London Borough of Lewisham
Housing Select Committee, Thursday 5 March 2026 at 7.00pm

Major works and stock condition

Noted Committee 1 paper

AI summaryLewisham Housing Select Committee noted a report on the major works programme for c20,000 council homes, with the HRA capital programme set at £329m over five years from 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted the major works and stock condition report
Money£329m over 5 yearsHRA capital programme from 2026/27, per Mayor & Cabinet budget report
What happens nextSIAM team expansionAsset management team growth during 2026/2027 financial year
Who it affectsCouncil tenants and leaseholdersc13,900 rented and c6,100 leasehold homes in the HRA

What was decided

The committee noted the report on major works, stock condition, decency progress, capital investment, and service priorities for the Housing Revenue Account. Report 2.1

The committee accepted that the HRA capital programme will total £329m over five years from 2026/27 and that over £65m per year is likely needed going forward. Report 6.4

Why

The Council has been subject to a regulatory notice from the Regulator of Social Housing since March 2024 due to failures in responsive repairs, fire remedial actions and non-decency, and the major works programme addresses two of those areas. Report 1.4

A stock condition survey by Savills found 26% of tenanted homes were non-decent, and the service is targeting fewer than 10% non-decent homes by April 2027 and below 5% by April 2028. Report 4.7, 4.11

New legislation including Awaab's Law, the Building Safety Act 2022, Decent Homes 2 (2035), MEES (2030 and 2039) and the Carbon Net Zero 2050 target is reshaping landlord duties and costs. Report 1.5, 1.6

What happens next

An Asset Management Framework will be considered against corporate priorities in 2026 and then presented to Mayor and Cabinet to guide investment planning. Report 4.16

The service will grow SIAM capacity, introduce a new asset management ICT system in summer 2025, expand the supply chain, and pursue Building Safety Regulator Gateway 2 approvals. Report 5.1, 4.27

All HRA stock will be managed in house from June 2027 when the Brockley PFI contract ends. Report 1.1

The money

  • £329m Total HRA capital programme over five years from 2026/27, per the Mayor & Cabinet budget report of February 2026 Report 6.4
  • £55m Average annual HRA capital investment over the past five years
  • £65m Minimum annual investment likely required going forward to meet decency and other regulatory requirements
  • 11.1% Peak construction industry inflation in October 2022 cited as a cost pressure on major works Report 1.5

Options considered

  • Chosen: Note the report (as recommended). Officers recommended noting and commenting on the report's content Report 2.1
  • Rejected: Disposal of a small number of properties considered economically unviable. Not adopted in this decision; remains an option subject to a business case and appropriate approvals Report 4.18

Implications

  • Financial: SIAM is resourced from the ringfenced HRA funded by rents and service charges, and finite resources must be prioritised from statutory compliance to discretionary investment. Report 1.1, 4.16
  • Legal: The Council must meet statutory duties as a social landlord under Awaab's Law, the Building Safety Act 2022, HHSRS and the Decent Homes Standard. Report 1.5, 1.6, 7.1
  • Equalities: Council tenants include a higher than average proportion of older people and black and minority ethnic communities; decency and regulatory standards apply to all tenanted properties. Report 8.1
  • Climate: The service is working towards EPC C by 2030 and Carbon Net Zero by 2050 through ventilation, affordable heating and insulation investment. Report 9.1, 9.2, 1.6
  • Risk: A regulatory notice from the Regulator of Social Housing has applied since March 2024 covering responsive repairs, fire remedial actions and non-decency; the service aims to have it lifted with a C1 rating. Report 1.4, 5.1
  • Other: Crime and disorder implications are not specific to the report, though door entry systems help prevent anti-social behaviour, especially for older residents. Report 10.1

Who and where

  • Council tenants in c13,900 rented homes Report 1.1
  • c6,100 leaseholders responsible for S20 contributions on major works Report 1.1, 4.21
  • Residents of Brockley PFI properties (2,000 rented and leasehold homes) transferring in-house from June 2027 Report 1.1
  • Small number of shared ownership residents Report 1.1

Timeline

  • March 2024: Council became subject to a regulatory notice from the Regulator of Social Housing Report 1.4
  • Summer 2025: New asset management ICT system introduction planned Report 5.1
  • 2025: Awaab's Law commencement for damp and mould Report 1.6
  • May 2024 to March 2025: Stock condition survey carried out by Savills, accessing 86% of council rented homes and all blocks of flats
  • February 2026: Category 1 HHSRS hazards reduced to 97 Report 4.8
  • February 2026: Mayor & Cabinet budget report for 2026/27 published, setting out the £329m five-year HRA capital allocation Report 6.4
  • 1st April 2026: 17.3% of homes recorded as non-decent Report 4.10
  • 1st November 2026: 11.1% of homes recorded as non-decent Report 4.10
  • 2026/2027: SIAM asset management team recruitment and embedding to take place Report 4.15
  • 2026 and 2027: Awaab's Law statutory timescales progressively introduced for most other HHSRS hazards Report 1.6
  • April 2027: Target of fewer than 10% non-decent homes Report 4.11
  • June 2027: Brockley PFI contract ends; all HRA stock managed in house Report 1.1
  • April 2028: Target of below 5% non-decent homes Report 4.11
  • 2030: EPC C and MEES energy efficiency target Report 1.6, 9.1
  • 2035: Decent Homes 2 target Report 1.6
  • 2039: Further MEES milestone Report 1.6
  • 2050: Carbon Net Zero target Report 1.6

Plain English for the jargon

  • HRA: Housing Revenue Account, a ringfenced council account funded mainly by rents and service charges
  • SIAM: Stock Investment and Asset Management Service within the Housing directorate
  • PFI: Private Finance Initiative, here the Brockley PFI managing 2,000 properties until June 2027
  • HHSRS: Housing Health and Safety Rating System, the statutory safety standard for housing
  • MEES: Minimum Energy Efficiency Standards, with targets in 2030 and 2039
  • HRB: Higher Risk Building under the Building Safety Act 2022
  • S20: Section 20 consultation and contribution process for leaseholders facing major works
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

that the report be noted.
Word for word from the decision Lewisham published for this meeting. Source: councilmeetings.lewisham.gov.uk

Follow this further

Built from Lewisham's papers

What the report saysPro

Report to Housing Select Committee

Summary

1.1The Council has c20,000 homes, with both the income and expenditure being located in the Housing Revenue Account (HRA) of the Council. The HRA is a ringfenced account of the Council funded primarily by rents and service charges. These homes are made up of c13,900 rented homes and c6,100 leasehold properties. The service manages a small number of shared ownership properties. The Council’s housing service manages c18,000 of these properties, with the Brockley Private Finance Initiative (PFI) managing 2,000 rented and leaseholder properties. All the Council’s HRA stock will be managed in house from June 2027 when the PFI contract ends.

1.2The Council must ensure its homes are compliant with legislation and the Council’s own policy standards. To achieve this, we must deliver effective repairs and maintenance, health and safety compliance and major works services. The major works service ensures that components in residential buildings are replaced as they reach the end of the component’s life and that components meet ever higher standards of building safety, compliance, decency and thermal comfort.

1.3This report focuses on the service provided by the Stock Investment and Asset Management Service (SIAM) which sits in the Quality & Investment area of the Housing directorate. SIAM is responsible for understanding the needs of the Council’s HRA stock, designing and delivering annual, 5-year and 30-year priorities to optimise investment in Council owned homes. It seeks to ensure decent, safe and regulatory compliant homes for our tenants and leaseholders.

1.4Since March 2024 the Council has been subject to a regulatory notice from the Regulator of Social Housing due to service failures in 3 key areas which are responsive repairs, fire remedial actions and non-decency. In all 3 areas the Council has made progress to improve services with the aim of resolving service failure and to allow the notice to be lifted. The major works programme has a critical role in two of the three areas.

1.5Social landlords have responded to significant changes in legislation over recent years and a new economic environment. Legislative change includes Awaab’s Law, 2030 energy efficiency target, Building Safety Act 2022 and the Consumer Standards. All social landlords are under scrutiny from the Regulator of Social Housing, the Building Safety Regulator and the Housing Ombudsman Service, as well as scrutiny and potential direct legal action by residents. The economic environment has changed with significant inflation in the construction industry peaking in October 2022 at 11.1%. In addition to inflation, the shortage of construction and specialist skills such as fire and building safety engineers, Principal Designers, etc; has increased the cost of major works and also the timescales to plan and design programmes of work.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Major works and stock conditionReport 226 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 16 attended
SP
Councillor Stephen PenfoldChair, present
DA
Councillor Dawn AtkinsonVice-Chair, present
YA
Councillor Yemisi AnifowoseCommittee Member, apologies
PD
Councillor Pauline DallCommittee Member, present
LJ
Councillor Liz Johnston-FranklinCommittee Member, present
BH
Councillor Billy HardingCommittee Member, present
LS
Councillor Liam ShrivastavaCommittee Member, present
AN
Abbygirl NnadiPublic, apologies
KP
Katie PritchardPublic, in attendance, virtual
TR
Theresa ReidPublic, in attendance
WC
Councillor Will CooperCommittee Member, in attendance
PD
Patrick DubeckOfficer, in attendance

All 16 on the meeting page

On this subject at Lewisham

Search all
  1. Major works and stock conditionThis decision
  2. Leaseholder Major Works Payment Options ReviewAgreed
  3. Extension of Term Contract for Major Works in HousingApproved

More from Lewisham Housing Select Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Apologies for absenceApologies received from Councillor El Fry and Councillor Robin McGhee Councillor James Rathbone attended as substitut... Decided Open
2 Sep 2026 Declarations of interestNo interest was declared. Decided Open
2 Sep 2026 Minutes of previous meetingRESOLVED that the minutes of the meeting of the Housing Select Committee held on 17 June 2026 be confirmed and signed... Decided Open
2 Sep 2026 Compliance with Awaab’s Law Phase 1 and Preparation for Phase 21, That the report outlining the implementation of Awaab's Law Phase 1 and preparation for Phase 2, the Council's cur... Noted Open
2 Sep 2026 Learning from Complaints 2025/261, That the report be noted. 2, That consideration be given to increasing the use of in-person complaints handling tr... Noted Open