Mayor and Cabinet decided this item on Wednesday 10 September 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 14.
KEY DECISION
Mayor and Cabinet
Report title: Surrey Canal station update Date: September 2025
Key decision: Yes
Class: Part 1
Ward(s) affected: New Cross Gate
Contributors: Director of Inclusive Regeneration, Head of Legal Services, Director of Finance
Outline and recommendations This paper provides an update on the current status of the Surrey Canal station project and Renewal’s New Bermondsey masterplan. It sets out a direction of travel for the proposed next steps to progress delivery of the station.
It is recommended that Mayor and Cabinet:
• Note the current progress on the Surrey Canal station
• Approve the use of Strategic Community Infrastructure Levy (SCIL) to support the delivery of Surrey Canal station and delegating authority to the Executive Director of Place to approve allocations of SCIL as set out in Part 2 of the Report.
• Delegate authority to the Executive Director of Place in consultation with the Director of Law and Corporate Governance to enter into such agreements as are necessary to give effect to the recommendations in this report. Timeline of engagement and decision-making 10 October 2019 – Termination of Conditional Land Sale Agreement - Mayor & Cabinet resolved to terminate the Conditional Land Sale Agreement with Renewal Group Limited, conditional upon adoption of the Surrey Canal Triangle SPD.
30 October 2019 – Approval of Draft SPD for Consultation - Mayor & Cabinet approved the draft Surrey Canal Triangle Design Framework SPD for public consultation, taking into account comments from the Sustainable Development Select Committee (28 October 2019).
January 2022 – Strategic Planning Committee resolved to grant planning permission for the New Bermondsey hybrid application (DC/20/119706).
12 October 2023 – Strategic Planning Committee resolve to approve redevelopment of Apollo Business Centre, including £958,518 contribution towards Surrey Canal Station
31 July 2024 – Strategic Planning Committee reaffirmed approval for New Bermondsey hybrid application with updated Section 106 terms, including a £25m contribution toward Surrey Canal Station (DC/20/119706).
1. Summary 1.1. Surrey Canal station is a proposed new station on the Windrush Line between Surrey Quays station and Queens Road Peckham station. The new Surrey Canal station will directly support the proposed New Bermondsey development (3,500 new homes) and will indirectly support the delivery of over 4,000 new homes in Lewisham and Southwark. The station will significantly improve transport connectivity in the area, including the Winslade Estate (currently PTAL 1a to 2), which has significant levels of deprivation. 1.2. The station at Surrey Canal will also be step-free from ground to platform level which will enable many more passengers to access rail travel. Reduced walking/cycle times to the station for existing residents and businesses is expected to reduce car usage resulting in better air quality. 1.3. Passive provision for the station was delivered when the Overground was extended in the early 2010s. The Greater London Authority (GLA) and Transport for London (TfL) secured Housing Infrastructure Fund (HIF) grant to deliver the station but due to significant budget pressures across the programme caused by cost inflationary pressures the East London Line
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Surrey Canal Station Update: Part 1 v.FINALReport | 12 pages | DownloadRead as text |
PDF |
Surrey Canal Station UpdateReport | 1 pages | Download |
Follow Mayor and Cabinet at Lewisham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | MinutesThe minutes of the Mayor and Cabinet meeting held on 1 July 2026 were agreed as a correct record. | Agreed | Open |
| 9 Sep 2026 | Matters Raised by Scrutiny and other Constitutional BodiesThere were no matters raised by scrutiny or other constitutional bodies for consideration at the meeting. | Decided | Open |
| 9 Sep 2026 | Smoke Control Area: Whole Borough DesignationMayor and Cabinet • Approved the commencement of the statutory process to revoke the existing Smoke Control Orders fo... | Approved | Open |
| 9 Sep 2026 | Treasury Management Mid-Year Review 2026/27Mayor and Cabinet • Approved and recommended that Council approves the Treasury Management Outturn report for 2025/26... | Approved | Open |
| 9 Sep 2026 | Approval to enact permitted extension to 0-19 Public Health Nursing Service contractMayor and Cabinet • Approved a three-year extension to the 0-19 Public Health Nursing Service contract from 1st April... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.