AI summaryLewisham Housing Select Committee noted the John Smythe Court update, expressing concern over delays to the 39-home over-55s scheme and recording support for officers.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee also placed on record support for officers
Moneycirca £10m contract sumBuild contract with Guildmore Limited
What happens nextTarget completion March/April 2026Subject to contractor finishing outstanding works
Who it affectsAllocated residents and homeless householdsMost are over 55s, several aged 70 or over
What was decided
The Committee noted the report on John Smythe Court. Report P6
The Committee expressed concern about the delays and the way the project has progressed.
The Committee placed on record its support for officers and recognised the work being done.
Why
Completion was originally forecast for May 2023 but the project is delayed by nearly two years, with most works around 90% complete and outstanding items still to resolve. Report 3.2, 3.3, 4.5, 4.6
Causes included the discovery of Virgin Media cables under the building footprint and broader construction industry pressures from Brexit and Covid, with protracted commercial negotiations until October 2024. Report 4.2, 4.3, P13, P14
Four homeless households allocated to the scheme have remained in temporary accommodation during the delay, and other residents have been unable to progress planned moves. Report 3.5
What happens next
The Council will continue to drive the contractor to deliver as soon as possible, while ensuring quality and resident safety. Report 7.2, P27
Officers will keep allocated households informed, manage expectations and update their records. Report 5.3
Financial impact details are set out in Part 2 of the report. Report P26
The money
circa £10m Build contract sum with Guildmore Limited for John Smythe Court Report 3.2
Implications
Legal: The contract is a JCT Design and Build agreement, allowing the Council to issue rectification notices, withhold retention and seek damages for contractor breaches. Report P20, 4.8, P22
Financial: Full financial impact is covered in Part 2 of the report, not included in Part 1. Report P26
Risk: Brexit, Covid, build cost inflation and supply scarcity have increased contractor insolvency risk across the industry. Report P13, P14
Other: The matched cohort is over 55s, several aged 70 or over, leading to increased enquiries, correspondence and complaints. Report 5.2
Who and where
35 households allocated in March 2024 under standard Housing Allocation Policy routes Report 1.4, 3.4
4 homeless households still in temporary accommodation due to the delay Report 3.5
Applicants for the 4 wheelchair-accessible units, not yet advertised Report 1.4, 3.4
October 2020: Build contract entered into with Guildmore Limited Report 1.3, 3.2
June 2021: Phase 1 (demolition of garages and ball court relocation) completed Report 3.2
October 2021: Phase 2 construction of 39 flats commenced Report 3.2
23 May 2023: Original completion date forecast Report 3.2, 4.2
March 2024: 35 homes allocated through Housing Allocation Policy Report 1.4, 3.4
October 2024: Virgin Media cable diversion resolved after protracted negotiations Report 4.2
November 2024: Contractor provided revised completion programme citing February 2025 Report 4.3
end of March/early April 2026: Current target for completion of all outstanding matters Report 1.5, 3.3, 4.6
Plain English for the jargon
Building for Lewisham (BfL): The Council's new build housing programme launched in 2018 to deliver new affordable homes.
JCT D&B: Joint Contracts Tribunal Design and Build contract, the form of contract used for the build.
Bampton Estate: The location on which the John Smythe Court development is being built.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6
Resolved
that the report be noted; that the Committee express concern about the delays and the way in which the project has progressed to date; and that the Committee place on record its support for officers and its recognition of the work being undertaken to bring the scheme to a successful conclusion. that the report be noted; that the Committee express concern about the delays and the way in which the project has progressed to date; and that the Committee place on record its support for officers and its recognition of the work being undertaken to bring the scheme to a successful conclusion.
Word for word from the decision Lewisham published for this meeting.Source: councilmeetings.lewisham.gov.uk
1.1An ambitious new build development programme, the Building for Lewisham Programme (BfL), was launched in 2018 and successfully contributed to the 2018- 2022 manifesto target of 1000 new social homes. It now contributes to the current manifesto 2022 - 2026 target of 800 new affordable homes in Borough. The approved programme has a total of 218 homes that are in design development or being prepared for planning submission. This is in addition to 644 homes that are either on site or recently completed.
1.2John Smythe Court, Bampton Estate, which forms part of the BfL programme, comprises 39 one-bedroom homes, including four wheelchair-accessible units.
1.3The Council entered into a build contract with Guildmore Limited in October 2020 with a completion date of May 2023.
1.4Of the 39 homes, 35 were allocated in March 2024 through standard Housing Allocation Policy routes. The four wheelchair-accessible units were not advertised at that time and, therefore, sit outside the original advertised match dataset.
1.5The projects delivery has been delayed, and the contractor is targeting the end of March/April 2026.
2 Recommendations 2.1 Housing Select Committee are asked to note the update on the Building for Lewisham development at John Smythe Court, Bampton Estate
Is this report easy to understand? Please give us feedback so we can improve. Go to https://lewisham.gov.uk/contact-us/send-us-feedback-on-our-reports 3 Background 3.1 John Smythe Court, Bampton Estate received planning consent in November 2019 (DC/19/112918) for the demolition of seven garages at Bampton Estate, to allow for the construction of 39 Flats for over 55’s and associated landscaping, with the relocation of the ball court on Windrush Lane.
3.2The Council entered into a build contract with Guildmore Limited in October 2020 for a contract sum of circa £10m. The contract was in 2 phases: Phase 1 was the demolition of the existing garages and relocation of the ball court and associated landscaping. These works completed in June 2021. Phase 2 works, the construction of the residential element, started in October 2021 with an originally forecasted completion date of May 2023.
3.3The project is delayed, and the likely completion date is the end of March/early April 2026. This is dependent on the contractor’s ability to complete the works to specified contractual and statuary standards.
3.4Of the 39 homes, 35 were allocated in March 2024 through standard Housing Allocation Policy routes. The four wheelchair-accessible units were not advertised at that time and therefore sat outside the original advertised match dataset. The properties were allocated as detailed below: Number of Rehousing Reason Households Welfare for Older People 25 Homeless 4 Medical Priority 2 Under-occupiers 2 Supported Housing Move-On 1 Management Discretion 1 Total 35
3.5As a result of the almost 2-year delay, 4 homeless households matched to John Smythe Court have remained in temporary accommodation, while others have been unable to progress planned moves or resolve identified housing needs.
4 Project Status
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Learning from Complaints 2025/261, That the report be noted. 2, That consideration be given to increasing the use of in-person complaints handling tr...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.