2) Noted the responses to the pre-production consultation in Appendix 3; (3) Noted the responses to the public consultation in Appendix 5; (4) took account of any comments received from the meeting of Sustainable Development Select Committee held on 21 st January 2020; (5) Adopted the Surrey Canal Triangle Design Framework Supplementary Planning Document – Appendix 1; (6) Noted the financial and legal implications set out in section 9 and 10; (7) Noted that with the adoption of the Surrey Canal Triangle Design Framework Supplementary Planning Document the Conditional Land Sale Agreement between the Council and Renewal Group Limited will be terminated in accordance with the resolution of the Mayor and Cabinet at its meeting on 10 October 2019; and (8) Authorised the Executive Director for Housing, Regeneration and Environment to make minor textual or format changes to the SPD prior to publication.
Word for word from the decision Lewisham published for this meeting. Source: councilmeetings.lewisham.gov.uk

Follow this further

Built from Lewisham's papers

What the report saysPro

Report to Mayor and Cabinet

Summary

2.1This report sets out the background, need and policy context for the draft SCT SPD, reports back on the pre-production consultation and public consultation carried out by officers, and summarises the draft SPD’s contents.

Recommendations

3.1Mayor and Cabinet are recommended to;

a. Note the findings of the Strategic Environmental Assessment (SEA) screening report in Appendix 2 b. Note the responses to the pre-production consultation in Appendix 3 c. Note the responses to the public consultation in Appendix 5 d. Take account of any comments received from the meeting of Sustainable Development Select Committee held on 21st January 2020 e. Adopt the Surrey Canal Triangle Design Framework Supplementary Planning Document – Appendix 1 f. Note the financial and legal implications set out in section 9 and 10 g. Note that with the adoption of the Surrey Canal Triangle Design Framework Supplementary Planning Document the Conditional Land Sale Agreement between the Council and Renewal Group Limited will be terminated in accordance with the resolution of the Mayor and Cabinet at its meeting on 10 October 2019 h. Authorise the Executive Director for Housing, Regeneration and Environment to make minor textual or format changes to the SPD prior to publication. 4. Background

4.1On 10 October 2019 Mayor and Cabinet resolved that the Conditional Land Sale Agreement entered into on 20 December 2013 between the Council and Renewal Group Limited be terminated conditional upon the adoption of a Surrey Canal Triangle Design Framework as a Supplementary Planning Document. This report brings forward for consideration the final version of Surrey Canal Triangle Design Framework, seeking a resolution for its adoption as a Supplementary Planning Document.

4.2The draft SPD has been produced to provide further guidance on the comprehensive regeneration of the Surrey Canal Triangle, as allocated for redevelopment in the LB Lewisham Core Strategy 2011.

4.3The Development Area, known as Surrey Canal Triangle, is identified in the Adopted Core Strategy as Strategic Site Allocation 3 (SSA3). It covers an area of more than 10 hectares of land in the north west of the Borough. The land is bounded by railway lines and bisected by Surrey Canal Road. Millwall Football Stadium occupies a key site in the north east of the development area.

4.4The regeneration of the site is strategic in nature and considered essential to the delivery of the existing Core Strategy. It is important that the site is developed comprehensively to ensure a coordinated outcome, setting high standards of design quality and deliverability. Individual planning applications should comply with the objectives of the Design Framework set out in the draft SPD. Proposals which fail to respond to the draft SPD or which undermine the delivery of a comprehensive outcome will not be supported.

4.5Outline planning permission was granted in March 2012 for the redevelopment of the entire Development Area (known then as New Bermondsey), under reference DC/11/76357. A subsequent S73 planning approval was granted on 18 December 2015 under reference DC/13/085143 to amend Condition 3 of the DC/11/76357 outline permission. In granting the DC/11/76357 outline permission, the Council allowed a period of up to 10 years for the submission of subsequent reserved matters applications, recognising the scale of the development and its proposed phasing and delivery. This planning permission is extant and applications for reserved matters approval can be submitted no later than 30 March 2022.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Surrey Canal Triangle SPDAppendix 1 99 MB Download
PDF
SEA assessmentAppendix 2 975 KB Download
PDF
updateAppendix 3 237 KB Download
PDF
SCT draft SPD consultation programme (1)Appendix 4 258 KB Download
PDF
Stage 2 Summary of consultation issues raised SCT SPD FINAL (1)Appendix 5 352 KB Download
PDF
Surrey Canal Triangle Draft Design Framework Supplementary Planning DocumentSupplementary 196 KB DownloadRead as text
PDF
Surrey Canal Triangle Draft Design Framework Supplementary Planning DocumentSupplementary 126 KB Download

At this meeting

Whole meeting

Who was there

12 of 12 attended
MD
Mayor Damien EganMayor, present
CB
Councillor Chris BestCommittee Member, present
CB
Councillor Chris BarnhamCommittee Member, present
PB
Councillor Paul BellCommittee Member, present
KB
Councillor Kevin BonaviaCommittee Member, present
AB
Councillor Andre BourneCommittee Member, present
JD
Councillor Joe DromeyCommittee Member, present
BD
Councillor Brenda DacresCommittee Member, present
SM
Councillor Sophie McGeevorCommittee Member, present
AD
Councillor Amanda De RykCommittee Member, present
JS
Councillor Jonathan SlaterCommittee Member, present
JK
Jasmine KassimSecretary, present

On this subject at Lewisham

Search all
  1. Surrey Canal Triangle Draft Design Framework Supplementary Planning DocumentThis decision
  2. Surrey Canal Station UpdateDecided
  3. Land at Surrey Canal Road, Stockholm Road, Bolina Road and Rolins Street, London SE15 and SE16Decided
  4. Land at Surrey Canal Road, Stockholm Road, Bolina Road and Rollins Street, London SE15 AND SE16Agreed
  5. Surrey Canal Triangle supplementary planning documentNoted
  6. Response to Select Committee Surrey Canal Triangle Design FrameworkAgreed

More from Lewisham Mayor and Cabinet

All decisions
MeetingDecisionOutcome
9 Sep 2026 MinutesThe minutes of the Mayor and Cabinet meeting held on 1 July 2026 were agreed as a correct record. Agreed Open
9 Sep 2026 Matters Raised by Scrutiny and other Constitutional BodiesThere were no matters raised by scrutiny or other constitutional bodies for consideration at the meeting. Decided Open
9 Sep 2026 Smoke Control Area: Whole Borough DesignationMayor and Cabinet • Approved the commencement of the statutory process to revoke the existing Smoke Control Orders fo... Approved Open
9 Sep 2026 Treasury Management Mid-Year Review 2026/27Mayor and Cabinet • Approved and recommended that Council approves the Treasury Management Outturn report for 2025/26... Approved Open
9 Sep 2026 Approval to enact permitted extension to 0-19 Public Health Nursing Service contractMayor and Cabinet • Approved a three-year extension to the 0-19 Public Health Nursing Service contract from 1st April... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies