Mayor and Cabinet, Wednesday 25 February 2026 at 6.00pm

School Minor Works Programme 2026: approval to procure and budget allocation

Approved Executive 2 papers

AI summaryLewisham Mayor and Cabinet approved the School Minor Works Programme 2026 at an estimated cost of £4,156,300, covering repairs and replacements across community schools, subject to receipt of the Department for Education grant.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedProgramme, procurement, budget, and delegations
Money£4,156,300Subject to receipt of the School Condition Allocation
What happens nextFinalise programme and select contractorsDelegated to the Executive Director for Children and Young People
Who it affectsCommunity schools in multiple Lewisham wardsPupils, staff and school visitors across all wards

What was decided

Mayor and Cabinet approved the draft programme of works for the School Minor Works Programme 2026 and the procurement and award of contracts at a total estimated cost of £4,156,300, subject to receipt of the School Condition Allocation 2026/27. Report P13

Authority was delegated to the Executive Director for Children and Young People, in consultation with the Director of Law and Corporate Governance and the Director of Inclusive Regeneration, to agree the final programme of works and to select preferred contractors and the final form of contracts. Report P13

The overall budget for the School Minor Works Programme 2026 was approved as set out in section 9 of the report. Report P13

Why

The Council has a duty to ensure school accommodation is suitable, in good condition and safe for pupils, staff and visitors, including under the Health and Safety at Work Act 1974. Report P14

The annual programme is funded by the Department for Education through the School Condition Allocation and uses building condition surveys and school bids to target essential capital works such as roof and heating system replacements. Report P15, P16, P12

Works were prioritised where estimated value exceeded £50,000, where there was a significant health and safety risk, or where there would be a substantial impact on the operation of a school. Report 5.6

What happens next

The Executive Director for Children and Young People will finalise the programme of works and select preferred contractors under delegated authority, with a separate report to be prepared to seek authority to select preferred contractors in line with the Council's procurement rules. Report P13, P51

Construction works will be procured through a below threshold tender process with a minimum of four contractors via the London Tenders Portal, evaluated on a 45:55 price/quality basis with a 10 percent Social Value weighting. Report P51

The Department for Education is expected to announce the School Condition Allocation for 2026/27 in April 2026, and the programme may need to be re-assessed if the grant differs significantly from the anticipated circa £4m, with any changes brought back to Mayor and Cabinet. Report P54, P56

The money

  • £4,156,300 Total budget proposed for the SMWP 2026 Report P56
  • £4,067,800 SCA funding assumed for the programme Report P56
  • £93,500 Contributions from schools, up to £5,000 per school Report P56
  • circa £4m Expected School Condition Allocation from the Department for Education for 2026/27 Report P54, P56
  • £1.195m Public Sector Decarbonisation Scheme funding approved in May 2025 for four decarbonisation projects Report P55
  • £50k Threshold above which works were considered for the School Minor Works Programme Report 5.6, P53

Options considered

  • Chosen: Below threshold tender with a minimum of four contractors via the London Tenders Portal. The Council lacks the skills and capacity to deliver building works in-house, and this approach reflects the nature and scale of the programme Report P51
  • Rejected: Use of frameworks such as the London Construction Programme. Previous use produced uncompetitive prices and a low number of responses Report P51
  • Rejected: In-house delivery of construction works. Setting up the required infrastructure does not represent good commercial or practical sense given the nature and scale of works Report P51

Implications

  • Financial: If the School Condition Allocation received is significantly less than the expected circa £4m, the programme will have to be re-assessed and any changes brought back to Mayor and Cabinet. Report P56
  • Legal: Each procurement must comply with Procurement Legislation and the Council's Contract Procedure Rules, with each contract approved in advance by Legal Services. Report P57
  • Equalities: The services will benefit all pupils and staff in the schools, and no individual or group will be disadvantaged. Report P59
  • Climate: The programme will improve energy efficiency by upgrading boilers, improving insulation and installing LED lighting, supporting the Council's aim for Lewisham to be carbon neutral by 2030. Report P60
  • Risk: Key risks include unforeseen issues inherent in refurbishment works, disruption to staff and students, and the discovery of asbestos, mitigated through contingencies, scheduling outside school hours, and refurbishment and demolition surveys. Report P58
  • Staffing: Successful contractors will be expected to meet London Living Wage requirements and submit a Social Value Action Plan. Report P63
  • Other: The programme will help improve the health and wellbeing of staff and children by creating a safer environment and better functioning facilities. Report P62

Who and where

  • Community schools across the wards of Bellingham, Brockley, Crofton Park, Downham, Evelyn, Forest Hill, Grove Park, Hither Green, Lee Green, Perry Vale, Rushey Green and Telegraph Hill Report P6
  • Pupils, staff and visitors at the schools receiving works, including Abbey Manor College, Baring, Brindishe Manor, Chelwood, Clyde Nursery, Deptford Park, Drumbeat Brockley, Elfrida, Fairlawn, Greenvale, Haseltine, Holbeach, Horniman, Kilmorie, Launcelot, Oak Gardens, Lucas Vale, Rangefield, Stillness Infants, Stillness Juniors, Perrymount, Prendergast Ladywell, Forest Hill and Sandhurst Report P18, P19, P20, P21, P22, P23, P24, P25, P26, P27, P28, P29, P30, P31, P32, P33, P34, P35, P36, P37, P41, P42
  • Multi-Academy Trusts and larger Voluntary Aided school bodies, which receive the School Condition Allocation directly Report P15

Timeline

  • November 2024: Four Public Sector Decarbonisation Scheme funding applications submitted Report P15
  • May 2025: Four Public Sector Decarbonisation Scheme applications approved, totalling £1.195m for decarbonisation works Report P55, P15
  • November 2025 to January 2026: School surveys carried out to inform the programme Report P11
  • 25 February 2026: Mayor and Cabinet decision on the School Minor Works Programme 2026 Report P3
  • April 2026: Expected announcement of the School Condition Allocation for 2026/27 Report P54
  • Summer 2026: New round of building condition surveys due to be conducted by McBains Report P16
  • 2027 and 2028: Public Sector Decarbonisation Scheme works to be delivered as part of SMWP27 and SMWP28, with some preliminary building fabric works taking place in 2026 as part of SMWP26 Report P55, P15

Plain English for the jargon

  • SCA: School Condition Allocation, a grant funded by the Department for Education
  • SMWP: School Minor Works Programme
  • PSDS: Public Sector Decarbonisation Scheme
  • ASHP: Air Source Heat Pump, which transfers heat from outside air to water for radiators, underfloor heating or hot water
  • RAAC: Reinforced Autoclaved Aerated Concrete, a lightweight form of concrete used in UK buildings from the mid 1950s to mid 1980s, less durable than traditional concrete
  • Principal Designer: An organisation or individual appointed by the client to lead on health and safety during the pre-construction phase under the Construction Design and Management Regulations 2015
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

Mayor and Cabinet • Approved the draft programme of works for the School Minor Works Programme 2026 (SMWP26) as set out in section 5. • Approved the procurement and award of contracts as set out in section 5 at a total estimated cost of £4,156,300 to deliver the School Minor Works Programme 2026 subject to receipt of the School Condition Allocation (SCA) 2026/27. • Delegated authority to the Executive Director for Children & Young People (in consultation with the Director of Law and Corporate Governance and the Director of Inclusive Regeneration) to agree the final programme of works for the School Minor Works Programme 2026 (SMWP26). • Delegated authority to the Executive Director for Children & Young People (in consultation with the Director of Law and Corporate Governance and the Director of Inclusive Regeneration) to select the preferred contractors and agree final form of contracts to deliver the SMWP26. • Approved the overall budget for the SMWP26 as set out in section 9.
Word for word from the decision Lewisham published for this meeting. Source: councilmeetings.lewisham.gov.uk

Follow this further

Built from Lewisham's papers

What the report saysPro

Report to Mayor and Cabinet

KEY DECISION

Mayor and Cabinet

Report title: School Minor Works Programme 2026: approval to procure and budget allocation. Date: 25 February 2026

Key decision: Yes

Class: Part 1

Ward(s) affected: Bellingham, Brockley, Crofton Park, Downham, Evelyn, Forest Hill, Grove Park, Hither Green, Lee Green, Perry Vale, Rushey Green, Telegraph Hill.

Contributors: Acting Group Finance Manager, Director of Law, Governance and Elections, Procurement and Commercial Services Manager and SGM Capital Programme Delivery

Outline and recommendations • Approve the draft programme of works for the School Minor Works Programme 2026 (SMWP26). • Approve the procurement of contractors and the award of contracts to deliver the School Minor Works Programme (SMWP) 2026 subject to the receipt of the School Condition Allocation (SCA) 2026/27.

• Delegate authority to the Executive Director for Children & Young People (in consultation with the Director of Law and Corporate Governance and the Director of Inclusive Regeneration) to agree the final programme of works for the School Minor Works Programme 2026 (SMWP26).

• Delegate authority to the Executive Director for Children & Young People (in consultation with the Director of Law and Corporate Governance and the Director of Inclusive Regeneration) to select the preferred contractors and agree final form of contracts to deliver the SMWP26.

• Approve the overall budget for the SMWP26 as set out in the recommendations below. Timeline of engagement and decision-making School surveys carried out between November 2025 and January 2026

1. Summary 1.1. The purpose of this report is to seek approval from Mayor and Cabinet to agree the programme of works and procure capital works contracts to deliver the School Minor Works Programme (SMWP) 2026. 1.2. The SMWP is an annual capital repair and replacement programme of works funded by the School Condition Allocation grant from the Department for Education.

2. Recommendations: 2.1. Mayor and Cabinet are recommended to: 2.2. Approve the draft programme of works for the School Minor Works Programme 2026 (SMWP26) as set out in section 5. 2.3. Approve the procurement and award of contracts as set out in section 5 at a total estimated cost of £4,156,300 to deliver the School Minor Works Programme 2026 subject to receipt of the School Condition Allocation (SCA) 2026/27. 2.4. Delegate authority to the Executive Director for Children & Young People (in consultation with the Director of Law and Corporate Governance and the Director of Inclusive Regeneration) to agree the final programme of works for the School Minor Works Programme 2026 (SMWP26). 2.5. Delegate authority to the Executive Director for Children & Young People (in consultation with the Director of Law and Corporate Governance and the Director of Inclusive Regeneration) to select the preferred contractors and agree final forms of contract to deliver the School Minor Works Programme 2026. 2.6. Approve the overall budget for the SMWP26 as set out in section 9.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
School Minor Works Programme 2026 approval to procure and budget allocation Part 1 REPORTReport 237 KB DownloadRead as text
PDF
School Minor Works Programme 2026: approval to procure and budget allocationReport 166 KB Download

At this meeting

Whole meeting

Who was there

7 of 13 attended
MB
Mayor Brenda DacresChair, apologies
LK
Councillor Louise KrupskiVice-Chair, present
PB
Councillor Paul BellCommittee Member, present
WC
Councillor Will CooperCommittee Member, present
AD
Councillor Amanda De RykCommittee Member, apologies
EE
Councillor Ese ErherieneCommittee Member, present
EH
Councillor Edison HuynhCommittee Member, present
OO
Councillor Oana Olaru-HolmesCommittee Member, present
SS
Councillor Sakina SheikhCommittee Member, apologies
JW
Councillor James-J WalshCommittee Member, present
JD
Jennifer DaothongOfficer, in attendance
JS
Jacob SakilOfficer, in attendance

All 13 on the meeting page

On this subject at Lewisham

Search all
  1. School Minor Works Programme 2026: approval to procure and budget allocationThis decision
  2. School Minor Works Programme 2025Decided
  3. School Minor Works Programme - approval to procure PART 1Approved
  4. School Minor Works Programme 2022 (part 1)Agreed
  5. Contract Award-School Minor Works Programme Consultant (part 1)Agreed
  6. Schools Minor Works Programme 2021 - 2025 (part 1)Agreed

More from Lewisham Mayor and Cabinet

All decisions
MeetingDecisionOutcome
9 Sep 2026 MinutesThe minutes of the Mayor and Cabinet meeting held on 1 July 2026 were agreed as a correct record. Agreed Open
9 Sep 2026 Matters Raised by Scrutiny and other Constitutional BodiesThere were no matters raised by scrutiny or other constitutional bodies for consideration at the meeting. Decided Open
9 Sep 2026 Smoke Control Area: Whole Borough DesignationMayor and Cabinet • Approved the commencement of the statutory process to revoke the existing Smoke Control Orders fo... Approved Open
9 Sep 2026 Treasury Management Mid-Year Review 2026/27Mayor and Cabinet • Approved and recommended that Council approves the Treasury Management Outturn report for 2025/26... Approved Open
9 Sep 2026 Approval to enact permitted extension to 0-19 Public Health Nursing Service contractMayor and Cabinet • Approved a three-year extension to the 0-19 Public Health Nursing Service contract from 1st April... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies